BASSETT UNIFIED SCHOOL DISTRICT

Download Report

Transcript BASSETT UNIFIED SCHOOL DISTRICT

BOND PROGRAM UPDATE
Building Tomorrow Today
Long Beach Community College District
Citizens’ Oversight Committee
April 9, 2007
AGENDA


Completed Construction Projects
Current & Upcoming Construction
Projects
-


South Quad Complex – Bid #2
LAC Central Plant Structure
LAC Learning Resources Center – Interim
LAC Learning Resources Center - Structure
South Quad Complex Structure
PCC Central Plant & Utilities
PCC Learning Resources Center
PCC Industrial Tech Phase 1
PCC Industrial Tech Phase 2
What’s Next?
Q &A
COMPLETED CONSTRUCTION PROJECTS
Various Projects









PCC CDC – 4/06
District Facilities &
Warehouse Complex –
Opened 1/17/06
Men’s Gym Boiler
Replacement – 4/06
PCC MM/NN Lighting
Upgrade – 4/05
LAC Athletic Field – 3/06
South Quad Complex
Bid Pkg. #1 – 12/05
LAC/LRC Utilities–6/06
LAC Men’s Gym Façade
Replacement (FEMA &
Insurance Funded)
East Campus Demolition
LAC Construction Phasing
CURRENT & UPCOMING
CONSTRUCTION PROJECTS
South Quad Complex – Bid Package #2





Construction 98.5%
Complete
Relocation of Water
Main and Reclaimed
Water Lines
Coordinated with
Central Plant
Relocates Major
Utilities Out of
Golf Mall
Clears Way for
Structures
CURRENT & UPCOMING
CONSTRUCTION PROJECTS
LAC Central Plant – Structure





Part of Infrastructure
Master Plan Improvements
Early Utility Package
Under Construction
Awarded to Siemens on
DBOM Contract
Construction Starts April;
Contractor Mobilizing
Completion Anticipated
Summer 2008
CURRENT & UPCOMING
CONSTRUCTION PROJECTS
LAC/Learning Resources Center – Interim Facilities





Construction 50%
Complete
Anticipate Completion
June 2007
Modular Buildings to be
Installed Saturday 3/31/07
Utility Installation
Complete Under Previous
Phase (Bid Pkg. #1)
Includes Retrofit of
Building E Basement
CURRENT & UPCOMING
CONSTRUCTION PROJECTS
LAC/Learning Resources Center – Structure




Re-Bid Opening 3/29/07
First Bids Rejected Move
Planning Underway
Utility Installation
Complete Under Previous
Phase (Bid Pkg. #1)
Anticipate Start in June
2007; Completion in
December 2008
CURRENT & UPCOMING
CONSTRUCTION PROJECTS
South Quad Complex Structure (Bid Pkg. #3)




Construction Begun;
Approx. 35%
Complete
Overlaps Central
Plant Early Piping
Due to Utility
Conflicts
Additional Modern
Classrooms, Multipurpose Rm., Offices,
etc.
Shifts Campus Center
South of Carson off
Lew Davis
PCC Construction Phasing
CURRENT & UPCOMING
CONSTRUCTION PROJECTS
PCC Central Plant & Utilities






Part of Infrastructure
Master Plan
Improvements
Early Utility Package
Under Construction;
Approx. 98.5% Complete.
Allows Utility Installation
while Structure is in Plan
Check
Clears Way for Structure
Structure in Plan Check
DBOM Contract Awarded
to Siemens; Anticipate
NTP April (NOI Issued)
CURRENT & UPCOMING
CONSTRUCTION PROJECTS
PCC Learning Resources Center






Awarded to Soltek Pacific
Construction Start in April
Pending State
Authorization
Modern Facility with
Computer Lab and
Multimedia
Expanded Facility
Bridge to Bldg. EE
Art Deco Style
CURRENT & UPCOMING
CONSTRUCTION PROJECTS
PCC Industrial Technology Center Phase 1





Replaces Existing
Antiquated Structures
DSA Reviewing
Changes; Out to Bid;
Start in July 2007
Modern Facility Houses
Machine Tools and
Welding Depts.
New Campus “Bookend”
S.E. Interim Bungalow
Construction In Close
Out Phase to Clear Tech
1 Site
CURRENT & UPCOMING
CONSTRUCTION PROJECTS
PCC Industrial Technology Center Phase 2





Replaces Existing Antiquated
Structures
Construction Underway; Approx. 53%
Complete
Modern Facility
Houses Aviation
and Automotive
Depts.
Impacted by
DF&WC
Completion in
Summer 2007
WHAT’S NEXT?
Secondary Projects LAC & PCC

Student Services Centers
– LAC Planning Underway;
Construction to Start at End
of South Quad Complex
– PCC Awaiting State Funding;
Will Start Construction in
2009/2010
– Centralizes Student Support
Services (Admissions,
Financial Aid, Cashier,
Counseling, Job Placement,
etc.)



New Building M
Gym (Q & R) Projects
Building E & F

Multi-Disciplinary Academic
Buildings (AA, BB, DD, EE)
– Awaiting State Approval to Start
Design; Antic. August 2007
– Construction 2009
– Retrofits Most of Existing
Occupants in More Efficient
Facility
– Classrooms and Offices
– Labs Including Computer, Art,
Foreign Language, English, and
Science Labs
– Absorbs Some Portable
Occupants
QUESTIONS & ANSWERS
Prepared By:
Bond Management Team – Cordoba Corporation
April 9, 2007
BUILDING  TOMORROW  TODAY