Transcript Slide 1
School District of Osceola County Facilities, Planning, Maintenance & Construction Monthly Update May/June 2009 7/20/2015 1 Report Contents 1. 2. 3. 4. Planning Services Division Update □ Concurrency □ Project Coordination with Local Government Permitting Services Division Update □ Activity Report – Permits, Inspections, C.O.’s □ Administrative Issues (No Updates this Period) Maintenance Department Update □ Portable Classroom Update □ Summer Projects Update □ Work Orders 2008-2009 Update Design and Construction Services Division Update □ Goals □ Capital Outlay Planned Projects Update □ Major Projects Status Summary □ New Schools in Development Update □ Project Highlights- Summary Cost Report Current Major Projects □ Tax Savings Summary – New Schools □ Major Projects Highlight Reports □ Request for Services (RFQ/RFP/Bid update) □ Working Issues 7/20/2015 2 Planning Concurrency The ILA was executed on May 12, 2009. The PSFE has been adopted by Osceola County, St. Cloud and the City of Kissimmee. Osceola County and St. Cloud have also adopted their implementing ordinances. With these dates, implementation of school concurrency will be in late July for Osceola County and St. Cloud and September for the City of Kissimmee. District Staff has been finalizing elements of the process for a smooth transition into concurrency. Until concurrency is implemented staff will continue to submit capacity reports to all local governments as comment for inclusion in their development review meetings and track all residential development TWG has been working together to gain a consensus for the administration and management of concurrency among all agencies and to facilitate the process for the applicants. 7/20/2015 3 Planning Project Coordination The Long Range Planning and Permitting Services staff is working with staff and other SDOC Departments and our local governments to coordinate projects for improvements to schools within the community. Examples of the projects include: o Working with County and City staff to develop an inventory and priority listing of new sidewalks needed near existing schools for pedestrian access. o Attendance at the Community Traffic Safety Team (CTST) meetings to discuss safe access to schools. o Coordination of plan review for Renovation and Classroom Addition projects at existing schools. o Data collection and information sharing for the development of long range student enrollment projections and future school siting. 7/20/2015 4 Permitting – Activity Report June 10 – July 10, 2009 7/20/2015 Inspections Recorded Certificates of Occupancy Certificates of Completion Permits Issued Month Total 66 0 8 12 YTD 791 58 99 116 5 Maintenance Department Portable Classroom Update Williams Scotsman Portables Removed 2009/2010 through present (198) $119,407.03 x 12 = $1,432,884.36 (annual savings) To be removed by end of July (2) $1,274.00 x 12 = $15,288.00 To be removed by August 8th (8) $4,964.00 x 12 = $59,568.00 To be removed by August 12th (10) $6,180.00 x 12 = $74,160.00 Mobile Modular Portables Removed July 2008 through present (6) $ 675.00 x 12 = $48,600.00 Total savings Williams Scotsman Mobile Modular 7/20/2015 $1,581,900.36 $ 48,600.00 6 Maintenance Department Summer Projects Update Fire Alarm System Replacements: Parkway Middle School- to be complete by opening of school Hickory Tree Elementary- to be complete by opening of school Reedy Creek Elementary- to be complete by opening of school Thacker Avenue Elementary (completion Nov 2009) HVAC Chiller Replacements: Gateway High School (9th grade center)- to be complete by opening of school Celebration K-8- to be complete by opening of school 7/20/2015 7 Maintenance Department Work Orders 2008-2009 Update Type General Maintenance Fire Alarm Preventive Maintenance Received 20,657 964 10,026 31,647 Completed 20,660 986 9,928 31,574 ** Figures do not calculate work orders that are carried over from previous fiscal years. Type General Maintenance Fire Alarm Preventive Maintenance 7/20/2015 Current Work Orders 1968 39 3418 5425 8 Design & Construction Goals 1. Completion/Start of all Capital Outlay Planned Projects within the fiscal year. □ Completion/Start of 90% of ’08-’09 planned projects by June 2009. 