Transcript Slide 1

GEORANGE
Är Järn Guld för Pajala ?
2 april 2009
Planned Iron Ore Mining in
the Pajala/Kolari Region
Karl-Axel Waplan
MD of European Operations
April 2, 2009
1
Infrastructure
Key events
• MOU signed with operator as well as port authorities to develop
Kemi port for the initial tonnage
• MOU signed with GIIC on long term shipment of concentrate
from the Pajala/Kolari area
• Consortium organized to support the development of the Rail
transportation to port; NRI, Bombardier and VR
• EPA Filed April 1, 2009
• Application to the Border River Commission to be filed
May/April
April 2, 2009
2
MoU with GIIC
Contractual Year
2011
2012
2013
2014 onwards
April 2, 2009
Annual Basic Quantity (in WMT)
250,000
1,500,000
2,000,000
3,000,000
3
Investment Highlights
Investment Highlights
• Focus on Tapuli, Hannukainen, Stora Sahavaara and Pellivuoma
• Management priority is developing early cash flow
– start up of Tapuli mine with Kaunisvaara mill
• Existing infrastructure support early production of up to 2-3 Mt pa
• Resource base growing
• Staged growth of production up to 8-10 Mt pa of iron ore products
April 2, 2009
4
●Kaunisvaara
April 2, 2009
5
Fast Track Tapuli
Tapuli: Fast Track to Cash Flow
• Open-pittable resource
• Existing infrastructure can take Tapuli’s full production
with minor upgrades
• Preliminary studies suggest lowest CapEx, highest IRR
and quickest payback
• Synergies with nearby Stora Sahavaara and Pellivuoma
projects
April 2, 2009
6
Tapuli mine
•
•
•
•
•
Open cast mine
Minimum operation time 10 years
Verified resource 65 Mton (NI 43-101)
Additional reserves ca 40 Mton
Blasting daytime, ca 1-4 times/week
April 2, 2009
7
Temporär sedimenteringsbassäng
och översilningsyta
Planned industry layout:
Gråbergsupplag
•Mine
•Mill
•Service facilities
Sandmagasin
Klarningsmagasin
Kaunisvaara
anrikningsverk
Processvattenbassäng
•Office
•Waste rock deposit
•Tailings storage facility
•Access & transportation roads
1:32 000 (A3)
April 2, 2009
8
Artists impression of the mine during operation
April 2, 2009
9
Waste rock
• A total of 250 Mton will be mined
• May be used for construction purposes
• Area ca 330 ha
• Height ca 75 m
April 2, 2009
10
Anrikningsprocess
• Planerad genomsnittlig produktion
År 1:
3 Mton malm, motsvarande ca 1 Mton Slig
År 2-10:
10 Mton malm, motsvarande ca 3 Mton Slig
Ansökan avser 20 Mton per år
• Process
Krossning, malning, magnetseparering, avvattning och möjligen torkning
Inget flotationssteg
Magnetic separators
Dewatering
Grinding
Concentrate
storage
Storage ore
Storage crushed
ore
April 2, 2009
Thickeners
11
Mill tailings storage
• Total tonnage c. 70 Mton
• Total area c. 340 ha
• Final height c. 60 m
ca 2-3 m
April 2, 2009
12
Efterbehandling
• Byggnader tas bort och vägar återställs. Ledningar kvar i marken.
• Gråberg täcks med morän och vegeteras. Sandmagasin vegeteras.
Gödningsmedel kan behöva tillföras.
• Dagbrottet bildar en sjö
April 2, 2009
13
Transport
• Initially truck (60 ton net) to Kolari – rail to Kemi
• Extension of railroad to Kaunisvaara being investigated
• 290 return transports per day (c. 12 per hour)
April 2, 2009
14
Transloading station alternatives
April 2, 2009
15
8000
7000
6000
5000
4000
3000
2000
1000
0
Hannukainen
Sahavaara
Pellivuoma
2031
2029
2027
2025
2023
2021
2019
2017
2015
2013
Tapuli
2011
kt/year
Tentative production schedule
production year
April 2, 2009
16
Rail & Port Options
Narvik
Pajala
Kolari
Existing
rail link
Kalix
Kemi
Luleå
April 2, 2009
17
Infrastructure
Logistics – Key issues
• Initial transportation Kaunisvaara – Kolari on road
• Long term solution Kaunisvaara – Kolari to be railroad
• Increase capacity on rail from Kolari region to Tornio up
to 10 Mt
• Develop Kemi port initially for 3 Mt and up to 10 Mt in
case Kemi is the only port going forward
• Kemi port dredging to enable access by feasible vessels
April 2, 2009
18
Infrastructure
Transportation from Kaunisvaara/Tapuli
to Finnish Rail
• 2011 – 2013 trucking
• Rail alternative is studied
• Alternative studies on pipeline and conveyor belt in
progress
• Future solution operational from 2012/13
• Loading station south of Kolari, land available
• Rail – Necassary
April 2, 2009
19
Northland’s Future Growth
Production Timeline Estimate
2013 / 2014
2012
• Tapuli – ramp up
production to
1.5Mt Concentrate
2011
2010
• Tapuli – Begin
production of
Concentrate
• Pellivuoma –
begin production
of Concentrate
April 2, 2009
• Pellivuoma – ramps up
production to 1.5 Mt of
Concentrate
• Stora Sahavaara – begin
production of 2 Mt of
Concentrate
• Hannukainen begins
production and ramps up
to 2-3 Mt of DR pellet feed
• Tapuli – Begin
construction
Production:
• Tapuli at full production
1.5 Mt Concentrate
1-2 Mt/y
3 Mt/y
8-10 Mt/y
20
Summary NRI projects
• Staged development to build the assets in
Sweden and Finland
• Initial cash flow will be the base to increase
production and employment
• Joint effort necessary - NO “Finnkamp”
• The projects will create employment within
NRI as well as support structures, services etc
• Employment will be created in the whole
region – in both countries
April 2, 2009
21
Summary Logistics
• Rail Kaunisvaara – Tornio with capacity + 8 Mt
necessary for development of the projects
• Rail from Kaunisvaara to be operational from
2013
• Port development Kemi ready 2011
• Dredging Kemi ready 2011/12
• Ice breaker capacity must be expanded
April 2, 2009
22