Programme Management Board Reporting Period: October 2014 17 November 2014 Programme Management Board 1 Programme Status • At month 7 the Trust has achieved £3,318k in savings. For the same period the planned savings target was £4,099k, representing £716k under performance. In October 2014 budgets associated with savings expectations were removed and the stepped change in under-performance reflects the removal of those budgets. As reported at the November Board meeting the forecast savings identified for 2014/15 from the service review programme currently stand at £2.626m; planned savings from service reviews are £2.961m. The forecast recurrent shortfall is £335k. • Each service now has detailed timelines regarding all aspects of the review – workforce, service redesign, estates, EPR, administration functions etc. The Programme Management Office is responsible for monitoring the plans and escalating any issues to Programme Management Board. • The updated (recovery) plan for the EPR project has been accepted by General Managers, Service Managers, SMT and PMB. Appropriate project resources have been recruited to deliver the project. MSK project has gone live. Detailed work on the implementation plan will ensure for Children's Nursing Services go live on 20 November and Hannah House go live on 8 December 2014 17 November 2014 Programme Management Board 2 2014/15 Programme Status Projects Recurrent Plan £k In Year Annual Forecast Outturn Plan £k £k Forecast Variance £K Year to Date Plan £k Year to Date Plan Actual £k Variance Year to Date Actual £k Estates Utilisation 256 256 256 0 149 149 0 Medicines Use 28 28 28 0 16 16 0 Non-Pay Efficiency 256 256 256 0 149 149 0 Procurement 153 153 153 0 89 61 -29 Health and Wellbeing 202 202 0 -202 118 0 -118 Travel 204 204 204 0 119 119 0 Productivity (Gains) 202 202 202 0 118 118 0 Skills Mix 109 109 109 0 64 64 0 CNS Remodel 51 51 69 18 0 0 0 2,910 2,910 1,838 -1,072 485 339 -146 EPR 253 253 0 -253 42 0 -42 Contribution of New Business 100 100 100 0 58 58 0 1,000 1,000 0 -1,000 1000 618 -382 531 531 531 0 310 310 0 Release of Reserves 1,777 1,777 1,777 0 1,316 1,316 0 Total for 2014/15 8,032 8,032 5,523 -2,509 4,033 3,318 -716 Service Reviews Increase in Vacancy Factor Estates Utilisation 17 November 2014 Programme Management Board 3 2014/15 & 2015/16 Programme Status Projects 14/15 Plan £k 14/15 Confidence of Delivery 15/16 Plan £k 15/16 Confidence of Delivery Opportunity Plan Status Estates Utilisation 256 664 Medicines Use 28 28 Non-Pay Efficiency 256 256 Procurement 153 153 Health and Wellbeing 202 N/A Travel 204 N/A Productivity - Initial Changes 202 N/A Skill Mix 109 N/A CNS Remodel 51 80 Service Review 3,580 3,580 Service Review CAN Investment Offset -670 N/A Integration N/A 505 EPR 253 253 Corporate Cost Reduction N/A 252 Profit on New Business / Income 100 100 1,000 N/A Estates Cost Savings 531 N/A Release of Reserves 1,777 N/A N/A 729 £8,032 £6,600 Increase in Vacancy Factor To be confirmed Total for year before adjustment 17 November 2014 Programme Management Board Clear rationale and underlying analysis which has been reviewed by Finance Clear rationale, further work required to test the analysis and assumptions Provisional rationale Confidence of Delivery Status Successful delivery of the project to time, cost and quality is achievable. There are no outstanding issues that will impact the project delivery Successful delivery appears feasible. There are issues that exist and require management attention. These issues appear resolvable at this stage and if addressed promptly, should not impact project delivery Successful delivery of the project/programme appears to be at risk. There are significant issues on project/programme scope, timeline, budget, quality and /or benefits delivery. The project/programme may need rebaselining and/or overall viability reassessed 4