Transcript COC
Bond Construction Update
Citizen’s Oversight Committee
Long Beach Community College District
January 25, 2010
EDUCATE ENGAGE EMPOWER
1
Agenda
Completed Construction Projects
Current & Upcoming Construction Projects
LAC South Quad Complex
PCC Industrial Tech Phase 1
Los Coyotes Property Upgrades
Bldg. F - Conversions of rooms F104 and F106 to new classroom space.
Bldg. G and H - Repainting
LAC Building A, Student Services Retrofit
LAC Math Technology Building
LAC Parking Structure
LAC Building O Complex
LAC Infrastructure Improvements
LAC Q & R ADA/HVAC Upgrades
LAC Building I (Bookstore)
PCC MDAB (Multi-Disciplinary Academic Building)
PCC Building CC Retrofit
District Wide – Electronic Signage Plan
Upcoming Projects
Planned Phasing of Future Projects
Q&A
2
Completed
Construction Projects
South Quad Complex – Measure E 2002
Space includes
Approx. 68,000 ASF
32 modern classrooms and labs
38 faculty offices
Executive offices
Multipurpose room
State of the art Board Room
3
Completed
Construction Projects
PCC Industrial Technology Center Phase 1
Measure E 2002
Modern facility houses Welding
Department and other trade programs
Replaces existing antiquated structures
New Northern face of the campus
4
Current and Upcoming
Construction Projects
LAC Building A – Student Services Retrofit
Measure E 2008
Plans submitted to DSA September 2009
Adds 6,500 Sq. Ft. to existing building
Will house A&R, Counseling, Health Services, Cashier, Transfer Ctr., etc.
Estimated start of construction end of Fall 2010
5
Current and Upcoming
Construction Projects
LAC Math Technology Building – Measure E 2008
Completed Schematic Design
Will house Math and Culinary Arts instructional
program as well as Reprographics
Estimated start of construction Winter 2013
6
Current and Upcoming
Construction Projects
LAC Parking Structure – Measure E 2008
Spaces for 900 Vehicles
Photovoltaic Electrical Generation Array on top level
To be located Southeast corner of Lot J adjacent to the Verizon building
Outfitted with single-axis tracking system
Minimum 450 KW+ output
Curriculum building opportunity
Exhibit classroom
Groundbreaking anticipated February, 2010
7
Current and Upcoming
Construction Projects
LAC Building O Complex – Measure E 2008
Two structures totaling 87,000
square feet
Current Occupants:
Future Occupants:
ERD, Foundation, Warehouse
Facility, and one leasee
IITS and BMT
Potential rental spaces being
assessed
8
Current and Upcoming
Construction Projects
LAC Infrastructure Improvement Projects
Measure E 2008
Project to be completed in a
phased construction schedule
Total annual estimated savings
of 1.5 million Kwh
Project started Fall 2009.
Anticipated completion Summer
2011
Upgrades include; Reclaimed
Water, Domestic Water, Data,
etc.
Majority of existing building
HVAC systems to be connected
to new infrastructure
Landscaping upgrades to be
implemented in conjunction
with infrastructure project
phasing
9
Current and Upcoming
Construction Projects
LAC Q & R ADA/HVAC - Measure E 2008
Complete building ADA upgrade: includes restrooms, stair
lift, etc. (Bldg. R)
All new infrastructure: new piping, fixtures, etc. (Bldg. R)
Minor renovations to offices (Bldg. R)
Total renovation of locker/training rooms (Bldg. R)
HVAC upgrade: includes new air handlers, ductwork, etc.
(Bldg. Q & R)
Update fire alarm system (Bldg. Q & R)
Construction will be done in phases so as to minimize
disruption of classes
Final construction documents submitted to DSA Fall 2009
Estimated start of construction Summer 2010
10
Current and Upcoming
Construction Projects
LAC Building I - Measure E 2008
Add additional 4,000 square feet to existing building
Architecture to match LAC Mediterranean Theme
Submitted for DSA review
Construction scheduled for Summer 2010
11
Current and Upcoming
Construction Projects
PCC MDAB
(Multi-Disciplinary Academic Building) - Measure E 2002
Received reviewed plans from DSA.
