Chapter 7 Funding & The Bid Process
Download
Report
Transcript Chapter 7 Funding & The Bid Process
SPORT MANAGEMENT 302 (a)
B. FLAHERTY
Questions/Comments?? Quiz next week,
Chapters 1-6
Complete Chapter 7 “Funding and the Bid
Process”
Chapter 8 “Constructing Recreation
Facilities”
Small Group Work
Summary/Assignments
Chapter 7 Funding & The Bid
Process
Funding is a critical part of the design project
Generate support & interest
Project Costs
1. Hard Costs “Fixed”, part of the facility, permanent & relate to
construction. (material cost + labor) Cost per square foot common.
GSF and ASF. What are they? What is tear space??
Construction Mgmt: Have expertise to guide construction to ensure it
goes according to plan, safely
“FFE” Furniture, fixtures, and equipment
2. Soft Costs; “Start-up costs” Contingencies (unexpected costs 10-20 %
of construction cost) Architect fees, engineering, consultants, permits,
permits, permits!!
Chapter 7
Operational costs need to be considered in the design stage;
i.e. sustainability “Plan well, save later”
CONSTRUCTION OPTIONS (Be aware of funding and time frame
to completion)
1.
Conventional; Most common; design is put out to bid, lowest,
most qualified is awarded the contract. Common in the
public sector.
2.
Design-Build; One company does both the design and
construction. Cost savings, mostly used by the private sector.
3.
Fast-Track; Construction begins before design is complete.
Potential savings.
4.
Turnkey; Contractor does it all, design through construction
Chapter 7
BIDDING THE PROJECT
Private sector organizations need not go through the bid
process, but may do since bidding causes competition
Public sector organizations are required by law to bid projects.
Ensures a fair & equal process
Lump sum = General contractor provides quote. Includes all
work. Separate bid pricing = several contractors bid on different
phases; i.e. structural, electrical, HVAC
Alternates; Bid separately from initial bid. Can be added if funds
available
Bonds; Percentage of project cost, all bidders provide.
Returned to selected bidder once work complete
Chapter 7
Bid process example:
Public announcement
↓↓
Bid submission deadline
↓↓
Formal bid opening
↓↓
Review of bids
↓↓
Award
Chapter 7
Contract Arrangements
“You need more than a handshake!”
1.
Value Engineering; Comparison of
specifications & costs. Negotiate to solve
problems
2.
Insurance; Worker’s compensation,
property, casualty loss
3.
Financing; Pay for the work/materials
4.
Cost control; Incentives
5.
Signing; Once signed, price locked in
Chapter 7 Complete
FUNDING OPTIONS (Usually a combination)
1.
Mandatory Fees; i.e. Memberships
2.
Tax Levy; Public sector. Taxes.
3.
User fees; Charge for service
4.
Bond Issue; Public sector. Tax exempt bonds (principle +
interest) sold to general public
5.
Revenue Bond; Public sector. Revenue raised repays the
loan.
6.
Donations/Contributions
7.
In-Kind Donations; Labor/materials donated
8.
Grants; Public sector.
9.
Sponsorships; EXAMPLES????
http://www.vucommodores.com/ot/multipurposefacility.html
Chapter 8 “Constructing Recreation
Facilities”
Green Stadium
Celebration time!! Break that ground, build that facility.
“Turn paper into brick”
CONSTRUCTION DOCUMENTS
Architect completes adjustments. Critical to have in good order.
1.
Final Blueprints; Details the project. Contractors must follow to ensure
safety & to avoid mistakes.
2.
SpecBook: More detail. Codes, standards.
3.
Shop drawings: Interpret blueprints & spec book. Focus on specialized
designs
4.
Change Orders: Problems should be expected. Written design order to
make approved change.
5.
Project Schedule: All aspects listed, estimated completion.
Chapter 8
CONSTRUCTION MANAGEMENT
•Oversee entire project.
•Expertise & experience
•Formal written agreement w/owner
•Progress Meetings
•Coordination: Avoid conflicts, keep it on schedule
•Project Schedule
•QUALITY CONTROL; Inspect work of all
contractors. Ensure design becomes reality
•Legal Requirements; Ensure codes are followed
•Inspections; Will arrange. Outside agencies,
examine electrical, structural, plumbing
•Changes; CM, architect review, owner for approval
•Site safety/security: Critical. EXAMPLES????
•Visits: Hard hats, sign-in, supervise
•http://www.sportvenueconstruction.com/act-globalsports/
Chapter 8 Complete
FINAL STAGES “Before the doors open”
Training; Technical equipment, HVAC, security, av
Maintenance Manuals; “A dull read, but necessary”
Finishing Stage; Painting, lights, floor coverings, furniture,
equipment
“Keymaster”; New & old. EXAMPLES????
Signage; Safety, direction
Punch List; List at the end of project detailing what needs to
be completed. “Walk about”
Furniture/Equipment; Very detailed. Owner pays portion.
Acceptance/Occupancy; Move in prior to completed punch list
acceptable. “Certificate of Occupancy” “RIBBON CUTTING”