LAT Level Design Status
Rob Black [email protected]
1
11/3/2004
GLAST LAT Project
LAT Engineering Meeting
Agenda
•
Agenda
–
–
–
Last Month's Accomplishments
Drawing Release Plan
Issues and Concerns
2
11/3/2004
GLAST LAT Project
LAT Engineering Meeting
Last Months Accomplishments
•
•
Support of Mechanical Systems
– Released LAT-DS-01580, Grid Box Base Assembly
– Continued detail design efforts on MLI
– Continued documentation maintenance
Support of DAQ
– Released Cable Way detail parts
– Continued documentation maintenance
– Instrumentation
• Defined thermistor and accelerometer quantities and locations.
– Need to review with appropriate subsystems and update all
documentation
• Established basic harness definitions, connector locations, pin outs etc.
•
Top Assembly Documentation
– CAL-TEM Assembly Drawing submitted for release
– Reviewing Tower installation drawing with Design Integration
and I & T.
3
11/3/2004
GLAST LAT Project
LAT Engineering Meeting
Drawing Release Plan
Top Level Drawings
Document
Description
Issues
Release
ECD
Need Date
LAT-DS-01624
LAT Assembly Drawing
MLI design must be completed
4/30/2005
4/30/2005
LAT-DS-02561
LAT Tower & Elect Assembly Drawing
Instrumentation routings defined
12/3/2004
11/1/2004
LAT-DS-02560
LAT Tower assembly drawing
Finalizing instrumentation routing,
TEM clocking, tracker cable bonding
11/12/2004
10/1/2004
LAT-DS-02559
CAL-TEM-PS Assembly drawing
In review cycle with changes based
on NRL review
11/10/2004
10/1/2004
Interface Drawings
Document
LAT-DS-00309
Description
ACD-LAT INTERFACE, IDD
Pending
Rev.
04
Issues
Updates complete, waiting for comments
Drafting
ECD
Submitted
for review
9/22
To Doc
Control
11/3
LAT-DS-00233
CAL-LAT INTERFACE, IDD
07
Received comments from NRL 10/28
LAT-DS-00040
LAT INSTRUMENT STAY CLEAR
12
Update ACD envelope, Flexure clearance, MLI Interface
Waiting for inputs from Spectrum
?
LAT-DS-00851
TRACKER-LAT INTERFACE, IDD
2
Received comments from I & T 10/28, need to resolve
Submitted
9/2
4
11/3/2004
GLAST LAT Project
LAT Engineering Meeting
Issues & Concerns
• Timely and Appropriate review of Documents
•
CAL Interface (CAL-LAT IDD LAT-DS-00233 Rev 07)
– 4 weeks to receive comments.
•
ACD Interface (ACD-LAT IDD LAT-DS-00309 Rev 04)
– Check print sent out for review, 9/22, waiting for feedback
•
MLI Blanket Design
– Conceptual design still in review by Spectrum
– The only feed back received since 9/7/04 is a request for additional drawing views on
10/28
– Note the additional work to provide views was not planned until conceptual design
approval was given.
•
Instrumentation
– Detail design of cabling over 50% complete, cooperation between subsystems is required
– Issues still open from last month
•
•
•
Instrumentation Termination Bracket design definition
Specific locations and mounting methods have been defined, need to be reviewed
Still need detail harness definition for accelerometers