Currently in construction drawing technical review phase
Install portables for swing space at PCC Spring 2010
Anticipated start of MDAB construction Summer 2010
Project to be completed in two phases
12
Current and Upcoming
Construction Projects
PCC Building CC Retrofit - Measure E 2008
To be designed by Hill Partnership Architects
Houses the Fitness Center, Gymnasium, Weight Room, and
Faculty and Staff Offices
Swing space to be located on PCC Campus (Bldg. GG)
To be completed concurrently with MDAB project phase 2
Anticipated start of construction Summer 2011
13
Current and Upcoming
Construction Projects
District Wide – Electronic Signage Plan
Measure E 2008
District Wide Signage Plan complete
Final site locations determined
Construction bids received/NTP to be issued
Anticipated construction completion of
Marquee Signs Summer 2010
14
liberal arts
Liberal Arts Campus
LAC
Facility Site Plan
Site Plan
pacific coast
Pacific Coast Campus
PCC
Facility Site Plan
Site Plan
Current and Upcoming
Construction Projects
Upcoming Projects
LAC
Expansion of Building I (Awaiting DSA approval)
Bookstore swing space to be located West of J building.
Relocate Bond Management Team Offices to O Building (Community Outreach and
Services Facility) and removal of W trailers (Fall 2010)
Increase parking at Faculty and Lew Davis St.
IITS relocation to O building
Bldg. K – Roof extension over Kiln area
Bldg. J – Theater lighting control panel replacement
CDC – new carpet installation
PCC
Bldg. JJ – Add new landscaping around perimeter
MDAB swing space preparation
Install exterior lighting at Tech1
Demolition of UU and VV
17
Planned Phasing of Future Projects
2009-10
Parking Structure – groundbreaking anticipated
February 2010
Building O2 occupancy scheduled
BMT and IITS – Fall 2010
Begin infrastructure construction – Fall 2009
Master landscaping implementation will follow this project
Install portables for swing space at PCC – Spring 2010
Begin construction of Buildings DD and EE at PCC
Anticipating Summer 2010 start
Anticipating swing space move for Building A at LAC –
Summer 2010
Marquees complete – Summer 2010
18
Planned Phasing of Future Projects
2010-11
Begin Building R (Gym) HVAC and ADA upgrades –
Summer 2010
Anticipating Summer 2011 completion
Begin construction of Building I (Bookstore) and move to
portable swing space – Summer 2010
Retrofit completion of Building Z – Summer 2010
Begin construction of Building A at LAC – Fall 2010
Begin Schematic Design for Buildings C and F at LAC
Submit plans to DSA no later than Summer 2011
19
Planned Phasing of Future Projects
2011-12
Infrastructure project complete at LAC – Summer 2011
Submit plans to DSA for Math/Technology Building at LAC –
Summer 2012
Construction completion of Buildings DD and EE at PCC –
Summer 2011
Begin construction of Buildings AA, BB and CC at PCC –
Summer 2011
Anticipated construction completion of Building I (Bookstore)
at LAC – Fall 2011
Anticipated construction completion of Parking Structure at
LAC – Spring 2012
20
Planned Phasing of Future Projects
2012-13
Move Buildings C and F programs into Swing Space (M/N
Building) and begin construction – Summer 2012
Anticipated Construction completion of Building A at LAC –
Summer 2012
Submit plans to DSA for M/N Building at LAC and Building
MM (Phase 1) at PCC – Summer 2012
Begin Schematic Design for Building P at LAC and Building
MM (Phase 2) at PCC – Summer 2012
Submit to DSA – Spring 2013
Begin construction of Math/Technology Building at LAC –
Winter 2013
21
Planned Phasing of Future Projects
2012-13
(continued)
Begin Schematic Design for Building D and E renovations –
Fall 2013
Anticipated Construction completion of Buildings AA, BB and
CC at PCC – Spring 2013
22
Planned Phasing of Future Projects
2013-14
Anticipated Construction completion of Buildings C and F at
LAC – Fall 2013
Begin construction of Buildings M/N at LAC and MM (Phase
1) at PCC – Fall 2013
Submit plans to DSA for Buildings D and E renovations at
LAC – Fall 2013
Schematic design for Performing Arts Building (G & H) and
Building R at LAC – Spring 2014
23
Planned Phasing of Future Projects
2014-15
Anticipated Construction completion of Math/Technology
Building at LAC – Summer 2014
Begin construction on Buildings D and E at LAC – Fall 2014
Submit plans to DSA for Performing Arts Building and
Building R (Gym) at LAC – Spring 2015
Anticipate construction start – Spring 2016
Anticipated construction completion of Buildings M/N at LAC
and MM at PCC – late Spring 2015
Begin construction on Buildings P at LAC and MM (Phase 2)
at PCC – Spring 2015
24
QUESTIONS
&
ANSWERS