Transcript Document

2013 Roads and Sidewalk Capital
Programs
Roads and Parks Maintenance Department
Development & Infrastructure Division
December 2, 2013
Presentation Outline
– Provide an update on 2013 Capital funded
programs
• shave and pave
• crack sealing
• rural resurfacing
• sidewalk replacement/repair
– Successes
– Going forward
Shave and Pave
What is it ?
•
•
•
•
•
•
•
•
Milling road surface –curb to curb
Minimum milling depth 40 mm
Drainage improvements – curb/catch basin rebuilds
Placement of top coat of asphalt – re-establish road crown and drainage
pattern
No changes to the road cross section – width or longitude high points
Beginning to end – typically 4 weeks on a road
Minimum design required
Generally warranted once or twice over roadway life cycle
Shave and Pave
When to use it?
• Signs of pavement
distress:
• Alligatoring (crossing of
cracks)
• High density of
longitudinal/transverse
cracking
• Pavement oxidization
(brittle)
• Loss of road crown
• Poor road drainage
Shave and Pave
• 2013 program:
– Original scope – 35 roads – 14
lane/km.
– Early tendering led to unit costs
lower than budgeted
– Additional 19 roads included – 12
lane/km.
– Construction start – late May
– Completion – Early December
Crack Sealing
What is it?
• Preventive maintenance techniques to extend the life of a
pavement structure
• Process of creating a flexible, waterproof seal, in and over
a road crack or joint
• Prevents water from entering the crack and causing further
damage through freeze/thaw cycles
• Generally will extend the road life cycle by 3 to 5 years
before shave and pave is required
Crack Sealing
What is it ? con’t
• Road cracks are mechanically
routed to a depth and width of
approximately 40 mm
• Modified hot polymer bituminous
sealant is applied in the prepared
crack
When to use ?
• Initial signs of road surface
deterioration
• Approximately 55,000 linear
metres of road cracks were filled
on 20 road sections
Rural Surface Treatment Program
What is it?
•
•
•
Surface treatment is city standard for
rural roads
Tar and chip
– Asphalt emulsion is applied /w
– Layer of stone chips
– Driveable within a short period of
time
Guide rails, drainage and road base
conditions are inspected and repaired
in advance, as required.
Rural Surface Treatment Program
2013 Rural Road Program:
• 138 lane/km in the rural area
• 6 year cycle with focus on
building road base
• 20 to 25 lane/km of roadway
completed yearly
• Once roadway bases have been
improved, other smoother micro
paving surface materials will be
placed in 2017
• Improved rider comfort
Sidewalk Program
What is it?
• Program developed to provide a safe walking surface for
pedestrians by addressing trip ledges
• City has approximately 800 km of sidewalk
• Ontario Regulation (239/02) requires sidewalks to be
inspected annually
• Inventory increases as additional sidewalks are constructed
• Implementation of replacement and repairs program needs to
be systematic and focused to meet level of service
requirements
Sidewalk Program
Annual Inspection:
• GPS and mobile computing used in the spring
• All 800 km of sidewalk was inspected and trip ledges
marked by 4 staff – completed in 18 working days
• Trip ledges were organized into 2 categories
– 40 mm +++ ( to be replaced)
– 15 mm to 40 mm ( to be ground or mudjacked)
Sidewalk Program
2013 Program
• Early start for replacements
and repairs
• Improved tendering
requirements
• 2 contractors used with
specific tasks assigned to
each
– Remove and replace slab and
grinding ledges
– Other - Mud jacking
2013 Sidewalk Program
2013
Program
# of Trip
Ledges
Completion
Rate
413
100%
Trip Ledges 15
mm to 40 mm
10,400
90 %*
Total
10,813
Trip ledges >
than 40 mm
• Priority was given to replacement
of the 40 mm +++ trip ledges –
greatest risk to pedestrians
• Large amount of 15 to 40 mm trip
ledges required additional
contractor resources
• Any remaining will be completed
first in 2014
* weather permitting
2013 Sidewalk Program
Alternative Sidewalk Rehabilitation – Context Sensitive
• When sidewalk locations impact the root system of mature
trees
• Guidelines developed with city forestry group.
• Evaluated by an Arborist to determine appropriate technique.
Key Successes
1. Early tendering for the shave and pave program led to lower than budgeted unit
costs, allowing a second group of roads to be added to the program.
2. Early completion of the sidewalk inspection program allowing for repairs to
proceed early in the summer with a high repair/replacement completion rate.
3. Continued road base repairs on rural roads will enable the future application of
alternative smoother surface materials for road users.
4. Development of context sensitive sidewalk replacement techniques to minimize
impact on tree roots.
5. Continued coordination of activities and resources between Roads and Parks
Maintenance and Engineering.
Staff well positioned to manage additional roads as funds become available
Going Forward
2014 Capital Program:
• Shave and Pave Program- $2,500,000 budget
• 3 year shave and pave program being developed
• Rural Resurfacing and Crack Sealing - $380,000 budget
• Continuation of 6 year rural resurfacing and crack sealing programs
• Sidewalk Repair/Renewal - $350,000 budget
• Inventory collection and replacement repairs, as identified
2013 Roads and Sidewalk Capital
Programs
Questions ?