Transcript Slide 1

Regional Intermodal Transportation Center
PROJECT COMPONENTS
-
Consolidated Rental Car Facility
New Bus Transit Station
Elevated Moving Sidewalk
1,043 space Replacement Parking Structure
Improvements on City of Burbank Streets
Linkage between Train Station and Transit Station
and moving sidewalk
- Skies of Freedom Pavilion
- Art Columns
PURPOSES OF PROJECT
- Runway Safety Area Issues
- Transit Connectivity/Intermodal Development
- Rental Car Need
- Sustainability
- Passenger Convenience
- History and Art Realization Program (“HARP”)
CHALLENGES OF THE PROJECT
- Economic downturn – five years continued
passenger loss with one third decline in passenger
levels from peak
- Bidding – Conditions that created need for designbuild structure within a design-bid-build project
- Federal agencies create funding silos for intermodal
- 24/7 Operation of an Airport
- Safety! Safety! Safety!
- Client Coordination – Understand Your Client
- Design Management
- Regulatory Agency management
- Construction Management is really:
Cost/Budget/Schedule/Change/Error/Inspection
Management
SAFETY! SAFETY! SAFETY!
- Create culture of safety throughout entire project
- Everyone entitled to stop an unsafe act
- Safety more important than schedule or budget
- OCIP/OCIP Benefits—RITC has no lost time days
since award of construction contracts—Team effort
pays off
CLIENT COORDINATION
(Give the Owner What It Wants)
- Clear understanding of project objectives
- Written log of Owner requests and responses
- Do not wait for the Owner to come to you-actively
and continuously seek client input
Consider using the PM/CM to provide pre-bid services
Need for using PM/CM for pre-bid services varies from
Owner to Owner and project to project
The following list of pre-bid considerations should be
done in any case, whether by PM/CM, Owner, architect
or other entity
DESIGN MANAGEMENT – PRE BID
-
NO ASSUMPTIONS
-
Hold Architects accountable to deliver project objectives while maintaining
project schedule, budget and deliverables
-
Architects work on their own vision, unless directed otherwise
-
Details, Details, Details – the Devil is in the Details
-
Make sure Owner is on board with Architect’s path
-
Clarify extent of deferred submittals-know the regulatory agency requirements
-
Construction Documents free of Errors and Omissions
-
Ensure that:
• on site conditions are recorded – seen and unseen
• a photo record all surface conditions is included as a part of construction
documents
• photo records are complete and show existing conditions (inside of vaults,
electrical cabinets, utility closets, attics, basements, conveyor tunnels, etc.)
• underground investigation is conducted before bidding
• potholes are dug near and around all critical utilities
DESIGN MANAGEMENT – PRE BID
-
Coordinate design RFIs with Owner and potential contractors
-
Protect the Owner by ensuring quality of Plans and Specifications:
• Establishing Owner versus Contractor responsibilities
• Read the Plans and Specifications – ALL OF THEM
• Understand the project better than the Contractor
• Make the project buildable. Show access points, laydown and staging
areas, temporary utility point of connections,
• “General Notes” on lead sheet of drawings, and “General Notes” on
trade drawings apply to Contractor and Subcontractors alike
• Ensure documents clearly hold contractor responsible for ensuring
subs know the scope for their trades
• Say it once and in the right place
• Never allow the words “By Others” anywhere in the Construction Docs
REGULATORY AGENCY MANAGEMENT
- Intermodal Project means a multitude of agencies
•
•
•
•
•
•
•
•
•
•
City of Burbank
FAA
FHWA
FTA
Metro
Union Pacific Railroad
Amtrak
County of Los Angeles
AQMD
SCRWQCB
CONSTRUCTION MANAGEMENT IS REALLY COST, BUDGET,
SCHEDULE, CHANGE, ERROR AND INSPECTION
MANAGEMENT
-
Primary responsibility is enforcement of Owner contract with all
entities, including the prime contractor, designers, inspectors, etc.
• Document file with emails, notes, confirming letters, photos so
that there is a paper trail in the event of future dispute.
• Resolve change orders quickly
• Don’t allow out of scope work to be performed without knowing
the cost beforehand
• Don’t negotiate cost without negotiating time/delay
• Don’t hesitate to recommend additional specialty inspection
resources if the project dictates it (roofing, special tiling, etc.)
• Crack the whip on any recalcitrant team member, not just the
contractor
KNOW YOUR CLIENT
- Understand the level of communication/interaction
that makes the Owner’s staff comfortable and keep
them well informed
- Listen to the Owner and document requests
- No surprises – Most Owner Staff members report to
a governing body, such as a Council or a
Commission that really is the Owner, and these
bodies hate surprises