Project Overview
Download
Report
Transcript Project Overview
Washington Avenue
Reconstruction Project
Public Informational Meeting
City of Chelsea
May 31, 2011
Why Project is Occurring
Poor Roadway Conditions
Separation of Sewer and Stormwater
Replacement of Water
Replacement of Gas (by National Grid)
What Does the Project Entail?
Project Details
Geographic Scope of the Work
Heard St to Route 16
Back of Sidewalk to Back of Sidewalk
Reconfiguration of Cary Square
Full-Depth Roadway Reconstruction Explanation
1. New Street Surface
2. New Sidewalks
3. Streetscape Amenities (Benches, Bike Racks, Trees,
Etc.)
What Does the Project Entail?
Funding Sources
Municipal Borrowings through General Obligation
Sewer and Water Bonds
Chapter 90 Funds
Community Development Block Grant Funding
MWRA Grant and Zero Interest Loans
Total of $6M+
What Does the Project Entail?
Project Construction Schedule
Water, Sanitary & Drain - Spring/Summer/Fall 2011
Streetscape – Spring/Summer/Fall 2012
Completion – Spring 2013
Project Schedule
•
•
•
Contract has been awarded to J. Marchese
and Sons
Work starts Monday June 6th
Work hours approximately 7 AM to 3:30 PM,
Monday through Friday
Construction Schedule
Construction Schedule
June Construction
July Construction
August Construction
Questions/Comments/Concerns?