Transcript 5171 MW

GEOTHERMAL IN INDONESIA
(OVER VIEW)
Sigit Rahardjo
Operation Director
PT PERTAMINA GEOTHERMAL ENERGY
Jogjakarta , Mei 2013
GEOTHERMAL ENERGY
CHARACTERISTIC OF GEOTHERMAL BUSINESS
1
GEOTHERMAL ENERGY
INDONESIA HAS THE HIGHEST POTENTIAL FOR GEOTHERMAL
ENERGY IN THE WORLD
Conventional geothermal 2010 capacity and
total potential capacity
GW
Indonesia
U.S.
Japan
•
1
•
3
•
1
2
Philippines
2
Mexico
1
•
Iceland
1 •
New Zealand
1•
Total
•
•
20
19
•
Others1
•
27
18
Resource
Utilization
%
4
28
13
23
•
20
3
•
20
10
•
6
33
5
•
6
20
5
•
6
10
4
3•
16
4
11
102
•
113
10
• In spite of its world’s
largest potential of
geothermal resource,
the utilization only
remains 4%
• Geothermal resource
in Indonesia is also
high temperature
resource which
enable more
economical
geothermal
development project
•
•
Installed
Potential
1 Includes mostly South/South-East Asia and Africa
SOURCE: GEA; DOE; EER; World Geothermal Congress; Energy Information Administration (EIA); interviews
2
GEOTHERMAL ENERGY
INDONESIA’S WORLD LEADING GEOTHERMAL PROSPECT
Borneo
Sumatera
Speculative : 13.258 MWe
Probable * : 5.433 MWe
Speculative : 45 MWe
Probable * : - MWe
Speculative : 27.141 MW
Probable
: 10.253 MW
Current Installed Capacity : 1,337 MW
Maluku
Sulawesi
Speculative : 1.907 MWe
Probable * : 721 MWe
Medan
Speculative : 734 MWe
Probable * : 142 MWe
Manado
Tanjung Karang
Bandung
Semarang
Java
Speculative : 9.471 MWe
Probable * : 3.086 MWe
Geothermal location
Papua
Bali & NTT
Speculative : 1.676 MWe
Probable * : 871 MWe
Speculative : 50 MWe
MAGMA
Probable * : - MWe
3
GEOTHERMAL ENERGY
GEOTHERMAL ROAD MAP
(Based on President Decree No. 5/2006 on National Energy Policy; Modified by MEMR.REG. No. 15/2010)
2006
2008
2012
2016
2020
2025
2014
852 MW
(Production)
1148 MW
Existing WKP
2000 MW
3442 MW
5171 MW
12332 MW
7788 MW
(Target baru )
4600 MW *
1442 MW
Existing WKP
3977 MW
Existing WKP +
New WKP
2617 MW
New WKP
9500 MW *
4544 MW
New WKP
1.337 MW
Current Condition
Ministry decree MEMR
No. 15/2010
5171 MW
Plus The second 10,000
MW fast track program
Under the second 10,000 MW fast-track plan, 34% of energy
development come from geothermal energy.
(GSDM, 2010, Update Jan 2013)
*) Road Map 2007
4
GEOTHERMAL ENERGY
PERTAMINA AIMS TO BE A LEADER IN GEOTHERMAL
DEVELOPMENT
Geothermal development by operator type
Capacity
GW
Indonesia
SOE
Philippines
Share of SOE
%
23
0.8
2.0
61
100
0 1.2
1.2
Private
1.3
1.2
Mexico
Iceland
0.9
0.4
1
84
0.1 0.6
0.5
New Zealand
0.7
0.4
54
0.3
State-owned Enterprise energy companies developed more than 50%
of geothermal energy in respective markets
1 State Owned Enterprise
•
SOURCE: company websites
5
GEOTHERMAL ENERGY
PGE’s WORKING AREA
TOTAL PGE’S INSTALLED CAPACITY: 402 MW
1
14
13
2
3
4
5
Ref. Ministerial Decree MEMR
No 2067K/30/MEM/2012
1.
2.
3.
4.
5.
