Davis-Woodland Water
Supply Project
Agency Board
July 15, 2013
Upcoming Activities/Milestones
June - July 2013
PROJECT FUNDING
• Continue to pursue SRF low interest loan and grant funding
opportunities
Project added to Clean Water SRF Project funding list
• West Side IRWMP approved
DWWSP highly-ranked
• $10m in State grant funding for Joint Intake included in
approved State Budget
2
Upcoming Activities/Milestones
June – July 2013 (cont’)
LAND AND ROW ACQUISITIONS
• Continue work with Yolo County regarding
encroachment permits/road construction
 Meeting with Yolo County on July 9
• Complete acquisition of Heidrick/McGinnis, Lillard,
Turner, and Oates easements
• Complete land and easement agreements with City of
Davis
• Continue eminent domain actions on 3 parcels
PLANNING, DESIGN, AND CONSTRUCTION
• Receive priced DBO proposal July 30th
3
Updated 30 mgd Project Costs
(April 2013 million dollars)
Construction Costs(a)
Capital Costs, 2009-2016
Component
Total
Woodland
Davis
Agency Administration
3.47
1.78
1.69
Program Management
4.19
2.21
2.00
Water Supply
1.69
1.23
0.46
Environmental & Permitting
1.48
0.75
0.72
Land/ROW Acquisition
4.19
2.13
2.06
23.99
Pre-Design
6.78
3.65
3.11
2.89
Construction
169.13
90.01
79.12
Capital Contingency
7.06
3.78
3.29
Woodland and Davis Local Facilities
31.74
16.75
14.99
Costs Expended Since 2009
7.49
4.01
3.48
126.31
110.91
Facility
Cost
Joint Intake (Agency Portion)
16.82
Raw Water Pipeline
23.66
Regional Water Treatment Facility
(RWTF)
96.32
Woodland Treated Water Pipelines
5.46
Davis Treated Water Pipeline
Permit Fees & Construction
Counsel
TOTAL 169.13
(a)
Includes DBO contract design and construction
costs, design-bid-build construction costs, and
Agency design review, construction management,
engineering services during construction,
environmental construction monitoring, and
environmental mitigation, permitting and incidental
costs.
TOTAL CAPITAL COSTS 237.22
4
Project Schedule Milestones
Task
Completion By
Complete RWTF Site Fill
November 2012
Obtain water rights for 10 TAF purchased from CPG
November 2012
Issue Final RFP for DBO Contract
December 2012
Approval of Project Final Engineering and Construction by
Each City
March 2013
Obtain USACE 404 Permit
July 2013
Secure Joint Intake Construction Funding
July 2013
Authorization to Proceed with Bond Financing by Each City
August 2013
Award DBO Contract
October 2013
Advertise Joint Intake Construction Bid Documents
October 2013
Joint Intake Construction Completion
DWWSP Acceptance Testing Completion
March 2016
September 2016
Updated: 07/15/13
5
Questions