Transcript COC

Bond Construction Update
Citizen’s Oversight Committee
Long Beach Community College District
October 2008
EDUCATE  ENGAGE  EMPOWER
1
Agenda


Completed Construction Projects
 PCC Learning Resource Center
Current & Upcoming Construction Projects
 LAC Central Plant
 LAC South Quad Complex
 LAC Learning Resource Center
 LAC Building A, Student Services Retrofit
 LAC Math Technology Building
 LAC Parking Structure
 LAC Infrastructure Improvements – Phase 3
 PCC Central Plant
 PCC Industrial Tech Phase 1
 PCC MDAB (Multi-Disciplinary Academic Building)
 PCC Building C Retrofit
 District Wide Building Needs Assessment Projects






Q&A
Toilet Improvement Projects
Quick-Start Projects
ADA Projects
Lighting Projects
Classroom Improvement Projects
2
Completed Construction Projects
PCC Learning Resource Center – Measure E 2002






Construction Complete
Modern Facility with Computer Lab
and Multimedia
Stand alone Data Center. Provides
District IT redundancy
Bridge to building E
Design elements move towards
energy efficiencies
Ribbon cutting held 9/17/08
3
Current and Upcoming
Construction Projects
LAC Central Plant – Measure E 2002





Central Plant equipment, Public
Safety, & Field House for Athletics
Final FF&E installation underway
Plant ready for operation and awaiting
completion of LRC & SQC
Construction 99% Complete
Anticipated startup 11/08
4
Current and Upcoming
Construction Projects
South Quad Complex – Measure E 2002


Construction approx. 86%
Complete
Space includes







Approx. 68,000 ASF
32 modern classrooms and labs
38 faculty offices
Executive office suites
Multipurpose room
State of the art Board Room
Substantial completion
anticipated December 2008
5
Current and Upcoming
Construction Projects
LAC/Learning Resource Center – Measure E 2002



Construction 89% Complete
Adds 10,000 ASF to existing
building
Substantial Completion
Anticipated December 2008
6
Current and Upcoming
Construction Projects
LAC Building A – Student Services Retrofit
Measure E 2008



Design Development to be submitted this month
Adds 4,000 ASF to existing building
Will house A&R, Counseling, Health Services, Cashier, Transfer Ctr., etc.
7
Current and Upcoming
Construction Projects
LAC Math Technology Building – Measure E 2008
 Completed Schematic Design (June 2008)
 Currently in Design Development phase
 Will house Math and Culinary Arts instructional
program as well as Reprographics
 Estimated start of construction 2011
8
Current and Upcoming
Construction Projects
LAC Parking Structure – Measure E 2008
 Planning initiated for approximately 900 Vehicles
 To be procured under “Design Build Delivery”
method
 To be located Southeast corner of Lot J adjacent
to the Verizon building
 Photovoltaic Electrical Generation Array on top
level of structure
 Anticipated start of construction 2009
9
Current and Upcoming
Construction Projects
LAC Infrastructure Improvements – Phase 3
Measure E 2008





Planning underway with P2S
Engineering
Completes chilled water lines to
North side of campus
Includes other major utility
upgrades; RW,DW, Data, etc.
Existing building HVAC systems to
be upgraded in synch with
infrastructure improvements
Coordinated with modernization
and quick start projects
10
Current and Upcoming
Construction Projects
PCC Central Plant – Measure E 2002



Houses Central Plant
equipment and
Maintenance and
Operations facility
Construction
Approximately 99%
Complete
Currently provides
chilled water to the PCC
LRC
11
Current and Upcoming
Construction Projects
PCC Industrial Technology Center Phase 1
Measure E 2002





Modern facility houses
Machine Tool and Welding
Departments
Construction is 42%
complete
Replaces existing
antiquated structures
New Northern face of the
campus
Completion anticipated
summer 2009
12
Current and Upcoming
Construction Projects
PCC MDAB
(Multi-Disciplinary Academic Building) Measure E 2002




50% construction documents submitted
Swing space planning completed 9/2008, construction Spring 2009
Anticipated start of MDAB construction Summer 2009
To be completed in two phases
13
Current and Upcoming
Construction Projects
PCC Building C Retrofit - Measure E 2008
 To be designed by Hill Partnership Architects
 Houses the Fitness Center, Gymnasium, Weight
Room, and Faculty and Staff Offices
 Swing space to be located in PCC building V
 Anticipated start of construction Summer 2009
 To be completed concurrently with MDAB project
14
Current and Upcoming
Construction Projects
District Wide Building Needs Assessment Project
Measure E 2008



Toilet Improvement
Projects
Quick-Start Projects
ADA Projects
15
Current and Upcoming
Construction Projects
District Wide Building Needs Assessment Projects
Measure E 2008


Lighting Projects
Classroom Improvement Projects
16
QUESTIONS &
ANSWERS
EDUCATE  ENGAGE  EMPOWER
17