Transcript COC

Bond Construction Update
Citizens’ Oversight Committee
Cordoba Corporation
Long Beach Community College District
January 28, 2008
BUILDING  TOMORROW  TODAY
Agenda
 Completed Construction Projects
 Current & Upcoming Construction Projects







South Quad Complex Structure
LAC Central Plant Structure
LAC Learning Resources Center – Structure
LAC Building R, Men’s Gymnasium Renovation
PCC Central Plant
PCC Learning Resources Center
PCC Industrial Tech Phase 1
 Q&A
Completed Construction Projects
Various Projects – Completed in 2006 & 2007









PCC Industrial Technology
Center Phase 2 – 7/07
PCC Central Plant Utilities,
LAC Central Plant & SQC
Utilities – 6/07
LAC/LRC Interim – 5/07
East Campus Demo – 12/06
LAC Men’s Gym Façade
Replacement (FEMA &
Insurance Funded) – 8/06
LAC/LRC Utilities – 6/06
PCC CDC – 4/06
Men’s Gym Boiler
Replacement – 4/06
LAC Athletic Field – 3/06
District Facilities &
Warehouse Complex – 1/06
liberal arts
LAC Facility Site Plan
Current and Upcoming
Construction Projects
LAC Central Plant – Structure




Part of Infrastructure Master
Plan Improvements
Awarded to Siemens on DBOM
Contract
Construction 55% Complete
Completion Anticipated
Summer 2008
Current and Upcoming
Construction Projects
LAC/Learning Resources Center – Structure



Construction 38%
Complete
Utility Installation
Complete Under
Previous Phase (Bid
Pkg. #1)
Completion Anticipated
First Quarter 2009
Current and Upcoming
Construction Projects
LAC Building R, Men’s Gymnasium Renovation






Original floor and
bleachers removed
New sprung wood
flooring system
Lettering, graphics and
game lines applied to
the new floor system
New telescopic
bleachers installed on
both the main floor
and the mezzanine
level
Interior of the gym
painted
Lamps replaced for
new fixtures and
electrical capabilities
added
Current and Upcoming
Construction Projects
South Quad Complex Structure (Bid Pkg. #3)




Construction Approx.
48% Complete
Additional Modern
Classrooms, Multipurpose Rm.,
Offices, etc.
Shifts Campus
Center South of
Carson off Lew Davis
Completion
Anticipated Summer
2008
pacific coast
PCC Facility Site Plan
Current and Upcoming
Construction Projects
PCC Central Plant





Part of Infrastructure
Master Plan
Improvements
Early Utility Package
Construction
Complete
DBOM Contract
Awarded to Siemens;
Finalizing Value
Engineering
Negotiations
Construction
Approximately 20%
Complete
Completion
Anticipated Summer
2008
Current and Upcoming
Construction Projects
PCC Learning Resources Center





Construction 55%
Complete
Modern Facility with
Computer Lab and
Multimedia
Expanded Facility
Bridge to Bldg. EE
Completion Anticipated
Winter 2008
Current and Upcoming
Construction Projects
PCC Industrial Technology Center Phase 1





Replaces Existing
Antiquated Structures
Construction is 8%
Complete
Modern Facility Houses
Machine Tool and Welding
Departments
New Campus “Bookend”
Completion Anticipated
Winter 2009
Escalation Trends – per Leland Saylor Associates
QUESTIONS &
ANSWERS
Cordoba Corporation
Prepared by
Bond Management Team
January 28, 2008
BUILDING  TOMORROW  TODAY