2. Design and start construction of Major Construction Projects √ Start construction on Mill Creek ES Wing Addition, pending approvals and open August ‘09. √ Start construction on Pleasant Hill ES Wing Addition, pending approvals and open August ‘09. √ Open New Beginnings January ‘09. √ Start construction on ES “N” in 2009, pending approvals, and open August ‘10. √ Start Phase I Construction on OHS Comprehensive Renovation in ‘09. √ Start Phase I Construction on SCHS Comprehensive Renovation in ‘09. 3. Implement Management Initiatives. □ Publish a Process & Procedures Manual; 2nd draft copy for October ’09. 7/20/2015 9 Design & Construction Capital Outlay Program Status – ’08-’09 Summary Status Started Not Started Complete On Hold Cancelled Total Projects • 89.1% of the Planned Capital Projects have been “Completed” or “Started”. • 68% of the remaining Planned Capital Projects are scheduled to be completed during the 2009 Summer Break 30 4 36 4 4 78 The data provided reflects Capital Outlay amounts based on Board approved budgets for planned projects for renovation, remodeling, and other cyclical renewal projects only. 7/20/2015 10 Design & Construction Major Projects Status Summary 1. Elementary School N- GMP for Board Approval 7/28/2009 2. Mill Creek Elementary Classroom Wing Addition – Construction Started 2/5/2009 3. Pleasant Hill Elementary Classroom Wing Addition- Construction Started 2/18/2009 4. Thacker Avenue Elementary Classroom Wing Addition- in Permit Phase 5. Poinciana High School Auditorium- Construction Started 12/1/08 6. Osceola High School Comprehensive Renovation- Phase I Early Work Construction Started 7. St. Cloud High School Comprehensive Renovation- Phase I Early Work Construction Started 8. Lakeview Elementary HVAC System Replacement- Construction Started June 3, 2009 9. Elementary School L- Construction Complete, opening 8/24/2009 10. Elementary School M- Construction Complete, opening 8/24/2009 11. Middle School CC- Construction Complete, opening 8/24/2009 12. Osceola School for the Arts HVAC Replacement/Functional Remodeling- Opened March 27, 2009 13. Mill Creek Elementary School HVAC System Replacement- Phase 2 in Construction 7/20/2015 11 Design & Construction New School Development Update Elementary School “N” A. Planning √ Contracts for purchase and sale for two parcels have been approved. √ 10/15/08 Due Diligence evaluations completed. □ 08/28/09 Projected completion for County approvals of Final Plat. B. √ √ √ √ √ □ Design & Construction (pending acquisition and jurisdictional approvals) 10/21/08 Projected Architectural Contract Approval to Board. 2/2/09 Projected for Construction Document completion. 6/19/09 Projected for CM bidding 7/28/09 Projected for GMP approval to the Board. 7/31/09 Projected Construction Start. 8/15/10 School available for Opening. Comments: Reuse of the Osceola Plan elementary prototype in the Boggy Creek corridor. 7/20/2015 12 Design & Construction New Construction Development Update Osceola High School Comprehensive Renovation Project A. Planning □ 07/28/09 Contracts for purchase and sale for one parcels to School Board. □ 10/31/09 Projected completion for Due Diligence evaluations. □ 09/30/09 Projected completion for City of Kissimmee approvals of school site plan review. B. √ □ □ □ □ Design & Construction (pending acquisition and jurisdictional approvals) 7/27/09 Projected for Construction Document completion. 8/20/09 Projected for CM bidding 9/15/09 Projected for GMP approval to the Board. 9/22/09 Projected Construction Start- Phase 1B 12/15/10 Phase 1B available for Opening. (Gym/Cafeteria, Auditorium) Comprehensive Renovation of the entire campus over multiple phases and years. 7/20/2015 13 Design & Construction New Construction Development Update St. Cloud High School Comprehensive Renovation Project Planning A. Planning □ Contracts for purchase and sale for two parcels have been approved. □ 10/31/09 Projected completion of acquisition of two parcels. □ 09/30/09 Projected completion for City of St. Cloud approvals of school site plan, annexation, land use, and zoning. B. √ □ □ □ □ Design & Construction (pending acquisition and jurisdictional approvals) 7/25/09 Projected for Construction Document completion. 