Transcript MICE VC 141 16 June 2011 1. MOM is now Victoria 2.

MICE VC 141 16 June 2011

1. MOM is now Victoria 2. Linda Coney is new MICE Online Group coordinator (rep Jean-Sebastien) 3. 23-25 May we held a MICE cost and schedule review (organized by Andy Nichols) see agenda and presentations. https://indico.cern.ch/conferenceDisplay.py?confId=136454 Please note that this is an internal review and that the information contained in the talks is not "MICE-official"!

Aim: prepare schedule for MICE MPB report on June 28 . Reviewers: Marzio Nessi (CERN), Jim Kerby (FNAL), Phil Atkinson (DL) 4.Next boards MICE Project Board 28 June (see agenda enclosed) MICE Funding agency committee 14 July 5. MICE goals unchanged. Target tests in coming MPs. Commissioning and restart of MICE in MP run 27Jun-4Juy. 6. Next MICE collaboration meeting July 6-9, 2011 - Oxford do register! 7. INSS school and NUFACT11 (see http://nufact11.unige.ch

)

1

Schedule review highlights

23-25 May we held a MICE cost and schedule review (organized by Andy Nichols) see agenda and presentations. https://indico.cern.ch/conferenceDisplay.py?confId=136454 Please note that this is an internal review and that the information contained in the talks is not "MICE-official"!

Aim: prepare schedule for MICE MPB report on June 28 . Reviewers: Marzio Nessi (CERN), Jim Kerby (FNAL), Phil Atkinson (DL)

Step I

1. The EMR test run in July is confirmed (EMR has arrived!) 2. The full EMR data taking delayed to the winter period (February-March 2012)

MICE VC140 19-05-2011 Alain Blondel 2

Schedule review highlights

Step IV

1. There is now a schedule and milestones for the spectrometer solenoids, the manpower has been considerably reinforced, decision on the quench protection system leaning to passive for the magnet, reinforced for the leads 2. The first AFC magnet has been wound and a schedule exists for commissioning at RAL in the fall of this year (2011) 3. the LH2 absorber number one is on its way to RAL from Japan. 4. the LH2 R&D is progressing well in the MICE hall, next milestone July 2011 with LHe filling, final results by the end of 2011 5. the solid absorbers are getting defined and the diffuser in construction at Oxford. 6. and as can be expected there is some head-scratching to do to dispatch efficiently all these activities between the MICE Hall/R9 at RAL

MICE VC140 19-05-2011 Alain Blondel 3

MICE VC140 16-06-2011 Alain Blondel

Roy Preece

4

Schedule review highlights

Step IV (CTD)

7. Controls and monitoring are taking shape -- this is becoming a real cornerstone and urgency of the experiment, volunteers are more than welcome to join, please get in touch with Pierrick Hanlet. 8. Software organization is evolving to a more structured and controlled environment -- help from every involved MICE is important Taking all into account, this leads to a new schedule of MICE step IV in time for the MPB on 28 June and final approval by MICE at the next collaboration meeting.

MICE VC140 19-05-2011 Alain Blondel 5

• • •

Step IV Step V Step VI MICE Top-Level Project Schedule

Revision date: 17

th

June, 2011

• •

Note: items in red text key schedule drivers Items in orange text are high risk items

Andy Nichols

STEP IV

Subsystem Spectrometer solenoid #1 + #2 Fibre tracker #1 + #2 Focus coil #1 LH 2 system A

Solid absorber(s)

Liquid absorber

Diffuser Virostek plate

Substation upgrade

EMR installation Radiation shutter AFC Moving platform #1

Date June’12 Ready Sept’11 Dec ‘11

June ‘12

Ready

June’11 Feb. ‘12

Ready

Dec’11 June ‘12 Nov’11 7

Step IV ready...Q3, 2012

8

Step IV running

Can start running for cycle 2012/03 (2 October 2012) As will become apparent later STEP IV running is a parameter that is under our control -- Minimum program -- Liq H2 full and empty. -- solid absorbers LiH, plastic, aluminium, Titanium additional program (optional) -- Liq He -- other solids: Be, C, Cu -- totally empty AFC module change-over time: 8 working days between solids running time two weeks each configuration conclusion to be discussed: minimum program is 3 ISIS cycles (e.g. October 1 2012 till 24 March 2013) and full program is 5 ISIS cycle (i.e. until August 2013)

Schedule review highlights

Step V

1. Main schedule driver is now RFCC module as full construction scheme of CC magnet is still under discussion. 2. thus we are not ready to commit to a step V schedule 3. There is a hard date: next ISIS long shut down is August 2014-April 2015 4. There is considerable progress in the understanding of the RF power and installation 5. Punchline: from the moment where both A. Step IV running is complete B. The RFCC module is delivered at RAL it will take one full year to prepare the experiment to step V. 6. executive policy to be proposed IFF the step IV running is in the way of installation of step V we should give priority to step V

MICE VC140 16-06-2011 Alain Blondel 9

SCENARIO I IF RFCC module can be delivered to RAL before April 2013 then we can achieve significant running of Step V before the long shut down We will now investigate with US colleagues how realistic this can be Otherwise we may consider other strategy. (even going directly to step VI)

MICE VC140 16-06-2011 Alain Blondel 10

STEP V is conditionned by RFCC module

Subsystem

Step IV data-taking complete

Absorber Focus Coil #2 LH2 system B

RF Amplifiers

RF Infrastructure Successful test of first CC coil RFCC #1

AFC Moving platform #2 RFCC Moving platform #1 ISIS Long shutdown start ISIS Long shutdown end

Date

Q1 2013

Q4 2011 Q1 2013

Q3 2013

Q3 2013 Q4 2011 Q1 2013

Q4 2012 Q4 2012 Aug 2014 Feb 2015 11

Step V ready... Q2, 2014