Sandy Run Watershed Flood Mitigation Final Report Team #4 Alison Hafer
Download
Report
Transcript Sandy Run Watershed Flood Mitigation Final Report Team #4 Alison Hafer
Sandy Run Watershed Flood
Mitigation Final Report
Team #4
Alison Hafer
Mike Shinton
Chris Naab
John Zollers
Steve Welsh
Location
Problem Background
Development
Residential
Commercial
Highly Developed in Past 20 Years
Location
Causes of flooding
Combined discharge
Three watersheds
Channel path
Problem Background
Several floods have occurred in this area
Some prominent examples
Hurricane Floyd
Overtopping of the Loch Alsh Reservoir
Problem Background
Tropical Storm Allison
Resulted in washout of a SEPTA bridge over Sandy Run
on the R5 Lansdale line
Introduction
Three independent watersheds
Analyzed individually
TR-55 Analysis
Development
Soil types
Topography
Hydrograph
Hydrographs
10 yr Composite Runoff Hydrograph at Wissahickon Creek
3500
Total
Pine Run
Rapp Run
Sandy Run
3000
Flow (cfs)
2500
2000
1500
1000
500
0
10
15
20
25
Time (hours)
30
35
Introduction
Criteria for success
Reduces the risk of flooding and damage
Does so economically
“Do no harm”
Two approaches
Water detention
Increase channel velocity
Introduction
Alternatives evaluated
Detention basins
Impoundments
Rain barrels and gardens
Channel Improvements
Best Practices
Introduction
Detention basins
Temporarily store runoff
Two types
Surface
Subsurface
Impoundments
Mini in-stream dam
Runoff is stored upstream
Introduction
Rain barrels
Store roof runoff
Varying sizes and applications
Rain gardens
Vegetative area that promotes infiltration
Public and private
Detention Basins
How do they
function
Reduce peak flow
Release storage
Detention Basins
Basin selection
Develop local
hydrograph
Size basin
Outflow vs Elevation
Modified Puls routing
Detention Basins
Final design
Two surface basins
Two subsurface
Results
5% peak reduction
Detention Basins
Other Issues
Localized flooding
Do no harm
Not economically
feasible
Detention Basins
Cause of minimal impact
Service area too large
Inadequate storage capacity
Feasibility
Many small surface and subsurface basins
Allow slow release
Impoundments – In-Stream Detention
Designed to retard the movement of runoff through the watershed
Flow is restricted by a concrete structure (mini-dam)
Can fail-safe through overtopping
Behaves like a quickly filling dam
Impoundments
Two suitable locations
were identified
Site characteristics
estimated using
topographic maps
Maximum height of water
limited to prevent local
flooding
Impoundments
Water Height (ft)
Outflow vs Height
10
8
6
4
2
0
0
200
400
Outflow (cfs)
600
Impoundments
Performance is limited by the storage area the
location is able to provide
The size of the opening is adjusted to dictate the
rate at which the impoundment fills
The impoundment reduces the peak outflow by
transferring inflow to storage
IDEAL IMPOUNDMENT PERFORMANCE
180.0
8.0
INFLOW HYDROGRAPH
OUTFLOW HYDROGRAPH
7.0
WATER LEVEL IN RESERVOIR
140.0
6.0
120.0
Q (cfs)
5.0
100.0
4.0
80.0
3.0
60.0
2.0
40.0
1.0
20.0
0.0
0.00
5.00
10.00
TIME (hours)
15.00
0.0
20.00
WATER LEVEL IN RESERVOIR
(ft)
160.0
RAPP RUN IMPOUNDMENT PERFORMANCE
9.0
200.0
INFLOW HYDROGRAPH
OUTFLOW HYDROGRAPH
WATER LEVEL IN RESERVOIR
160.0
140.0
8.0
7.0
6.0
Q (cfs)
120.0
5.0
100.0
4.0
80.0
3.0
60.0
2.0
40.0
20.0
1.0
0.0
0.0
20.00
0.00
5.00
10.00
TIME (hours)
15.00
WATER LEVEL IN RESERVOIR
(feet)
180.0
Impoundments
In-stream impoundments are not feasible in this
watershed
Available storage areas are far too small to handle the
amount of runoff generated
Homes are situated too close to the flood plains which
reduces the storage area
Available impoundment locations are too far
downstream
Estimated cost of $43,000 each
Rain Barrels
Rain barrel system
design
54 gallon rain barrel
Includes all necessary
installation equipment
Capacity doubled to
108 gallons by stacking
two rain barrels
Rain Gardens
Vegetated areas that store runoff and promote
infiltration and transpiration
Rain Gardens
Small scale applications
Typical residential rain gardens
Surface area = 50 ft2
Depth = 0.5 ft
Plants
• Water-tolerant trees
• Shrubs
• Herbaceous plants
Large scale applications
Rain Barrels and Rain Gardens
Best case scenario: 0.013 inches of runoff held
Density of 10 houses/acre would hold 0.1 inches
Subsurface Runoff Storage
Stores runoff on-site
Intended for commercial sites
Underneath parking or other open area
Feasible for other locations as well
Stored water ideally infiltrates into soil
Most local soil infiltrates too slowly
Detained water will be drained into streams
Slow drainage rate effectively removes stored runoff from the
hydrograph
Subsurface Runoff Storage
Three possible options explored
Subsurface gravel storage bed
Water stored between voids in gravel
Subsurface storage structure
