The London Millennium Bridge
Wobble
Group 12
Contents





Description
Problem
Explanation
Solution
Questions
Bridge Description



Shallow
suspension bridge
Deck supported by
cables
Prefabricated steel
V-brackets
Problem




Opened 10th June 2000
80,000 to 100,000 people
Unexpected sideways movements
Closed 12th June 2000
Explanation






Oscillating pattern of forces
Vertical and lateral forces
Spread feet apart to regain balance
“Lock-in” phenomenon
Motion further amplified
“Synchronous lateral excitation”
Explanation





Excitation increases with movement
Damping capacity remains constant
Lateral force increases
Lateral force becomes greater than
damping force
SLE occurs
Explanation
Solution




Add passive
damping
Increase resistance
to vibration
Greater pedestrian
load
Reopened Feb. 2002