Transcript pec.org.pk

Construction Fundamentals

Chapter 3 – Construction Management Functions Purpose of operating a business is to earn a profit!

Chapter 3 – Construction Management Functions To be successful a construction company must:

Estimate the cost of construction projects accurately

– –

Predict the schedule of the work Control the progress and expenditures during construction

Complete projects safely and on time

Construction Management Functions Responsibility to construct the project:

in accordance with the plans and

specifications to satisfy the customer’s cost, quality, and time expectations The project team is organized for the purpose of accomplishing those missions!

Owner Functions

Defining the scope of the project

Planning the project

Financing the project

Ensuring the project team understands the project’s goals

Construction Management Functions Company level

Selecting the right jobs to bid

– – –

Preparing the cost Submitting the bid estimate Procuring the payment and performance bonds

– –

Scheduling the work Securing project operating capital

Construction Management Functions Construction site level

Setting the standards for and safety quality

Planning the sequence of construction

Controlling expenditures progress and

Construction Management Functions Construction site level

Communicating owner and designer effectively with

Coordinating subcontractors the work of the

Managing submittals, change orders and periodic pay estimates

Closing out the project

Project Planning And Design

• •

Master planning Scope definition

Owner determines exactly what kind of a facility will be built

Sets the design objectives for the Architect/Engineer

Planning phase

Influence on Construction Quality

Influence on Construction Project Cost

Impact of Time on the Cost of Project Changes

The Business of Construction Management

Planning Phase

• • •

Select the Define the designer project goals

• •

Ensure the availability of sufficient funds to complete the project Select and purchase the project site, Determine construction procurement system and the form of construction contract to be used.

Design Phase

Primary requirement for any facility is that it must be safe!!

Building codes

Owner and A/E schedule design reviews

schematic drawings

preliminary drawings

working drawings

Bid Phase First step is to decide whether or not to bid the job. Contractors are generally limited in their ability to bid by two factors:

their bonding capacity and

the policies of management

Policies of Management Factors contractors consider in deciding whether or not to bid a particular project include:

Location of the work

Factors Contractors Consider

Identity of the owner

Availability of key company personnel

Experience in the type of work solicited

Factors Contractors Consider

Whether or not there is financing for the project

Size of the project .

Bid Preparation Bid preparation is expensive!

In preparing a bid, contractors must consider the costs of:

Equipment

Labor

Materials

Subcontractors

Bid Preparation Consider the costs of:

Job and company overhead , contingency , and profit

Should also consider the number of competitor bidders and the bidding history of those competitors on similar projects

Award Phase

Owner provides:

Builder’s Risk insurance

Successful bidder must provide:

Payment and performance bonds

– – –

Workers compensation insurance Liability insurance List of subcontractors

Detailed project schedule

Notice to Proceed Contractor cannot begin the work until the

Notice to Proceed

received – so is Use the time between bid opening and contract award for detailed pre project planning.

Pre-project planning Planning how the work will proceed and in what sequence

Construction procedures

– – –

Type of equipment to be used Job access Location of the field office and storage areas

Final selection of subcontractors and suppliers

Pre-project planning

Cash flow analysis should be completed to determine if the company needs to borrow money

Detailed project schedule is prepared

Work break down (WBS) and pay schedule are planned

Construction Phase Size of the contractor’s on-site project management organization is a function of the size and complexity of the project.

Mechanical

Project Management Team

Owner General Contractor Electrical Concrete Structural Other Trades Plumbing HVAC

Construction Company Team Functions

• • • • •

Project managers (PM) Superintendents Schedulers Estimators Material expediters

Owner’s Project Team

Size of the owner’s project team will depend on the size and complexity of the project – small project (A/E)

Large highway project

Resident engineer

Inspectors

Surveyors

Quality assurance technicians

Managing Critical Activities

• •

Contracts are broken down into activities for purposes of scheduling, estimating, progress control, and cost control . Large projects can have several hundred activities, or more!

Trick is to know which activities are

critical

Critical Activities Critical activities are those that could impact the cost of the work by at least one half of one percent of the bid price:

For example, on a $1,000,000 project, any activity with a potential for cost over-run or under-run of $5,000 or more is by definition a critical activity.

Pareto’s 80-20 rule

20% of the activities are critical and should be managed carefully

The other 80% will average out…

Project Control

Cost control

Cash Flow Analysis

Schedule Control

Material Management

Cost Control Possible corrective actions could include:

Adding additional trade workers or crews

Adding or removing equipment

Working overtime

Bringing in additional subcontractors

Cost Control Possible corrective actions could include:

Making the job more efficient

Eliminating factors that cause subcontractors to interfere with each other

Productivity Let R = Production rate T

Q R Where: T is total time , Q is the total quantity to be installed The total cost is determined by the equation: C t = C h

T Where C t = total cost and C h per hour, or C t = C h

(Q/R) = cost

Cash Flow Analysis Time

Front Loaded Cost Curve Time

Cash Flow Schematic Diagram

Profit (loss) To Date Project Manager must calculate

profit (loss) to date

on a regular, weekly basis

– – – –

Cost to date Re-estimated cost to complete Amount billed Contract amount (including change orders)

Example 3.2

Schedule Control

• •

Chapter 4 Critical path - By definition, activities on the critical path will delay the entire project if they are delayed Physical progress can be compared with the financial progress to determine if the project is:

– –

on schedule or late over budget or under budget

Materials Management Ensure that materials are delivered in a timely manner to the site in the quantity and quality required. When materials arrive they are:

Counted

– –

Inspected if necessary, Tested

Materials Management Must determine the latest order date accounting for the:

shop drawing

Preparation

submission and

approval time

lead time required for fabrication

shipping

Materials Management Too many materials stored on the site can lead to problem of:

space allocation

weather damage

theft

Construction Related Design Temporary structures such as:

Scaffolding

– –

Forms Temporary bridges

– – –

Shoring Cofferdams Rigging must be designed by the contractor

Risk Management

• •

Risks are inherent in construction Industry is moving toward allocating risks to the party most able to control the specific risk Managing risks means:

minimizing risks

insuring against risks

and sharing risks

Risk Management

• • • •

Construction risks - inability of a subcontractor to perform Economic risks - cost escalation Political/public risks - disapproval of the required project permits Physical risks - subsurface conditions

Risk Management

• •

Contractual and legal risks risks assigned by contract over which the contractor has no control Design risks a project design that is not constructible

Risk Management

Worker injured or killed

A job accident that injures the public

A construction vehicle is involved in an accident off the project

Risk Management Risks are best assumed by the party with the ability to best control the risk The best way to manage risks is to avoid them, but the construction industry is characterized by risks!

Risk Management

Contractors manage risks by purchasing insurance

Examining the contract language addressing changed conditions…

Contractor safety programs

Subcontracting is also a form of risk management –require performance and payment bonds

Value Engineering (VE)

Function analysis or value analysis

Main objective to reduce project cost, without reducing the quality of the structure

VE exists because contractors know better ways to build projects, and owners are willing to pay for that knowledge!!

Assignment Due next class Chapter 3 Review Questions

3.5

3.10

3.15