Transcript Slide 1
Objective FCM05
ESSIP Plan 2014 Octavian CIOARA DPS/PEPR 19.09.2014
Objective FCM05
• Comprehensive Explanation • What is new or has changed since LSSIP 2013 • Link to European ATM Master Plan • Finalisation Criteria and Closed Questions • ESSIP Report 2013 • Objective Coordinator’s Analysis, recommendations, tips & tricks • Links and contacts ESSIP Plan 2014 / Objective FCM05 2
Comprehensive Explanation
Area of applicability:
All ECAC
Initial Operational Capability (IOC): 09/2013 Full Operational Capability (FOC): 12/2016 The objective will ensure the improvement of B2B exchanges between local ASM tools and NM Implementation will provide enhanced NOP capabilities (ADR, DDR2, Flight Plan filling...) Most of the activities are part of the
Interim Deployment Programme
– IDP ESSIP Plan 2014 / Overview LSSIP 2013 3
What is new or has changed since LSSIP 2013
Nothing.
ESSIP Plan 2014 / Overview LSSIP 2013 4
Link to European ATM Master Plan
Objective FCM05 covers the following SESAR OI steps: OI Step – [AOM-0205] – Modular Temporary Airspace Structures and Reserved Areas OI step - [DCB-0102] – Interactive Rolling NOP ESSIP Plan 2014 / Overview LSSIP 2013 5
Most important SLoA(s)
FCM05-ASP01 – Upgrade the automated ASM support system with the capability of AIXM 5.1 B2B data exchange with NM FCM05-ASP02 – Perform an integration of the automated ASM support systems with the Network Each SLoA should be fulfilled in accordance with the relevant provisions of the NM B2B Reference Manuals ESSIP Plan 2014 / Overview LSSIP 2013 6
Finalisation Criteria and Closed Questions
Finalisation criteria: Contact your subject matter expert to determine the deployment Status for each SloA Closed questions: Closed Questions have been introduced for this Objective Statements on Deployment Status should provide answers to Closed Questions ESSIP Plan 2014 / Overview LSSIP 2013 7
ESSIP Report 2013
The submitted reports indicate that the objective will be implemented in time by the relevant stakeholders. However, as this is a new objective, there is still a high proportion of States having reported -No Plan-, therefore it is still premature to identify clear trends with regard the implementation progress.
ESSIP Plan 2014 / Overview LSSIP 2013 8
Objective Coordinator’s Analysis, recommendations, tips & tricks
Ensure that your subject matter expert is involvement once you make your statement.
Information provided per SLoA can be easily verified by checking the provisions laid down in the supporting material.
Attention to the applicability to the Military stakeholders as airspace users.
Objective also related to AOM19 ESSIP Plan 2014 / Overview LSSIP 2013 9
Links and contacts
Objective Coordinator: Octavian CIOARA +32 2 729 3282 [email protected] NMD Objective Expert: Nil AGACDIKEN +32 2 729 3073 [email protected]
ESSIP Plan 2014 / Overview LSSIP 2013 10