Transcript Document

Programme Management Board
Reporting Period: July 2014
19 August 2014
Programme Management Board
1
2014/15 Programme Status
• Overall the Trust achieved £2,073k in 2014/15. The planned savings were £2,163k. This is £90k under performance and is due to an
overspend on staffing (failure against the vacancy factor target)
Service Review Update
 Service Reviews are progressing well and the teams are mobilising to develop and deliver the implementation of the recommendations.
 Actual savings of £68k have been achieved through Service Reviews / Re-design work already initiated to date
 The Project teams are developing detailed implementation plans to support the delivery. These will need appropriate resources from both
corporate and front line to deliver the change.
 The Implementation model/process was signed off at the Programme Management Board. This will be communicated through the
September team brief
 Services and Corporate are developing regular sessions to share, learn and work together to deliver the implementation plans
 Individual Service Reviews are running according to the agreed scheduled (please see attached Plan on a Page – private session
 In July/August, the following services have presented to Senior Management Team
• Findings Reports – Family Nurse Partnership, Watch it, Sickle Cell , Long Term conditions
• Option Appraisal – Healthy Living, Podiatry, Primary Care Mental Health, Adult Integration, Wound Management, Continence,
Urology & Colorectal Service, Adult Domiciliary Physio and Falls team
 The opportunity figures and delivery status identified within these reports are noted for each review on the attached Plan on a Page
(private session)
EPR Update
 The project rollout plans are being reviewed in line with the business case plan. A recovery plan is being developed.
 As part of the recovery plan – aligning the output of Service Reviews and reviewing Phase 1 and 2 listing
 Preparing a launch event to explain EPR to the Phase 1 services to enable success
 Aligning the Clinical documentation and EPR has been initiated, further work required to embed this process within the EPR review
process
Estates Update
 Estates Team are developing clear structure to manage the strategic LCH Estates Project and the Service Review projects. Recovery
Plan being developed for 2015/16 to enable financial targets to be delivered.
Programme Management Board
2
2014/15 Programme Status
Recurrent Plan
£k
In Year Annual
Plan
£k
Forecast
Outturn
£k
Forecast
Variance
£K
Year to Date
Plan
£k
Year to Date
Actual
£k
Variance Year to
Date Actual
£k
Estates Utilisation
256
256
256
0
85
85
0
Medicines Use
28
28
28
0
9
9
0
Non-Pay Efficiency
256
256
256
0
85
85
0
Procurement
153
153
153
0
51
28
-23
Health and Wellbeing
202
202
0
-202
67
67
0
Travel
204
204
204
0
68
68
0
Productivity (Gains)
202
202
202
0
67
67
0
Skills Mix
109
109
109
0
36
36
0
CNS Remodel
51
51
51
0
0
0
0
2,910
2,910
2,711
-199
0
68
68
EPR
253
253
253
0
0
0
0
Contribution of New Business
100
100
100
0
33
33
0
1,000
1,000
0
-1,000
667
531
-135
531
531
531
0
177
177
0
Release of Reserves
1,777
1,777
1,777
0
816
816
0
Total for 2014/15
8,032
8,032
6,631
-1,401
2,163
2,073
-90
Projects
Service Reviews
Increase in Vacancy Factor
Estates Utilisation
19 August 2014
Programme Management Board
3
2014/15 & 2015/16 Programme Status
Projects
14/15
Plan £k
14/15
Confidence
of Delivery
15/16
Plan £k
Estates Utilisation
256
664
Medicines Use
28
28
Non-Pay Efficiency
256
256
Procurement
153
153
Health and Wellbeing
202
N/A
Travel
204
N/A
Productivity - Initial Changes
202
N/A
Skill Mix
109
N/A
CNS Remodel
51
80
Service Review
3,580
3,580
Service Review ACN Investment Offset
-670
N/A
Integration
N/A
505
EPR
253
253
Corporate Cost Reduction
N/A
252
Profit on New Business / Income
100
100
1,000
N/A
Estates Cost Savings
531
N/A
Release of Reserves
1,777
N/A
N/A
729
£8,032
£6,600
Increase in Vacancy Factor
To be confirmed
Total for year before adjustment
19 August 2014
15/16
Confidence
of Delivery
Programme Management Board
Opportunity Plan Status
Clear rationale and underlying analysis
which has been reviewed by Finance
Clear rationale, further work required to
test the analysis and assumptions
Provisional rationale
Confidence of Delivery Status
Successful delivery of the project to time,
cost and quality is achievable. There are
no outstanding issues that will impact the
project delivery
Successful delivery appears feasible.
There are issues that exist and require
management attention. These issues
appear resolvable at this stage and if
addressed promptly, should not impact
project delivery
Successful delivery of the
project/programme appears to be at risk.
There are significant issues on
project/programme scope, timeline,
budget, quality and /or benefits delivery.
The project/programme may need rebaselining and/or overall viability reassessed
4