Update on the Davis-Woodland Water Supply Project Agency Board February 20, 2014 Discussion Topics • • • • Recent Accomplishments Upcoming Activities/Milestones Project Cost and Schedule Update Mid-Year Budget Update.
Download
Report
Transcript Update on the Davis-Woodland Water Supply Project Agency Board February 20, 2014 Discussion Topics • • • • Recent Accomplishments Upcoming Activities/Milestones Project Cost and Schedule Update Mid-Year Budget Update.
Update on the
Davis-Woodland Water
Supply Project
Agency Board
February 20, 2014
Discussion Topics
•
•
•
•
Recent Accomplishments
Upcoming Activities/Milestones
Project Cost and Schedule Update
Mid-Year Budget Update
2
Recent Accomplishments
January-February 2014
GRANTS & LOANS
• Safe Drinking Water SRF Application for Woodland
Accepted: $143M for share of regional ($111M) and local
facilities ($32M)
• Woodland has 60 days to respond to offer
• Woodland eligibility based on lost well capacity due to
exceeding MCL’s (nitrate)
• Davis would be eligible upon consolidation of North Davis
Meadows or issuance of Chromium VI MCL
• Clean Water SRF Application: $211M for the regional
facilities
• Authority to issue 30 year loans approved by SWRCB and
EPA
• Consideration of Application by SWRCB continuing
3
Recent Accomplishments
January-February 2014
GRANTS & LOANS
• Continued pursuit of federal commitment for Joint Intake
funding
– $13.7M committed to date, additional $3M sought
– Outlook positive for receipt of remaining funds - Washington DC
trip confirmed for March 3 - 6, 2014
• Continued pursuit of state commitment for Joint Intake
funding
– $10M committed to date, additional $6.7M sought
– Working to have remaining funds included in FY15 State Budget
4
Recent Accomplishments
January-February 2014
PLANNING, DESIGN, AND CONSTRUCTION
• Received and reviewed CH2M Hill deliverables:
– Basis of Design Report and 30% design submittal
– Early Site Work and Mass Excavation 90% design
submittal
– Temporary Construction Facilities submittal
– Design-Build Period Insurance Certificates
• Received Permitting Matrix for review
5
Recent Accomplishments
January-February 2014
PLANNING, DESIGN, AND CONSTRUCTION
• Joint Intake Project bidding underway
• Four contractors pre-qualified:
•
•
•
•
Kiewit
Balfour Beatty
Overaa
Syblon Reid
• Engineer’s Estimate: $43,163,000
• Bids due March 5, 2014
• Construction financing and O&M agreements approved by both
WDCWA and RD2035
• Began injection testing for ASR project in Woodland
6
Recent Accomplishments
January-February 2014
ENVIRONMENTAL AND PERMITTING
• US Army Corps of Engineers 404 Permit and State 401 Water Quality
Certification pending
• Incidental Take Permit from California Department of Fish &
Wildlife (DF&G) required
• Updated proposals for Environmental Mitigation Credits received from:
• Westerveldt
• Wildlands
• Purchase of Credits required before initiation of Intake and
Transmission Main construction
• CDPH issued Conditional Approval letter for CH2M HILL proposed
design
7
Upcoming Activities/Milestones
PROGRAM MANAGEMENT
• Continue to pursue SRF low interest loans from Clean
Water Act SRF (SWRCB)
• Obtain federal and state commitments for remaining
share of grant funds for the Joint Intake
• Continue efforts to secure WAPA power at Joint Intake
• Continue efforts with PG&E re: improvements and costs
to serve RWTF and Joint Intake
• Complete Injection Testing for Woodland ASR Program
8
Upcoming Activities/Milestones
ENVIRONMENTAL AND PERMITTING
• Receive Incidental Take Permit from CA DF&G
• Obtain 404 Permit (US ACE) and State 401 Water
Quality Certification
• Complete negotiations for purchase of environmental
mitigation credits
9
Upcoming Activities/Milestones
LAND AND ROW ACQUISITIONS
• Finalize escrow for RWTF site purchased from
City of Woodland
• Complete negotiations for final property
easements:
– SNRR for transverse easement at Joint Intake site
– Lillard for Davis Finished Water Transmission Main