8/25/09 Projected for CM bidding 9/15/09 Projected for GMP approval to the Board. 9/22/09 Projected Construction Start- Phase 1 8/20/10 Phase 1 available for Opening. (Gym, Classroom Bldg., Cafeteria) Comprehensive Renovation of the entire campus over multiple phases and years. 7/20/2015 14 Design & Construction Project Highlights- Summary Cost Report Current Major Projects A B Committed Amount Current Budget Facility C D Expended Estimated Additional Costs E F Estimated Final Cost Estimated Final Cost Variance/ Savings Elementary J $ 20,896,167 $ 18,267,417 $ 18,149,816 $ - $ 18,254,249 $ 2,641,919 Elementary L $ 18,986,886 $ 17,265,106 $ 15,412,020 $ 10,500 $ 17,956,920 $ 1,029,966 Elementary M $ 20,239,926 $ 18,582,162 $ 15,822,154 $ - $ 19,362,043 $ 877,884 New Beginnings $ 11,385,383 $ 11,080,446 $ 10,936,398 $ - $ 10,961,141 $ 424,242 Middle School CC $ 31,164,015 $ 27,443,751 $ 20,374,649 $ $ 29,264,891 $ 1,899,124 MCE Class Add't $ 5,625,600 $ 4,312,326 $ 1,952,841 $ - $ 5,142,406 $ 483,194 PHE Class Add't $ 3,984,750 $ 3,456,397 $ 1,723,065 $ - $ 3,975,606 $ 9,144 PHS Auditorium Totals: $ 6,483,914 $ 118,766,640 $ 2,905,220 $ 87,276,163 $ $ (28,000) $ 5,786,992 232,500 $ 110,704,247 $ $ 696,921 8,062,393 $ 5,614,992 $ 106,022,599 250,000 Report Legend: 7/20/2015 A- Total Current Board Approved Budget B- Total Costs already Commited (and/or Encumbered) per Project C- Total Amount paid (from Purchase Orders) D- Estimated Additional Costs to be realized E- Estimated Final Cost of Project ( Including Projections & Columns B + D) F- Difference between Budget Amount (column A) and Estimated Final Cost (column E) 15 Design & Construction Project Highlights- Owner Direct Purchase Tax Savings Summary A Facility B Direct Purchase Orders C Estimated Tax Savings Paid To Date D E F Accumulated Tax Savings Target Sales Tax per Contract P.O.'s reconciled to GMP Elementary J $ 3,699,908 $ 223,850 $ 3,666,168 $ 223,829 $ 200,000 $ 3,666,168 Elementary L $ 3,965,353 $ 240,482 $ 3,922,523 $ 237,901 $ 200,000 $ 3,965,353 Elementary M $ 4,584,999 $ 277,832 $ 4,468,559 $ 271,154 $ 225,000 $ 4,596,771 Middle School CC $ 7,379,460 $ 446,475 $ 6,672,403 $ 382,107 $ 489,528 $ 6,824,235 New Beginnings $ 1,916,479 $ 116,187 $ 1,832,758 $ 111,164 $ 150,000 $ 1,832,758 Mill Creek ES HVAC $ 343,449 $ 20,857 $ 277,151 $ 16,779 OCSA HVAC $ 504,971 $ 30,698 $ 472,599 $ 28,756 $ 30,000 $ 472,599 PHS Auditorium $ 848,012 $ 51,581 $ 543,903 $ 33,134.15 Mill Creek ES Addt. $ 550,966 $ 33,988 $ 315,631 $ 19,537.83 Pleasant Hill ES Addt. $ 442,796 $ 27,268 $ 288,255 $ 17,795 24,236,393 $ 1,469,217 $ 22,459,949 $ 1,342,158 $ 1,294,528 Totals: $ $ 21,357,884 Report Legend: A- Total Current Owner Direct Purchase Orders per facility. D- Amount of Tax Savings accumulated based on C. B- Total Tax Savings estimated based on face value of Purchase Order. E- Tax Savings Targeted and already included in the CM Contract. C- Amount of Purchase Order paid through the end of the month. F- Purchase Orders deducted via Change Order to the GMP. 7/20/2015 16 Design & Construction Project Highlight – Koa Elementary (L) 7/20/2015 Schedule Date of Commencement or Notice to Proceed Contract Substantial Completion Date: Approved Time Extensions (work days): Substantial Completion Date: Projected Final Completion Date: 4/23/2008 3/25/2009 0 3/25/2009 5/25/2009 17 Design & Construction Project Highlight – Koa Elementary (L) Financial Original GMP Contract Amount: Amendment #1 Amendment #2 $ $ $ 14,375,000.00 221,631.00 14,596,631.00 Change Orders: CO#1 CO#2 CO#3 Subtotal $ $ $ $ (3,494,723.78) (407,629.45) 222,720.00 (3,679,633.23) Contingency Transfer Authorizations: Beginning Contingency CTA#1 CTA#2 CTA#3 Contingency Balance $ $ $ $ $ 133,261.00 (7,008.00) (23,815.00) (32,371.00) 70,067.00 Revised GMP Contract Amount: $ 10,916,997.77 Value of Completed Payments: $ 10,183,381.50 Percent Complete based on Completed Payments: 7/20/2015 93% 18 Design & Construction Project Highlight – Koa Elementary (L) Notes: 1 The Substantial Completion of March 25, 2009 was achieved. 