BASSETT UNIFIED SCHOOL DISTRICT
Download
Report
Transcript BASSETT UNIFIED SCHOOL DISTRICT
BOND PROGRAM UPDATE
Building Tomorrow Today
Long Beach Community College District
Citizens’ Oversight Committee
April 9, 2007
AGENDA
Completed Construction Projects
Current & Upcoming Construction
Projects
-
South Quad Complex – Bid #2
LAC Central Plant Structure
LAC Learning Resources Center – Interim
LAC Learning Resources Center - Structure
South Quad Complex Structure
PCC Central Plant & Utilities
PCC Learning Resources Center
PCC Industrial Tech Phase 1
PCC Industrial Tech Phase 2
What’s Next?
Q &A
COMPLETED CONSTRUCTION PROJECTS
Various Projects
PCC CDC – 4/06
District Facilities &
Warehouse Complex –
Opened 1/17/06
Men’s Gym Boiler
Replacement – 4/06
PCC MM/NN Lighting
Upgrade – 4/05
LAC Athletic Field – 3/06
South Quad Complex
Bid Pkg. #1 – 12/05
LAC/LRC Utilities–6/06
LAC Men’s Gym Façade
Replacement (FEMA &
Insurance Funded)
East Campus Demolition
LAC Construction Phasing
CURRENT & UPCOMING
CONSTRUCTION PROJECTS
South Quad Complex – Bid Package #2
Construction 98.5%
Complete
Relocation of Water
Main and Reclaimed
Water Lines
Coordinated with
Central Plant
Relocates Major
Utilities Out of
Golf Mall
Clears Way for
Structures
CURRENT & UPCOMING
CONSTRUCTION PROJECTS
LAC Central Plant – Structure
Part of Infrastructure
Master Plan Improvements
Early Utility Package
Under Construction
Awarded to Siemens on
DBOM Contract
Construction Starts April;
Contractor Mobilizing
Completion Anticipated
Summer 2008
CURRENT & UPCOMING
CONSTRUCTION PROJECTS
LAC/Learning Resources Center – Interim Facilities
Construction 50%
Complete
Anticipate Completion
June 2007
Modular Buildings to be
Installed Saturday 3/31/07
Utility Installation
Complete Under Previous
Phase (Bid Pkg. #1)
Includes Retrofit of
Building E Basement
CURRENT & UPCOMING
CONSTRUCTION PROJECTS
LAC/Learning Resources Center – Structure
Re-Bid Opening 3/29/07
First Bids Rejected Move
Planning Underway
Utility Installation
Complete Under Previous
Phase (Bid Pkg. #1)
Anticipate Start in June
2007; Completion in
December 2008
CURRENT & UPCOMING
CONSTRUCTION PROJECTS
South Quad Complex Structure (Bid Pkg. #3)
Construction Begun;
Approx. 35%
Complete
Overlaps Central
Plant Early Piping
Due to Utility
Conflicts
Additional Modern
Classrooms, Multipurpose Rm., Offices,
etc.
Shifts Campus Center
South of Carson off
Lew Davis
PCC Construction Phasing
CURRENT & UPCOMING
CONSTRUCTION PROJECTS
PCC Central Plant & Utilities
Part of Infrastructure
Master Plan
Improvements
Early Utility Package
Under Construction;
Approx. 98.5% Complete.
Allows Utility Installation
while Structure is in Plan
Check
Clears Way for Structure
Structure in Plan Check
DBOM Contract Awarded
to Siemens; Anticipate
NTP April (NOI Issued)
CURRENT & UPCOMING
CONSTRUCTION PROJECTS
PCC Learning Resources Center
Awarded to Soltek Pacific
Construction Start in April
Pending State
Authorization
Modern Facility with
Computer Lab and
Multimedia
Expanded Facility
Bridge to Bldg. EE
Art Deco Style
CURRENT & UPCOMING
CONSTRUCTION PROJECTS
PCC Industrial Technology Center Phase 1
Replaces Existing
Antiquated Structures
DSA Reviewing
Changes; Out to Bid;
Start in July 2007
Modern Facility Houses
Machine Tools and
Welding Depts.
New Campus “Bookend”
S.E. Interim Bungalow
Construction In Close
Out Phase to Clear Tech
1 Site
CURRENT & UPCOMING
CONSTRUCTION PROJECTS
PCC Industrial Technology Center Phase 2
Replaces Existing Antiquated
Structures
Construction Underway; Approx. 53%
Complete
Modern Facility
Houses Aviation
and Automotive
Depts.
Impacted by
DF&WC
Completion in
Summer 2007
WHAT’S NEXT?
Secondary Projects LAC & PCC
Student Services Centers
– LAC Planning Underway;
Construction to Start at End
of South Quad Complex
– PCC Awaiting State Funding;
Will Start Construction in
2009/2010
– Centralizes Student Support
Services (Admissions,
Financial Aid, Cashier,
Counseling, Job Placement,
etc.)
New Building M
Gym (Q & R) Projects
Building E & F
Multi-Disciplinary Academic
Buildings (AA, BB, DD, EE)
– Awaiting State Approval to Start
Design; Antic. August 2007
– Construction 2009
– Retrofits Most of Existing
Occupants in More Efficient
Facility
– Classrooms and Offices
– Labs Including Computer, Art,
Foreign Language, English, and
Science Labs
– Absorbs Some Portable
Occupants
QUESTIONS & ANSWERS
Prepared By:
Bond Management Team – Cordoba Corporation
April 9, 2007