BASSETT UNIFIED SCHOOL DISTRICT
Download
Report
Transcript BASSETT UNIFIED SCHOOL DISTRICT
BOND PROGRAM UPDATE
Building Tomorrow Today
Long Beach Community College District
Citizens’ Oversight Committee
July 9, 2007
AGENDA
Completed Construction Projects
Current & Upcoming Construction
Projects
- LAC Central Plant Structure
- LAC Learning Resources Center Structure
- South Quad Complex Structure
- PCC Central Plant
- PCC Learning Resources Center
- PCC Industrial Tech Phase 1
- PCC Industrial Tech Phase 2
What’s Next?
Q&A
COMPLETED CONSTRUCTION PROJECTS
Various Projects – Completed in 2006 & 2007
District Facilities &
Warehouse Complex –
Opened 1/06
LAC Athletic Field
– 3/06
PCC CDC – 4/06
Men’s Gym Boiler
Replacement – 4/06
LAC/LRC Utilities–6/06
LAC Men’s Gym Façade
Replacement
East Campus Demolition –
12/06
LAC/LRC Interim
Facilities – 5/07
LAC Central Plant &
SQC Utilities – 6/07
PCC Central Plant
Utilities – 6/07
LAC Construction Phasing
CURRENT & UPCOMING
CONSTRUCTION PROJECTS
LAC Central Plant – Structure
Part of Infrastructure
Master Plan
Improvements
Early Utility Package
Construction Complete
Awarded to Siemens on
DBOM Contract
Construction 3%
Complete
Completion Anticipated
Summer 2008
CURRENT & UPCOMING
CONSTRUCTION PROJECTS
LAC/Learning Resources Center – Structure
Construction 3%
Complete
Utility Installation
Complete Under Previous
Phase (Bid Pkg. #1)
Completion in December
2008
CURRENT & UPCOMING
CONSTRUCTION PROJECTS
South Quad Complex Structure (Bid Pkg. #3)
Construction Begun;
Approx. 40%
Complete
Additional Modern
Classrooms, Multipurpose Room,
Offices, etc.
Shifts Campus Center
South of Carson off
Lew Davis
PCC Construction Phasing
CURRENT & UPCOMING
CONSTRUCTION PROJECTS
PCC Central Plant
Part of Infrastructure
Master Plan
Improvements
Early Utility Package
Construction
Complete
Structure in Plan
Check
DBOM Contract
Awarded to Siemens;
Finalizing Value
Engineering
Negotiations
Anticipate Start Soon
CURRENT & UPCOMING
CONSTRUCTION PROJECTS
PCC Learning Resources Center
Construction 4%
Complete
Modern Facility with
Computer Lab and
Multimedia
Expanded Facility
Bridge to Bldg. EE
Art Deco Style
CURRENT & UPCOMING
CONSTRUCTION PROJECTS
PCC Industrial Technology Center Phase 1
Replaces Existing
Antiquated Structures
Bid Complete;
Construction to Start in
Late Summer 2007
Modern Facility Houses
Machine Tools and
Welding Depts.
New Campus “Bookend”
CURRENT & UPCOMING
CONSTRUCTION PROJECTS
PCC Industrial Technology Center Phase 2
Replaces Existing
Antiquated
Structures
Construction 97%
Complete
Modern Facility
Houses Aviation
and Automotive
Depts.
Move-in
Summer 2007
Classes Fall
2007
WHAT’S NEXT?
Secondary Projects LAC & PCC
Student Services Centers
– LAC Planning Underway;
Construction to Start at End
of South Quad Complex
– PCC Awaiting State Funding;
Will Start Construction in
2009/2010
– Centralizes Student Support
Services (Admissions,
Financial Aid, Cashier,
Counseling, Job Placement,
etc.)
New Building M
Gym (Q & R) Projects
Building E & F
Multi-Disciplinary Academic
Buildings (AA, BB, DD, EE)
– Awaiting State Approval to Start
Design; Antic. August 2007
– Construction 2009
– Retrofits Most of Existing
Occupants in More Efficient
Facility
– Classrooms and Offices
– Labs Including Computer, Art,
Foreign Language, English, and
Science Labs
– Absorbs Some Portable
Occupants
Stay Tuned????
QUESTIONS & ANSWERS
Prepared By:
Bond Management Team – Cordoba Corporation
July 9, 2007
BUILDING TOMORROW TODAY