alignment
10
Upcoming Activities/Milestones
PLANNING, DESIGN, AND CONSTRUCTION
• Receive bids for Joint Intake Facility construction on
March 5, 2014
• Begin construction at Regional Water Treatment
Facility on April 8, 2014
• Complete plan with the Yolo County Farm Bureau
for Road 22 closure coordination
• Continue TerraVerde work on opportunities for the
use of renewable energy
• TerraVerde-CH2M HILL coordination regarding RWTF
electricity use
11
Upcoming Activities/Milestones
PLANNING, DESIGN, AND CONSTRUCTION
• CH2M HILL submittals for Agency Review:
• 100% Early Site Work and Mass Excavation design
submittal (March 2014)
• Final Basis of Design Report (March 2014)
• 90% Early Concrete Structures design submittal
(March 2014)
• 90% Process Equipment for Procurement submittal
(March 2014)
12
Upcoming Activities/Milestones
PUBLIC EDUCATION AND OUTREACH
• Groundbreaking Ceremony: April 10, 2014 at
10:00am
• Monthly Project Status Summary issued
February 17, 2014
• March/April water bill inserts prepared
• Construction “Hotline” card and Signage
prepared
13
30 mgd Project Costs Integrating Final DBO
Contract Price (Apr 2013 million dollars)
Capital Costs, 2009-2016
Construction Costs
Project Component
Cost
DBO Contract(a)
133.80
Agency Quality Assurance &
Contract Compliance(b)
10.73
Joint Intake
15.71
TOTAL
160.24
Cost Category
Total
Woodland
Davis
Agency Administration
3.47
1.78
1.69
Program Management
4.19
2.21
2.00
Water Supply
1.69
1.23
0.46
Environmental & Permitting
1.48
0.75
0.72
Land/ROW Acquisition
4.19
2.13
2.06
Pre-Design
6.78
3.65
3.11
160.24
84.85
75.39
Capital Contingency
6.84
3.60
3.24
Woodland and Davis Local
Facilities
31.74
16.75
14.99
Costs Expended 2009-2011
7.49
4.01
3.48
228.10
120.97
107.13
Construction
(a) Costs do not include potential additive bid
items for SRF loan compliance and additional
Woodland storage and pumping at RWTF.
(b) Includes Agency design review, construction
quality assurance and contract compliance,
submittal and RFI review, environmental
construction monitoring, environmental
mitigation, Agency permitting and incidental
costs.
TOTAL CAPITAL COSTS
14
CH2M Hill Expenditure
Projections
(Add Total
graph
from
CH
monthly
report
showing
billings through
January 31, 2014:
cumulative
billings by month. Add a bullet
$4,325,494
indicating billings to date.)
15
Construction Milestones
Task
Completion By
Advertise for Construction of Joint Intake Facility
January 2014
Award Joint Intake Facility Construction Contract
March 2014
RWTF Site Work Begins
100% Pipeline Design Complete
April 2014
September 2014
Pipeline/Offsite Construction Begins
October 2014
100% RWTF Design Complete
October 2014
Permanent Power On-site
Commissioning of RWTF Begins
September 2015
January 2016
Substantial Completion of RWTF and Pipelines
May 2016
RWTF and Pipelines Acceptance Test Completion
June 2016
Substantial Completion of Joint Intake
September 2016
Updated: 2/19/14
16
Mid Year Budget Update
• FY 14 Approved Budget: $32.15M
• Staff review of actual expenditures through
Dec 31, 2013 and projected expenditures
through end of Fiscal Year
17
Mid Year Budget Update
• Total Budget Savings of $1.31M
• Primary budget items where savings were
realized:
– Public Outreach: $60K
– DBO Procurement: $873K
– Water Rights assistance: $60K
– Regional Facilities Permitting: $85K
– Land/ROW acquisition assistance: $66K
18
Mid Year Budget Update
• Total Budget “Increases” of $2.25M
• $1.78M of total is for accelerated CH2M
Hill schedule
• Primary budget items for remaining $470K
include:
– SRF loan assistance for Woodland: $90K
– Property easement purchases: $87K
– 100% Intake Design: $72K
19
Mid Year Budget Update
CONCLUSIONS:
• Approved FY 14 Budget is sufficient to
cover expenditures for remainder of FY
– $900K of $1.86M contingency expected to be
utilized
• Current consultant contracts sufficient for
remainder of FY
• Agency will issue quarterly invoices to
cities per original invoicing schedule
20