Commissioning Plan

Download Report

Transcript Commissioning Plan

CF MEP Commissioning
Oct 30, 2007
CF Commissioning
1
David Saenz
[email protected]
CF Commissioning Plan
Commissioning Plan (CP) developed by
Jacobs Facilities (Engineer of Record)
Title II project deliverable
Reviewed and approved by LCLS CF Eng
group leader – Javier Sevilla
CP includes a comprehensive list of field
deliverables and requirements that meet
expectations of LCLS
Administration
Detailed scope of Commissioning work
Quality Control Plan
Testing and Training Schedule
Field
Plumbing and Fire Protection Systems
Mechanical Systems
Electrical Systems
Elevator and Crane Systems
Demonstration and Testing
CP managed by 3rd party subcontractor,
independent of trades and Turner, hired by
LCLS
Oct 30, 2007
CF Commissioning
2
David Saenz
[email protected]
Commissioning Areas
Beam Transport Hall –
Undulator Hall
Near Experimental
Hall/Central Utility
Plant/12Kv Substation
Far Experimental Hall –
Electron Beam Dump
Front End Enclosure
X-Ray Transport &
Diagnostics Tunnel
Oct 30, 2007
CF Commissioning
3
David Saenz
[email protected]
Beam Transport Hall (BTH)
Oct 30, 2007
CF Commissioning
4
David Saenz
[email protected]
BTH Looking East
Ductwork
SB 2.3
Storage tank for runoff
water from tunnels
AHU
Drawings
M4201
A2200
Oct 30, 2007
CF Commissioning
5
David Saenz
[email protected]
NEH
Oct 30, 2007
CF Commissioning
6
David Saenz
[email protected]
HVAC ducting
NEH Cross Section
M4602
Oct 30, 2007
CF Commissioning
7
David Saenz
[email protected]
CUP
Oct 30, 2007
CF Commissioning
8
David Saenz
[email protected]
CUP Plan View
Drawing M0203
Boilers
Chillers
Mech Room-NEH
Electrical Rm
Oct 30, 2007
CF Commissioning
9
David Saenz
[email protected]
CENTRAL UTILITY PLANT (CUP)
Title II-IFC
Two Chillers (425 tons/ea), Primary and Secondary CHW loops and
Pumps BTH,UH,EBD,FEE, NEH and FEH
One Boiler (150 BHP/ea) Primary and Secondary HW loops and
pumps
DDC Temperature Control System to be connected to SLAC
network via Web Control
One Air Compressor (268 SCFM@150psi), Air Dryer and Receiver.
Will provide service to: BTH, UH, EBD, FEE, NEH,X-RAY, FEH
Wet Sprinkler System-Ordinary Hazard Group 1
One AHU for electrical room
Mechanical room for NEH HVAC system (MAU)
Oct 30, 2007
CF Commissioning
10
David Saenz
[email protected]
Substation 522-Phase I
S522
Oct 30, 2007
CF Commissioning
11
David Saenz
[email protected]
CP Procurement
Based on early estimates, budget was
established at $350K
Bids were solicited Aug 07 for CxA
(Commissioning Agent)
5 CxA bidders invited
4 bidders responded and all 4 were within budget!
Technical evaluation by CF group is complete
Weighted point score
Awarded to Engineering Economics Inc (EEI) at
$229K
Oct 30, 2007
CF Commissioning
12
David Saenz
[email protected]
CxA
Engineering Economics Inc (EEI)
Offices nationwide and able to shift resources if
necessary, although not likely
Commissioned over 33 million sf
Data centers
Medical research labs
Pharmaceutical labs
Federal facilities
LCLS Sector 20 Injector Facilities - successful
LCLS Magnetic Measurement Facilities - successful
Oct 30, 2007
CF Commissioning
13
David Saenz
[email protected]
Summary
Roles and responsibilities are clear
Expectations are documented and well
understood
CxA will be assigned to work with trades,
SLAC Facilities maintenance staff and LCLS
CF Engineering group
Goal is to deliver a complete and functional
project with all MEP systems fully
operational, inspected, tested, verified and
documented
Oct 30, 2007
CF Commissioning
14
David Saenz
[email protected]