Transcript COC

Bond Construction Update
Citizen’s Oversight Committee
Long Beach Community College District
July 26, 2010
EDUCATE  ENGAGE  EMPOWER
1
Agenda

Current & Upcoming Construction Projects











LAC Building A, Student Services Retrofit
LAC Parking Structure
LAC Building O Complex
LAC Infrastructure Improvements Project and District Wide –
Energy Efficiency Project
LAC Building I (Bookstore)
PCC MDAB (Multi-Disciplinary Academic Building)
PCC Building CC Retrofit
District Wide – Electronic Signage Plan
LAC South Walkway Extension
LAC Building P FPP
Q&A
2
Current and Upcoming
Construction Projects
LAC Building A – Student Services Retrofit
Measure E 2008




Awaiting DSA Final approval on Structural portion
Adds 6,500 Sq. Ft. to existing building
Will house A&R, Counseling, Health Services, Cashier, Transfer Ctr., etc.
Estimated start of construction Fall 2010
3
Current and Upcoming
Construction Projects
LAC Parking Structure – Measure E 2008



Spaces for 900 Vehicles
Construction started Summer of 2010
Anticipated end of Construction Fall 2011
4
Current and Upcoming
Construction Projects
LAC Building O Complex – Measure E 2008



Two structures totaling 87,000
square feet
Construction of Building O1 began
April 2010
Anticipated completion October 2010
5
Current and Upcoming
Construction Projects
LAC Infrastructure Improvement Project and
District Wide Energy Efficiency Project
Measure E 2008







Project to be completed in a phased construction
schedule
Total annual estimated savings of 1.5 million Kwh
Project started Fall 2009; currently working on phase
5, 5A, & 6A
Landscaping upgrades to be implemented in
conjunction with infrastructure project phasing
Majority of existing building HVAC systems to be
upgraded and connected to the Central Plant
Exterior lighting and controls upgrades in progress
Anticipated end of construction Winter 2011
6
Current and Upcoming
Construction Projects
LAC Building I - Measure E 2008






Received Final DSA
approval
Adds additional 4,000
square feet to existing
building
Architecture to match
LAC Mediterranean
Theme
Going to bid in August
Construction
scheduled for Fall
2010
Bookstore Swing
Space relocation
beginning Summer
2010
7
Current and Upcoming
Construction Projects
PCC MDAB
(Multi-Disciplinary Academic Building) - Measure E 2002





Received Final State (DOF) approval
NTP to be issued on 7/29/10
Install portables for swing space Summer 2010
Anticipated start of MDAB construction Fall 2010
Project to be completed in two phases
8
Current and Upcoming
Construction Projects
PCC Building CC Retrofit - Measure E 2008





Currently in DSA for plan check (Structural)
Houses the Fitness Center, Gymnasium, Weight Room, and
Faculty and Staff Offices
Swing space to be located on PCC Campus (Bldg. GG)
To be completed concurrently with MDAB project phase 1
Anticipated end of construction 2012
9
Current and Upcoming
Construction Projects
District Wide – Electronic Signage Plan
Measure E 2008
 District Wide Signage Plan complete for LAC & PCC
 Daktronics digital signs currently in fabrication
 Anticipated construction completion of Marquee Signs
Fall 2010
10
liberal arts
Liberal Arts Campus
Site Plan
pacific coast
Pacific Coast Campus
Site Plan
QUESTIONS
&
ANSWERS
EDUCATE  ENGAGE  EMPOWER
13