2 Punch list items are complete. Final Completion of May 25, 2009 was achieved. 3 School will open on August 24, 2009. 4 Project will be complete approximately $1,000,000 under Current Board Approved Project Budget, and approximately $3,000,000 under the Board Approved Original Budget. 5 Expect final change order for ODP reconciliation and GMP cost savings incentive reconciliation. 7/20/2015 19 Design & Construction Project Highlight – Westside K-8 7/20/2015 Schedule Date of Commencement or Notice to Proceed Contract Substantial Completion Date: Approved Time Extensions (work days): Projected Substantial Completion Date: Projected Final Completion Date: 4/23/2008 7/15/2009 0 7/15/2009 9/15/2009 20 Design & Construction Project Highlight – Westside K-8 Financial Original Contract Amount: $ 23,750,000.00 Change Orders: CO#1 CO#2 CO#3 CO#4 Subtotal $ $ $ $ $ (5,481,647.37) 276,069.00 186,501.00 (1,343,164.02) (6,362,241.39) Contingency Transfer Authorizations: Beginning Contingency Contingency Balance $ $ 170,000.00 170,000.00 Revised GMP Contract Amount: $ 17,387,758.61 Value of Completed Payments: $ 15,381,261.92 Percent Complete based on Completed Payments: 7/20/2015 88% 21 Design & Construction Project Highlight – Westside K-8 Notes: 1 Substantial Completion was achieved on 7/15/09. 2 Punch List in progress for target Final Completion of 9/15/09. 3 Expect final change order for ODP Reconciliation, and courtyard design additions of site lighting, stair/handrail changes of approximately $200,000. 4 Project expected to be completed approximately $7,000,000 under Original Board Approved Project Budget and $1,900,000 under Current Project Budget. 7/20/2015 22 Design & Construction Project Highlight – Narcoossee Elementary (M) 7/20/2015 Schedule Date of Commencement or Notice to Proceed Contract Substantial Completion Date: Approved Time Extensions (work days): Projected Substantial Completion Date: Projected Final Completion Date: 7/16/2008 6/10/2009 0 6/10/2009 8/10/2009 23 Design & Construction Project Highlight – Narcoossee Elementary (M) Financial Original GMP Contract Amount: Amendment #1 Amendment #2 Amendment #3 (MS Conversion) $ $ $ Change Orders: CO#1 CO#2 CO#3 CO#4 CO#5 Subtotal $ 176,774.78 (3,061,469.48) 97,454.09 93,004.80 (1,535,301.42) (4,229,537.23) Contingency Transfer Authorizations: Beginning Contingency CTA#1 CTA#2 Contingency Balance $ $ $ $ 125,000.00 (6,508.93) (6,725.70) 111,765.37 Revised GMP Contract Amount: $ 12,337,847.77 Value of Completed Payments: $ 10,991,677.52 Percent Complete based on Completed Payments: 7/20/2015 $ $ $ 763,670.00 14,436,330.00 1,367,385.00 16,567,385.00 89% 24 Design & Construction Project Highlight – Narcoossee Elementary (M) Notes: 1 Substantial Completion for the Elementary School was achieved June 8, 2009 . 2 Punch List is in progress with Final Completion on target for August 10, 2009. 3 Expect Final Change Order for ODP Reconciliation and GMP Cost Savings Incentives Reconciliation. 7/20/2015 25 Design & Construction Project Highlight – Narcoossee Elementary (M) 7/20/2015 26 Design & Construction Project Highlight – Narcoossee Elementary (M) 7/20/2015 27 Design & Construction Request for Services 1. Solicitations under development – to Purchasing – Fire Alarm System Inspections, Testing, Monitoring, and Installation Bid – HVAC Controls Installation and Maintenance Bid 2. Advertised Solicitations – Continuing Service Architect and Engineering Services 3. Solicitations Under Review/Selection Process None at this time. 7/20/2015 28 Design & Construction Working Issues – Information items to be presented and discussed with the Board. 1. OCSA Auditorium Roof – contractor default 7/20/2015 29 Design & Construction Working Issues – Information items to be presented and discussed with the Board. 1. OCSA Auditorium Roof – contractor default Contractor/Manufacturer indicates that complete replacement of deficient work will be completed at no cost to SDOC. Letter Agreement language has been Board approved and work to replace the deficient work has begun. Completion is targeted for August 7, 2009. 7/20/2015 30 End of Presentation 7/20/2015 31