FEH Layout, Status
John Arthur – LCLS Expt’l Facilities Div
June 3, 2009
FEH Status
CXI Review June 3, 2009
1
1
John Arthur
[email protected]
LCLS new construction
Undulator Hall
Near Experimental Hall
Front End Enclosure
Far Experimental Hall
FEH Status
CXI Review June 3, 2009
2
2
John Arthur
[email protected]
First LCLS FEL light at 1.5 Å
FEH Status
CXI Review June 3, 2009
3
3
John Arthur
[email protected]
Gain vs undulator length at 1.5 Å
FEL gain
length = 3.3 m
FEL
saturation
indicated
Pulse energy
~ 1 mJ
FEH Status
CXI Review June 3, 2009
4
4
John Arthur
[email protected]
The LCLS X-ray Beamline
3 Hutches
X-ray transport tunnel
Far
Experimental
Hall
3 Hutches
Near Experimental Hall
Front End Enclosure
FEH Status
CXI Review June 3, 2009
5
5
John Arthur
[email protected]
FEE
Solid
Attenuators
Gas
Attenuator
Calorimeter
Slit
Gas
Detectors
K-Mono
5 mm collimator
Direct Imager
(Scintillator)
FEH Status
CXI Review June 3, 2009
FEL Offset Mirror Systems
6
6
John Arthur
[email protected]
LCLS Offset Mirror Systems
800-2000 eV to
Hutch 1
HOMS: Hard x-ray Offset
Mirror System
SOMS: Soft x-ray Offset
Mirror System
insertable
800-2000 eV to
Hutch 2
Shadow
Wall
Wall 2
insertable
2000-25000 eV
to Hutch 3-6
FEH Status
CXI Review June 3, 2009
7
7
John Arthur
[email protected]
Far Experimental Hall
FEH Status
CXI Review June 3, 2009
8
8
John Arthur
[email protected]
FEH Hutch Layout
Roll-up door (interlocked)
HPS control
HPS door (one per hutch)
Online-offline status lights
PPS door (Tunnel entrance)
Accelerator status lights (two places)
PPS control (keybank, etc)
FEH Status
CXI Review June 3, 2009
exit
9
9
John Arthur
[email protected]
FEH Hutch Layout Detail
Roll-up door (interlocked)
HPS control
HPS door (one per hutch)
Online-offline status lights
Accelerator status lights (two places)
9m
20 m
FEH Status
CXI Review June 3, 2009
10 10
John Arthur
[email protected]
FEH Hutch construction plan
Bids were well below estimates
Contract about to be signed
Steel frame procurement already under way
Construction finished Dec 2009
CXI installation could start early 2010
Basic services installed Feb 2010
Network, PPS
FEH Status
CXI Review June 3, 2009
11
11
John Arthur
[email protected]
Open issues with hutches
PPS design needs to be finalized
Utilization of mezzanine
Cooling water system upgrade
These issues will be easier to resolve when
instrument designs are final
FEH Status
CXI Review June 3, 2009
12 12
John Arthur
[email protected]
Summary
LCLS works
FEH hutches will be ready in early 2010
Operations support including User support is in place