Upper Middle Road Grade Separation
Download
Report
Transcript Upper Middle Road Grade Separation
Upper Middle Road
Grade Separation Construction
Project Status Update
February 2009
The way it was.
The plan.
The construction of the Upper Middle Road (UMR) Grade Separation, located at the
Canadian National Railway crossing west of Appleby Line, is proceeding on schedule. The
initial phase which included the road and rail detour construction opened October 6, 2008.
The contractor is now working on the rail bridge foundations and piers as well as beginning
the excavation for Upper Middle Road to pass under the bridge.
Where we are today!
North abutment.
Note the texture on the
form panel, this is what
will be the impression
left on the concrete
when complete.
Centre piers.
Each of two piers
will support the
two tracks when
the bridge is
complete.
South
abutment footing.
Heat being
pumped to
underside of
footing to prevent
frost.
Rock
Excavation
Future Upper Middle Road
Road
profile,
see also
next
slide.
Final Underpass Design
Road
profile,
see also
previous
slide.
Project Schedule:
Phase
Description of Work
Tentative Timeline
Construction Stage 2
Bridge construction
September 2008 to June 2009
Construction Stage 3
Bridge Completion - Transfer CN tracks from
temporary alignment to new bridge
Early June 2009
5-day road closure required *
Road works
Transfer UMR from the detour to under bridge
June to October 2009
Two 3-day road closures required *
Construction Stage 4
Road works, grading and landscaping
October to November 2009
Construction Stage 5
Project Completion
Top layer of asphalt and project wrap up
Spring 2010
* The exact dates and times will be confirmed as the work on the site progresses.
We would like to thank you for your co-operation throughout this project.
Project Contact
Bob Jurk
Phone 905-335-7600 ext’n 7682
Email: [email protected]