Transcript Summary
GLAST LAT Project Gamma-ray Large Area Space Telescope DOE/NASA Review, March 31, 2004 GLAST Large Area Telescope: Summary April 1, 2004 Lowell A. Klaisner Stanford Linear Accelerator Center Project Manager [email protected] 650-926-2726 1 GLAST LAT Project DOE/NASA Review, March 31, 2004 Working Critical Path, 3/31/04 MCM Burn-In & Test Apr 29, 2004 Tower Assembly & Test Jul 7, 2004 Tower A RFI Aug 18, 2004 Tower 14 RFI Feb 15, 2005 LAT Assembly Complete Apr 8, 2005 System Test Complete Jun 28, 2005 Pre-ship/CD-4 Review June 29, 2005 Environmental Test Complete November 12 2005 LAT RFI November 12, 2005 This critical path based on Tracker estimates presented March 31, 2004. The schedule after Tower A will be worked to mitigate the resulting delay in LAT RFI. 2 GLAST LAT Project DOE/NASA Review, March 31, 2004 Mitigating late module arrival • The project is focusing on integration and test of the first tower. The following are areas to work as we learn more about actual performance – I&T can use the additional time for more training and testing to reduce risk in integration and improve productivity. – Some part of System Test could be moved earlier and tested with a partial LAT configuration – System Test Period is 2 Shift/5 Days, could be up to 3 Shift/7 Days – Increase the production rate of modules by working second shifts, etc. – Investigate compressing the environmental test schedule from the present 15 weeks 3 GLAST LAT Project DOE/NASA Review, March 31, 2004 Summary • • • • • • • • The LAT is a challenging instrument Significant technical progress -- no major issues outstanding Producing flight hardware Overall project funding is adequate if stay on schedule Funding in the current fiscal year is an issue being worked Schedule is challenging – Focusing on installation of the first flight tower in the grid – Mitigating delays as they occur • Delay in completing Grid design – Qualify 2nd grid • Delay in arrival of CAL ASICs -- Load parts before qualification • Tracker delay due to test anomalies – Proceed with fabrication before testing is complete Project management needs to be proactive in identifying plans to mitigate potential future schedule delays A strong, talented staff that is committed to delivering this instrument and doing the science 4 GLAST LAT Project GLAST DOE/NASA Review, March 31, 2004 Feb 2007 launch 5