Davis-Woodland Water Supply Project FY 14/15 Budget Agency Board Meeting June 19, 2014 Proposed FY 14/15 Budget at April 2014 Board Meeting Fiscal Year COST CATEGORY CAPITAL PROJECT 1.
Download ReportTranscript Davis-Woodland Water Supply Project FY 14/15 Budget Agency Board Meeting June 19, 2014 Proposed FY 14/15 Budget at April 2014 Board Meeting Fiscal Year COST CATEGORY CAPITAL PROJECT 1.
Davis-Woodland Water Supply Project FY 14/15 Budget Agency Board Meeting June 19, 2014 Proposed FY 14/15 Budget at April 2014 Board Meeting Fiscal Year COST CATEGORY CAPITAL PROJECT 1. Agency Administration 2. Program Management 3. Regional Facilities Design Criteria 4. Water Right Permits 5. Environmental & Permitting 6. Supplemental Water Supply 7. Land/RW Acquisitions 8. Pre-Design and Joint Intake Design 9. Construction - Agency Quality Assurance and Contract Compliance - DBO Design and Construction - Design-Bid-Build Projects 10. Capital Contingency SUBTOTAL CAPITAL PROJECT WATER PURCHASE BUDGET OPERATION & MAINTENANCE BUDGET TOTAL WDCWA COSTS Proposed FY 14/15 Budget $663,300 $633,000 $105,000 $329,000 $175,000 $0 $5,000 $15,000 $98,162,885 $2,757,792 $89,119,698 $6,285,395 $2,821,549 $102,909,734 $0 $0 $102,909,734 2 Proposed FY 14/15 Budget Fiscal Year COST CATEGORY CAPITAL PROJECT 1. Agency Administration 2. Program Management 3. Regional Facilities Design Criteria 4. Water Right Permits 5. Environmental & Permitting 6. Supplemental Water Supply 7. Land/RW Acquisitions 8. Design 9. Construction - Agency Quality Assurance and Contract Compliance - DBO Design and Construction - Design-Bid-Build Projects 10. Capital Contingency SUBTOTAL CAPITAL PROJECT WATER PURCHASE BUDGET OPERATION & MAINTENANCE BUDGET TOTAL WDCWA COSTS Proposed FY 14/15 Budget $692,000 $643,000 $105,000 $329,000 $175,000 $15,000 $24,000 $15,000 $91,818,000 $2,662,000 $82,073,000 $7,083,000 $2,662,000 $96,478,000 $0 $0 $96,478,000 3 April Draft FY14/15 Budget vs. Recommended FY14/15 Budget • FY14/15 budget reduced $6.4m: – (+) $675k shift in expected expenditures between FYs (based on CH2M Hill’s May 30, 2014 drawdown schedule) – (-) $7.0m for delayed payment of 10% private financing portion of DBO contract incorporated – (+) $97k for recently identified work activities – (-) $160k for capital contingency reduction 4 April Draft FY14/15 Budget vs. June Proposed FY14/15 Budget (cont’) • Budgets shifted between FYs: – (-) $75K for design review (Task 136) – (-) $20K for equipment submittal and RFI review (Task 138) – (-) $7.0M for delayed payment of 10% private financing portion of DBO contract (Tasks 147-150) – (+) $770K for delayed payment to PG&E for infrastructure improvements (Tasks 160 – 163) 5 April Draft FY14/15 Budget vs. June Proposed FY14/15 Budget (cont’) • Specific budget additions (+) and reductions (-): – (+) $26K for Agency’s contribution to Sacramento River Watershed Sanitary Survey Update (Task 7) – (+) $37K for additional management and construction oversight of joint intake project (Task 18 and Task 166) – (+) $15K for pursuit of supplemental surface water purchase (Task 61) – (+) $19K to finalize remaining three easements (Task 70) – (-) $160K reduction in capital contingency (Task 169) 6 FY 14/15 Major Budget Categories • Agency Administration ($692,000) – – – – – – – – Agency General Manager Agency Secretary Agency Treasurer Legal counsel Lobbyist Organizational membership & incidental costs Public outreach Administrative contingency (10%) 7 FY 14/15 Major Budget Categories • Program Management ($643,000) – – – – – Technical services to Agency & Cities Project monthly team meetings Joint Intake management Project budgeting & scheduling Grant and loan funding assistance • Regional Facilities Design Criteria ($105,000) – Alternative energy investigations – Water quality sampling 8 FY 14/15 Major Budget Categories • Water Right Permits ($329,000) – Completion of Supplemental EIR for ASR Program – Revision of water right permit for ASR • Environmental & Permitting ($175,000) – – – – Compliance w/ regulatory permits CDPH Domestic Water Supply Operating Permit Pond closure for solids drying bed site Regulatory, Utility, and Farm Bureau coordination 9 FY 14/15 Major Budget Categories • Supplemental Water Supply ($15,000) – Investigation of potential water purchase • Land & Rights-of-Way Acquisitions ($24,000) – Completion of Lillard easement purchase – Easement modifications to accommodate Willow Slough Bypass crossings • Design ($15,000) – Agency coordination with energy consultant – WAPA power application 10 FY 14/15 Major Budget Categories • Construction ($91,818,000) – – – – – – – – DBO contract compliance Agency permit fees and Farm Bureau reimbursement Agency review of the DBO design Agency review of construction submittals and RFI’s Construction quality oversight Environmental construction monitoring Payments to DBO for design and construction of DWWSP Joint Intake construction & engineering services during construction 11 FY 14/15 Major Budget Categories • Capital Contingency ($2,662,000) – 5% on engineering tasks – 3% of capital costs 12 Recommendation • Adopt Final FY 14/15 Budget • Consider Approval of Consultant Contracts 13 Questions 14