Water stored in underground pipes or structures
Rain garden with volume storage bed
Combines storage space and rain garden to hold water
and promote infiltration and transpiration
Subsurface Runoff Storage
Sample designs
Designed for site
pictured at right
Hold runoff from a
2-year storm that
falls over the entire
site
Drain storage area
within 2-3 days
Subsurface Storage: Option 1
Gravel bed with 40% void space stores water in
voids
Runoff routed into gravel bed via porous
pavement and/or edge drains
Geotextile protects gravel from contamination by
fine-grained soils
Perforated geopipe drains gravel at a rate of ~0.3
ft3/s
Subsurface Storage: Option 1
Subsurface Storage: Option 2
Underground storage which utilizes some
structure (often pipe) to store water
More efficient use of space than gravel
Routing of runoff into storage and drainage after
rainfall unchanged from gravel storage
Has potential to store water from larger storms or
from adjacent land areas
Subsurface Storage: Option 2
Subsurface Storage: Option 3
Rain garden with storage area
Sand storage area beneath a planting bed
Combines volume storage with infiltration and
transpiration-promoting plants
Requires considerable open space but also includes
aesthetic and environmental benefits
Most effective in locations that already have soil
that supports some infiltration
Subsurface Storage: Option 3
Subsurface Runoff Storage
Best Practices
Runoff controls are already required for all new
construction
Runoff controls should additionally be required for
renovation and reconstruction of existing facilities
To encourage runoff detention efforts, subsidies
or tax credits should be offered to landowners to
control runoff beyond the minimum requirements
Best Practices
Newly constructed housing should include rain
barrels and rain gardens to supplement local
detention basins
Adds less than 1% to cost of most new homes
Their installation can be encouraged in at
existing homes with tax credits or subsidies
Channel Improvements
Current channel path causes slow down in
stream flow
“Question mark” shape
It is narrow which doesn’t allow a larger flow
during storms
Bridge area also affects the flow
Make changes to improve flow and protect
commercial areas adjacent to stream
Channel Improvements
Channel Improvements
Channel Improvements
Improvements include excavation and
construction of a high flood wall
Three options
Short area near railroad bridge
Long area
Long area with stream widening
Channel Improvements
Channel Improvements
Short area
Excavation of islands and small areas along
parking lots
Construction of flood wall adjacent to parking
lots and railroad
Channel Improvements
Channel Improvements
Long area
Excavation of islands and small areas adjacent
to commercial areas
Construction of flood wall from railroad bridge to
Route 309 & PA Turnpike ramps
Channel Improvements
Channel Improvements
Long area with stream widening
Excavation of islands and large unused areas to
widen stream channel
Construction of flood wall from railroad bridge to
Route 309 & PA Turnpike ramps
Channel Improvements
Channel Improvements
Estimates
Most costs associated with excavation and flood wall
construction
Short Area
$1,404,000
Long Area
$1,639,000
Combination
$2,800,000
Channel Improvements
Cost Benefit
Local commercial areas have suffered flood
damages in the past
R & S Imports had approx. $1.4 million in damages in
a storm a few years ago
Using at least one of the options would probably
help in preventing or lessening flood damage.
Channel Improvements
Future work/considerations
Hydrologic study to determine effects of
improvements
Make use of a physical model
Use of parking lots to make a uniform stream width
Analyze downstream effects if improvements are
implemented
Channel Improvements
Channel Improvements
Engineering Budget
Updated time
allocation for
certain areas
of the project
and
overhead
costs
Total
estimate:
$147,000
Rain Barrel Estimate
Double unit system costs
Rain Barrel Solution Estimate (Double Unit)
Rain barrel
Shipping
Miscellaneous
installation
Object
Quantity
Cost
Total
54 Gallon
Rain Barrel
2
$290.00
$290.00
Shipping Cost
per barrel
2
$21.00
$42.00
Installation
1
$50.00
$50.00
Subtotal
$382.00
Overhead
Total Estimate: $460
Residential Rain Gardens
Estimate: $300
Overhead
$75.00
Total Estimate
$457.00
SAY
$460.00
Subsurface Detention
Subsurface Gravel Bed
Excavation
Gravel and asphalt
Geotextile
Total Estimate: $950,000
Rain Garden
Excavation
Mulch and topsoil
Vegetation
Volume storage sand
Total Estimate: $1,200,000
Schedule
Conclusions
Final solution encompasses entire watershed
There is no immediate short-term solution
Channel Improvements have potential
Require more research to design
Long-term solution requires changes in design
practices