BASSETT UNIFIED SCHOOL DISTRICT

Download Report

Transcript BASSETT UNIFIED SCHOOL DISTRICT

BOND PROGRAM UPDATE
Building Tomorrow Today
Long Beach Community College District
Citizens’ Oversight Committee
July 9, 2007
AGENDA


Completed Construction Projects
Current & Upcoming Construction
Projects
- LAC Central Plant Structure
- LAC Learning Resources Center Structure
- South Quad Complex Structure
- PCC Central Plant
- PCC Learning Resources Center
- PCC Industrial Tech Phase 1
- PCC Industrial Tech Phase 2


What’s Next?
Q&A
COMPLETED CONSTRUCTION PROJECTS
Various Projects – Completed in 2006 & 2007










District Facilities &
Warehouse Complex –
Opened 1/06
LAC Athletic Field
– 3/06
PCC CDC – 4/06
Men’s Gym Boiler
Replacement – 4/06
LAC/LRC Utilities–6/06
LAC Men’s Gym Façade
Replacement
East Campus Demolition –
12/06
LAC/LRC Interim
Facilities – 5/07
LAC Central Plant &
SQC Utilities – 6/07
PCC Central Plant
Utilities – 6/07
LAC Construction Phasing
CURRENT & UPCOMING
CONSTRUCTION PROJECTS
LAC Central Plant – Structure





Part of Infrastructure
Master Plan
Improvements
Early Utility Package
Construction Complete
Awarded to Siemens on
DBOM Contract
Construction 3%
Complete
Completion Anticipated
Summer 2008
CURRENT & UPCOMING
CONSTRUCTION PROJECTS
LAC/Learning Resources Center – Structure



Construction 3%
Complete
Utility Installation
Complete Under Previous
Phase (Bid Pkg. #1)
Completion in December
2008
CURRENT & UPCOMING
CONSTRUCTION PROJECTS
South Quad Complex Structure (Bid Pkg. #3)



Construction Begun;
Approx. 40%
Complete
Additional Modern
Classrooms, Multipurpose Room,
Offices, etc.
Shifts Campus Center
South of Carson off
Lew Davis
PCC Construction Phasing
CURRENT & UPCOMING
CONSTRUCTION PROJECTS
PCC Central Plant





Part of Infrastructure
Master Plan
Improvements
Early Utility Package
Construction
Complete
Structure in Plan
Check
DBOM Contract
Awarded to Siemens;
Finalizing Value
Engineering
Negotiations
Anticipate Start Soon
CURRENT & UPCOMING
CONSTRUCTION PROJECTS
PCC Learning Resources Center





Construction 4%
Complete
Modern Facility with
Computer Lab and
Multimedia
Expanded Facility
Bridge to Bldg. EE
Art Deco Style
CURRENT & UPCOMING
CONSTRUCTION PROJECTS
PCC Industrial Technology Center Phase 1




Replaces Existing
Antiquated Structures
Bid Complete;
Construction to Start in
Late Summer 2007
Modern Facility Houses
Machine Tools and
Welding Depts.
New Campus “Bookend”
CURRENT & UPCOMING
CONSTRUCTION PROJECTS
PCC Industrial Technology Center Phase 2





Replaces Existing
Antiquated
Structures
Construction 97%
Complete
Modern Facility
Houses Aviation
and Automotive
Depts.
Move-in
Summer 2007
Classes Fall
2007
WHAT’S NEXT?
Secondary Projects LAC & PCC

Student Services Centers

– LAC Planning Underway;
Construction to Start at End
of South Quad Complex
– PCC Awaiting State Funding;
Will Start Construction in
2009/2010
– Centralizes Student Support
Services (Admissions,
Financial Aid, Cashier,
Counseling, Job Placement,
etc.)



New Building M
Gym (Q & R) Projects
Building E & F
Multi-Disciplinary Academic
Buildings (AA, BB, DD, EE)
– Awaiting State Approval to Start
Design; Antic. August 2007
– Construction 2009
– Retrofits Most of Existing
Occupants in More Efficient
Facility
– Classrooms and Offices
– Labs Including Computer, Art,
Foreign Language, English, and
Science Labs
– Absorbs Some Portable
Occupants

Stay Tuned????
QUESTIONS & ANSWERS
Prepared By:
Bond Management Team – Cordoba Corporation
July 9, 2007
BUILDING  TOMORROW  TODAY