Objective COM09 - Migrate ground international or
regional X.25 data networks or services to the Internet
Protocol (IP)
ESSIP Plan 2014
Oscar ALFARO
DSS/EIPR
19.09.2014
Objective COM09










Explanation
What is new or has changed since previous ESSIP edition
Link to European ATM Master Plan
Most important SLoA(s)
Finalisation Criteria and Closed Questions
Supporting Material
ESSIP Report 2013
Objective Coordinator’s Analysis, recommendations, tips & tricks
Conclusions
Links and contacts
ESSIP Plan 2014 / Objective COM09
2
Explanation
 A replacement of X.25 for networks with a common standard at
European level is needed due to the diminishing support by the
industry for this protocol.
 Regulation (EC) No 633/2007 on the application of a common FMTP
implies de facto that IPv6 is the new standard for data networks or
services.
 IPv4 is accepted as a transition to IPv6.
 Closely linked to the PENS project.
 All ECAC states should migrate their international or regional data
services to IPv6 by the full operational capability date.
 The objective is an enabler for objective ITY-FMTP.
 Deployment date: end 2014
 Applicable to All ECAC States
ESSIP Plan 2014 / Objective COM09
3
What is new or has changed since previous
ESSIP edition
 Nothing
ESSIP Plan 2014 / Objective COM09
4
Link to European ATM Master Plan
 [CTE-C11a]-PENS: Set up of a first interconnection of existing IP
national data transport networks deployed by various ANSPs.
 [CTE-C11b]- Gateway to interconnect the Stakeholder's
Networks (ANSP/PENS, Airport, Airspace Users) [Ground IP
Network]: A European IP based data transport network is deployed
for ground/ground communications. This network is the main
element of the communication infrastructure supporting all the
Ground/Ground and Air/Ground communications. This network will
interconnect the ATM Stakeholders (ANSP, Airport, Airspace Users,
Network Manager) through gateways.
ESSIP Plan 2014 / Objective COM09
5
Most important SLoA(s)
 COM09-ASP01 Migrate international or regional X.25 data
networking facilities and/or services to IP
(Covers the transitional migration to IPv4, where applicable)
 COM09-ASP03 Migrate international or regional X.25 data
networking facilities and/or services to IPv6
(Covers the migration to IPv6, either directly from X.25 or from
IPv4)
ESSIP Plan 2014 / Objective COM09
6
Finalisation Criteria and Closed Questions
 COM09-ASP01 Migrate international or regional X.25 data
networking facilities and/or services to IP
 Finalisation Criteria (wrong in the published version of the ESSIP Plan
2013 – corrected in the ESSIP Database end September) should read:
International and regional ATM applications stipulated to make use of IP
networks are in operation under IPv4.
 COM09-ASP03 Migrate international or regional X.25 data
networking facilities and/or services to IPv6
 Finalisation Criteria: International and regional ATM applications
stipulated to make use of IPv6 networks are in operation under IPv6.
 No additional closed questions for these SLoAs
ESSIP Plan 2013 / Objective COM09
7
Supporting Material
 Regulation (EC) No 633/2007 of 7 June 2007 laying down
requirements for the application of a Flight Message Transfer
Protocol (FMTP)
 Regulation (EU) No 283/2011 of 22 March 2011 amending
Regulation (EC) No 633/2077
 Pan-European Network Services (PENS)
ESSIP Plan 2014 / Objective COM09
8
ESSIP Report 2013
 ANSPs’ plans as reported in 2012 are in line with the stipulated
deadline of December 2014.
ESSIP Plan 2014 / Objective COM09
9
Objective Coordinator’s Analysis,
recommendations, tips & tricks
 Ensure information is consistent with ITY-FMTP
 Make sure it is clear whether there is a plan to migrate to IPv4 as a
transition to IPv6 and specify plans and dates for both, where
applicable
 Pan-European Network Services (PENS) implementation can
facilitate the implementation
ESSIP Plan 2014 / Objective COM09
10
Conclusions
 N/A
ESSIP Plan 2014 / Objective COM09
11
Conclusions
 Objective Coordinator: Oscar ALFARO; +32 2 729 4665
[email protected]
 DNM Objective Expert(s): Liviu POPESCU; +32 2 729 3757
[email protected]