Transcript COC

Bond Construction Update
Citizen’s Oversight Committee
Long Beach Community College District
July 21, 2008
BUILDING  TOMORROW  TODAY
1
Agenda


Completed Construction Projects
Current & Upcoming Construction Projects
 LAC South Quad Complex
 LAC Central Plant
 LAC Learning Resources Center
 LAC Building A, Student Services
 LAC Math Technology Building
 PCC Central Plant
 PCC Learning Resources Center
 PCC Industrial Tech Phase 1
 PCC MDAB (Multi-Disciplinary Academic Building)
 LAC/PCC Building Needs Assessment Project








Toilet Improvement Projects
Quick-Start Projects
ADA Projects
Lighting Projects
Classroom Improvement Projects
Infrastructure Projects
Facilities Improvements
Q&A
2
Current and Upcoming
Construction Projects
LAC Central Plant



Central Plant equipment,
Public Safety, & Field house
for Athletics
Installed (2) 600 ton Chillers
and (1) 300 ton chiller with
room for expansion
Installed 4 cooling towers with
additional expansion space
3
Current and Upcoming
Construction Projects
LAC Central Plant



Plant ready for operation and
awaiting completion of SQC
Construction 96% Complete
Completion Anticipated Summer
2008
4
Current and Upcoming
Construction Projects
LAC/Learning Resources Center



Construction 70%
Complete
Adds 10,000 ASF to
existing building
Substantial Completion
anticipated December
2008
5
Current and Upcoming
Construction Projects
South Quad Complex


Construction Approx. 62%
Complete
Space includes







Approx. 68,000 ASF
32 modern classrooms and labs
38 faculty offices
Executive office suites
Multipurpose room
State of the art Board Room
Substantial Completion
Anticipated December 2008
6
Current and Upcoming
Construction Projects
LAC Building A – Student Services Retrofit






Martinez Architects received Board Approval as the Architect of Record
Programming work began on April 10, 2008
Completed Schematic Design (June 2008)
Currently in Design Development phase
Adds 4000 ASF to existing building
Will house A&R, Counseling, Health Services, Cashier, Transfer Ctr., etc.
7
Current and Upcoming
Construction Projects
LAC Math Technology Building
 Marlene Imirzian & Associates Architects received
Board Approval as the Architect of Record
 Will house Math and Culinary Arts instructional
program as well as Reprographics
8
Current and Upcoming
Construction Projects
LAC Math Technology Building




Programming work began in May 2008
Completed Schematic Design (June 2008)
Currently in Design Development phase
FPP was approved by Board of Trustees and sent
to state
9
Current and Upcoming
Construction Projects
LAC Math Technology Building

Currently completing Design Development Phase
10
Current and Upcoming
Construction Projects
PCC Central Plant






Houses Central
Plant equipment
and Maintenance
and Operations
facility
Installed (3) 300
ton Chillers
Installed 3 cooling
towers
Will support LRC
Construction
Approximately 67%
Complete
Completion
Anticipated late
Summer 2008
11
Current and Upcoming
Construction Projects
PCC Learning Resources Center






Construction 97% Complete
Modern Facility with Computer Lab
and Multimedia
Stand alone Data Center. Provides
District IT redundancy
Bridge to Bldg. EE
Design elements move towards
energy efficiencies
Substantial Completion July 2008
12
Current and Upcoming
Construction Projects
PCC Industrial Technology Center Phase 1





Replaces Existing Antiquated
Structures
Construction is 25%
Complete
Modern Facility Houses
Machine Tool and Welding
Departments
New Northern Face of the
Campus
Completion Anticipated
Spring 2009
13
Current and Upcoming
Construction Projects
PCC Multi-Disciplinary Academic Building (MDAB)





Programming is completed and submitted to the State for Approval
Completed Schematic Design and Design Development phase (June 2008)
Currently working on Construction Documents and Furniture Layouts
Anticipated start of construction Summer 2009
14
Completed in Two phases
pacific coast
PCC - LRC and MDAB (Fly-By)
15
Current and Upcoming
Construction Projects
LAC/PCC Building Needs Assessment Project



Restroom Improvement
Projects
Quick-Start Projects
ADA Projects
16
Current and Upcoming
Construction Projects
LAC/PCC Building Needs Assessment Project



Lighting Projects
Classroom Improvement Projects
Infrastructure Projects
17
Recently Completed
Facilities Improvements
Long Beach Community
College District
18
Facilities Improvements
LBCC
Building “D” Planetarium Improvements

With the help of LBCC Foundation,
funds were available to do the
following:







carpet replacement
carpet added to the walls to
ensure light-control for
observational needs.
AC unit independent from the
building HVAC system was added
to serve the server room, for
proper load ventilation.
New observation seats were
installed.
entire room painted
new lighting installed.
Completed 06/2008
19
Facilities Improvements
LBCC
Building “J” Boiler Replacement



Replace existing boilers, pumps,
expansion tanks and common flue
with new equipment.
A newly upgraded design
reflecting a mechanical
engineered system was installed
improving the efficiency of the
boilers. This system is the main
heating source serving the
Auditorium.
Completed 06/2008
20
Facilities Improvements
LBCC
Building “B”, “C”, and “D” Roof Replacement



Replacement of roofs with a 30year Garland roof materials
Removal of radio tower on Bldg
“B”
Expected Completion 07/2008
21
Facilities Improvements
LBCC
ERD Tenant Improvements and Relocation





Economic Resource Development
Complete build out of two-hard
walled offices, a kitchenette, and
a server room
Relocation of a 4,000sq. ft. office
space into the newly re-designed
3,000sq ft. office space
New modular cubicle work stations
were adapted and installed
Completed 05/2008
22
Facilities Improvements
LBCC
Important Ongoing Initiatives












Building Needs Assessment Project
Parking Structure/Traffic Study
Master Landscape Project
District Wide Energy Efficiency Improvements
Electronic Signage
Wayfaring and Building Signage
Facilities Website
Facilities Work Order System
Buildings M & N Replacement at LAC
Building G at PCC
Modernization of Building P at LAC (IPP)
Replacement of Building M (Construction Trades) at PCC
(IPP)
23
QUESTIONS &
ANSWERS
BUILDING  TOMORROW  TODAY
24