Far Experimental hall Hutches

Download Report

Transcript Far Experimental hall Hutches

Far Experimental Hall - Hutches
Scope
Budget
Schedule
June 17, 2008
Far Experimental Hall - Hutches
1
David Saenz
[email protected]
SLAC Site Plan
SLAC Main Gate
Pep Ring Road
MMF
Sector 25
FEH
B028
B751
Sector 20
Upstream
LCLS General
Work Boundary
Research Yard
June 17, 2008
Far Experimental Hall - Hutches
2
David Saenz
[email protected]
FEH Location
ACCESS TUNNEL
FEH
X-RAY TUNNEL
June 17, 2008
Far Experimental Hall - Hutches
3
David Saenz
[email protected]
June 17, 2008
Far Experimental Hall - Hutches
4
David Saenz
[email protected]
Far Hall rebar lattice
Tunnel construction complete 25 April 2008
June 17, 2008
Far Experimental Hall - Hutches
5
David Saenz
[email protected]
Installing re-bar in the Far Experimental Hall
Far Experimental Hall south rib
June 17, 2008
Far Experimental Hall - Hutches
6
David Saenz
[email protected]
Scope
Cavern space is well defined as part of current civil
construction preformed by TCCo
Scheduled Beneficial Occupancy date is Aug 08
Issue For Construction (IFC) set had sufficient
spatial and utility capacities to support future
hutches
Draft requirements of Room Data Sheets (RDS)
have been provided for hutches
Held meeting 12/07 to discuss further hutch
program requirements
Data received to date is at early stage of determining
final scope to support scientific mission needs
Need to advance quickly
June 17, 2008
Far Experimental Hall - Hutches
7
David Saenz
[email protected]
Scope Per IFC
ACCESS TUNNEL
Denotes
hutches (not
a part of
current
construction)
RATED WALL/RADITION
BARRIER
June 17, 2008
Far Experimental Hall - Hutches
8
David Saenz
[email protected]
Recent FEH Changes
Monolithic single pour floor for entire FEH
and to include 50 meter at the east end of XRay tunnel
Relocation of wall (fire rated, radiation
barrier) to inside X-Ray tunnel
Relocation of pipes and ducting for exhaust
of X-Ray tunnel
June 17, 2008
Far Experimental Hall - Hutches
9
David Saenz
[email protected]
FEH Location
ACCESS TUNNEL
RATED WALL
RADIATION
BARRIER
FEH
X-RAY TUNNEL
June 17, 2008
Far Experimental Hall - Hutches
10
David Saenz
[email protected]
Hutch #4 & #5 Layout-Aug 07
Hutch #5
Hutch #4
June 17, 2008
Far Experimental Hall - Hutches
11
Denotes
ancillary
space for
hutches #4
and #5
Hutch #6?
David Saenz
[email protected]
Budget
WBS for FEH Hutches has a TPC of $2.82M
EDI at $.24M
Independent cost estimate
Title I/II design
Construction at $2.58M
Title III
Construction cost estimate as provided by JE,
based on Room Data Sheets, Rev 0 include the
following:
Escalation (thru July 09), sales tax, below grade factor
(difficulty factor), oh&p, bonding, general conditions, hutch
doors, 1/8” lead lined walls and ceilings, 1 ton hoist,
mechanical and electrical
June 17, 2008
Far Experimental Hall - Hutches
12
David Saenz
[email protected]
Schedule
FEH Hutches 4 and 5
Title I Design (present – end of 6/08)
Title II
Procurement (7/08)
Design (8/08 – 11/08)
Title III
Procurement (11/08 – 12/08)
Construction (1/09 – 7/09)
Construction Complete July 09
Beneficial Occupancy July 09
Project Complete Aug 09
June 17, 2008
Far Experimental Hall - Hutches
13
David Saenz
[email protected]
Next 6 Months
Complete Title I effort (in house resources)
6/08
Procurement activities for Title II 7/08
Commence Title II design 8/08
Independent cost estimate 10/08
Complete Title II 11/08
Procurement activities for Construction 11/08
Construction start 1/09
June 17, 2008
Far Experimental Hall - Hutches
14
David Saenz
[email protected]
Summary
Cavern support space as currently being
constructed is well defined
Scheduled date for Beneficial Occupancy
Aug 08 is reasonable
Hutch requirements need to be solidified no
later than June 30, 08
Rad Physics requirements play major role
Need liaison between CF and LUSI
June 17, 2008
Far Experimental Hall - Hutches
15
David Saenz
[email protected]
End of presentation
June 17, 2008
Far Experimental Hall - Hutches
16
David Saenz
[email protected]
Scope in TCCo Contract
Power
Lighting and power FEH cavern
Capacity for two independent panels in each
hutch
Cable trays at perimeter of FEH
Welding outlet, 480 volts, 3 ph.
Mechanical
FEH cavern: conditioned space
Restrooms including showers
June 17, 2008
Far Experimental Hall - Hutches
17
David Saenz
[email protected]
Scope in TCCo Contract
Mechanical
Drainage (3 sump pumps inc. access tunnel)
and SW piping to sanitary waste system through
FEH access tunnel
Outside air capacity for three future hutches
Compressed air (from CUP) south wall (stub
outs w/valves)
Process cooling water (PCW) for Hutches and
work area- 68°F, 10GPM/ea
June 17, 2008
Far Experimental Hall - Hutches
18
David Saenz
[email protected]
Utility Yard at Entrance AT
EXHAUST FANS
FEH ACCESS TUNNEL
FEH ACCESS TUNNEL
TRANSFORMER
CROSS SECTION AT THE ENTRANCE OF ACCESS TUNNEL
June 17, 2008
Far Experimental Hall - Hutches
19
David Saenz
[email protected]
Room Data Sheets (RDS)
Preliminary “draft” for hutches #4 and 5
Requirements for:
Power (clean and dirty)
HVAC, 72 °F, ± 1°F, RH 45% ± 10%
Exhaust
1 ton crane
Fire protection/fire alarm system
Network and phone systems
Cable trays and penetrations thru walls
Lead lined walls
June 17, 2008
Far Experimental Hall - Hutches
20
David Saenz
[email protected]
Hutch #4 Utilities Requirements
June 17, 2008
Far Experimental Hall - Hutches
21
David Saenz
[email protected]