Sibayak-Sinabung
Sibual-buali
Sungai Penuh
Hululais
Lumut Balai &
Margabayur
6
7
8
9
10
6. Gunung Waypanas
7. Cibeureum Parabakti
8. Pangalengan
9. Kamojang/Drajat
10. Karaha Cakrabuana
11
12
11. Gn. Iyang Argopuro
12. Tabanan
13. Kotamobago
14. Lahendong
6
GEOTHERMAL ENERGY
GEOTHERMAL DEVELOPMENT CONCEPT
TO SUPPORT ACCELERATION OF GEOTHERMAL DEVELOPMENT
IN LINE WITH 10,000 MW POLICY STAGE II –
EBTKE’S VISION 25/25 (5 % ENERGY MIX / 12.332 MW - 2025)
IMPLEMENTATION
PROJECT MANAGEMENT,
RISK ASSESSMENT,
ENV MGT
BUSINESS PORTFOLIO
ECONOMIC APPROACH
LEGAL ASPECTS
LAW, REGULATION, PERMIT
TECHNICAL ASPECT
GGGR, OPERATIONAL,
MAINTENANCE
GEOTHERMAL ENERGY DEVELOPMENT POLICY
(PRES DECREE No. 5 / 2006; GOV’T REGULATION No. 3/2005 – No. 70/2010 : PERMEN ESDM. No. 5 / 2009; No. 2/2011;
PERPRES No. 4/2010 : PERPRES No. 10/2011)
1000 MW :
42.250 BOEPD
6.1 JT TON CER”S/YEAR
7
GEOTHERMAL ENERGY
IDEAL GEOTHERMAL BUSINESS PROCESS IN INDONESIA
HEAD OF AGREEMENT
PRICE AND CONTRACT
NEGOTIATION
Notice Of Resorces Confirmation
Notice Of Intend to
Develop
COD
US$
• AMDAL
/
UKL
/
UPL
(EIA/Environment
Management
Effort/Environment
Monitoring
Effort)
• Location Permit
• Permit of Land usage for
Exploration Activities – Forestry
Minister
• SIPPA (Surface Water Usage
Permit)
• IMB (Construction Permit)
EPC
FEED
EXPLOITATION
•
•
•
•
EXPLORATION
INVENTORY WKP
2 Years
AMDAL (EIA)
Location Permit
Land Usage Permit
SIPPA (Surface Water Usage
Permit)
• IMB (Construction Permit)
3 Years
8
GEOTHERMAL ENERGY
Pertamina aspires to achieve by 2015
•MW
2,295
2,445
2,505
•15
•16
•17
•2018
102
112
119
122
•2015
•2016
•2017
1,508
•Steam
Availability
2,090
823
610
•2012
•13
•14
•K Boepd
•Oil
equivalent
73
30
•2012
40
•2013
•2014
9
•2018
GEOTHERMAL ENERGY
KEY BARRIERS TO GEOTHERMAL DEVELOPMENT IN INDONESIA
Description
• Higher capital expenditure compared with other power
generation technologies
Uncertain
economics
High upfront • Cost of USD 35-50 Mn for preliminary studies including
exploration wells to prove the reserves without any
capital
requirement external financing
• Development and exploration costs are solely borne
Uncertainty
on pricing
•
by geothermal company and are not reimbursed by
government unlike the practice in oil & gas industry
Implementation of MEMR Decree on Feed In Tariff
requires further negotiation with PLN as a single buyer
• Most of the geothermal reserves are located in
protected forests and geothermal activities are not
allowed to carry out in forest conservation areas
Uncertain
environment
Regulatory
uncertainty
• Overlapping jurisdictions increases lead time and
complexity as local authorities often block the projects
approved by the central government
All these together
mean that under
the current
environment,
geothermal
development
projects are
potentially high
risk, especially for
smaller operators
• Tariff agreement with PLN often comes back for the
renegotiation, hence no guarantee on the price
Other risks
• PLN off take is not guaranteed by government
10
GEOTHERMAL ENERGY
11
PGE PRODUCTION FIELD - OWN OPERATION
POWER PLANT UNIT – 4 ( 60 MW )
POWER PLANT UNIT 1,2 & 3
(30; 2 x 55 MW)
KAMOJANG GEOTHERMAL FIELDS
POWER PLANT UNIT-1
SIBAYAK GEOTHERMAL FIELD
PRODUCTION
CLUSTER UNIT-2
POWER PLANT UNIT-4
LAHENDONG GEOTHERMAL FIELDS
GEOTHERMAL ENERGY
PGE GEOTHERMAL FIELDS UNDER JOC SCHEME
WAYANG-WINDU GEOTHERMAL FIELDS (JOC-STAR ENERGY)
PLTP 1x110 MW & 1x117 MW
DARAJAT GEOTHERMAL FIELD (JOC-CHEVRON)
PLTP 1x55 MW, 1x95 MW & 1x121 MW
SALAK GEOTHERMAL FIELD (JOC-CHEVRON)
PLTP 3x60 MW & 3x65 MW
12
GEOTHERMAL ENERGY
PGE’S GEOTHERMAL ONGOING PROJECTS
No
Project Name
Location
Capacity (MW)
Project Type
1
Lumutbalai Unit 1&2,
Sumatera Selatan
2 x 55 MW
Total Project
2
Lumutbalai Unit 3&4,
Sumatera Selatan
2 x 55 MW
Total Project
3
Ulubelu Unit 3&4,
Lampung
2 x 55 MW
Total Project
4
Kamojang Unit 5
Jawa Barat
30 MW
Total Project
5
Lahendong Unit 5&6
Sulawesi Utara
2x20 MW
Total Project
6
Kotamobagu Unit 1&2
Sulawesi Utara
2 x 20 MW
Steam Supply
7
Hululais Unit 1&2
Bengkulu
2 x 55 MW
Steam Supply
8
Sungai Penuh Unit 1
Jambi
55 MW
Steam Supply
9
Karaha
Jawa Barat
30 MW
Total Project
GEOTHERMAL ENERGY
UPCOMING GREENFIELDS DEVELOPMENT PLAN
Kotamobagu
Name of Prospect Area
Ins. Capacity
(MW)
Medan
Sumatera Island
Manado
1
2
3
4
Sinabung
WKP Sungai Penuh
1. Semurup
40
WKP Hululais – Tambang
Sawah
1.Tambang Sawah
2.Bukit Daun
70
110
WKP Lumut Balai
1. Margabayur
75
WKP Ulubelu – Way Panas
1. Way Panas
Sumurup
Tambang Sawah
Bukit Daun
Margabayur
Way Panas
Tanjung Karang
MAGMA
Ciharus
Semarang
Bandung
Masigit-Guntur
120
Iyang Argopuro
Java Island
5
6
Key Indicators:
WKP Kamojang
1.G. Masigit Guntur
2.Ciharus
50
30
WKP Iyang Argopuro
1. Iyang Argopuro
55
Sulawesi Island
7
WKP Kotamobago
1. Kotamobago
60
• New Geothermal Power Generation
Capacity : ± 610 MW
• Additional Power Generation (kWh per
year) : ± 4800 million
• Avoided CO2 : ± 4,5 million tonnes per
Year
14
GEOTHERMAL ENERGY
THANK YOU
Bekerja dan ibadah
adalah energi kami
Semoga semua upaya
menghasilkan manfaat
Insya Allah!
15
GEOTHERMAL ENERGY