Transcript COC

Bond Construction Update
Citizens Oversight Committee
Long Beach Community College District
April 18, 2011
EDUCATE  ENGAGE  EMPOWER
1
Agenda

Completed Construction Projects





Current Construction Projects









LAC Building A – Student Services Retrofit
LAC Infrastructure Improvements Project and District Wide –
Energy Efficiency Project
LAC Building I (Bookstore)
LAC South Walkway Extension
LAC W Trailers Demo
LAC Master Landscape
PCC MDAB (Multi-Disciplinary Academic Building)
PCC Tech1 (Sheet Metal)
Upcoming Construction Projects


LAC Parking Structure
LAC Building O Complex
PCC Walnut Ave. Arrival Court
District Wide – Monument Signs
PCC Building CC Retrofit
Q&A
2
Completed Construction Projects
LAC Parking Structure – Measure E 2008



Spaces for 893 vehicles
Solar generation system is commissioned and
operational
Project is complete and being used for student parking
3
Completed Construction Projects
LAC Building O Complex – Measure E 2008




Two structures totaling 87,000 square feet
Occupants for Building O2 are Foundation, ERD, LBNP and
ALCI
IITS and BMT are moved in, Warehouse Facility moving
Project is complete with some punch walk items left
4
Completed Construction Projects
PCC Walnut Ave. Arrival Court - Measure E 2008


UU/VV demo completed
Site converted to a parking lot April 4th, 2011
5
Completed Construction Projects
District Wide – Monument Signs
Measure E 2008
LAC Bldg. Designator

LAC Monument Sign
PCC Monument Sign
District Wide Monument Signs

Locations:
 LAC-Clark/Conant – completed January 8, 2011
 PCC-20th/Walnut Ave. – Completed March 30, 2011

Installation of building designators for LAC Bldg. O1 and O2
completed
6
Current Construction Projects
LAC Building A – Student Services Retrofit
Measure E 2008




New home for A&R, Counseling, Health Services,
Cashier, Transfer Center
Project currently in demolition and structure
upgrade
Construction fence and temporary walkways
complete
End of construction anticipated Summer 2012
7
Current Construction Projects
LAC Infrastructure Improvement Project and
District Wide Energy Efficiency Project
Measure E 2008



Total annual estimated savings of 1.5 mil. Kwh
Project started Fall 2009; currently hydro seeding all
affected areas(All phases)
Majority of existing building HVAC systems to be
upgraded and connected to the Central Plant



Exterior lighting and controls upgrades





Buildings C,D, G,H, & J are connected
Buildings B and E will be scheduled by end of April
All parking lots north of Lew Davis are on new system
New Reclaimed Water tie-ins to irrigation connected
New gas lines installed for Buildings B, C, D, E, G, H, J,
M, N, and P
New domestic lines installed for Buildings B, C, D, E, F, G,
H, I Trailers, J, K,L, M, N, P
Anticipated end of construction Winter 2011
8
Current Construction Projects
LAC Building I - Measure E 2008




Adds additional 4,000 square feet to existing building
Architecture to match LAC Mediterranean Theme
G2K Construction working on demolition and utilities
End of Construction anticipated Fall 2011
9
Current Construction Projects
LAC South Walkway Extension
Measure E 2008
 99% complete
 Palm trees to be replaced May 2011
 Continues Master Plan pedestrian corridor
10
Current Construction Projects
LAC W Trailers Demo - Measure E 2008





Green Giant Construction has removed old W trailers
Grading of lot to commence in this month
Project will address storm run off issues with bio swales
Site to be converted to a parking lot
Estimated project completion Summer 2011
11
Current Construction Projects
LAC Master Landscape - Measure E 2008




Currently in Design Phase
Quad areas North and South areas of Bldg. A bid Winter 2012
Remaining areas designed at 25%
Scope includes new hardscape/landscape and pedestrian
pathways
12
Current Construction Projects
PCC MDAB
(Multi-Disciplinary Academic Building)
Measure E 2002 and 2008




MDAB building remodel project
Phase 1 of 2 currently under construction
Project currently in demolition and structural reinforcement
Phase 1 Project to be completed Summer 2012
13
Current Construction Projects
PCC Tech 1 (Sheet Metal) - Measure E 2008



Currently in bid process
Construction to start Summer 2011
Projected to be completed before Fall 2011
14
Upcoming Construction Projects
PCC Building CC Retrofit - Measure E 2008





Houses the Fitness Center, Gymnasium, Weight Room, and
Faculty and Staff Offices
Swing space located on PCC Campus (Bldg. GG)
Approved by DSA on 1/27/11. Currently in bid process
To be completed concurrently with MDAB project phase 1
Anticipated end of construction 2012
15
liberal arts
Liberal Arts Campus
Site Plan
pacific coast
Pacific Coast Campus
Site Plan
QUESTIONS
&
ANSWERS
EDUCATE  ENGAGE  EMPOWER
18