Millennium Bridge
Group 12
Introduction
Opened 10th June 2000
Span 325m Suspension Bridge
What Happened and
Consequences
Swaying of up to
70mm
Panic and
discomfort
Bridge closed 12th
June 2000
Technical Factors
Contributing to the Disaster
Horizontal Forces
cause oscillation
Synchronous
Lateral Excitation
Accentuated
oscillation
Lessons To Be Learned
From the Disaster
Passive Damping
Viscous Dampers
and Tuned Mass
Dampers
Avoid 1.5Hz
natural freq when
building bridges!!