Suggestion to update Work Plan for IEEE 802.16m Standard
IEEE 802.16 Presentation Submission Template (Rev. 9)
Document Number:
IEEE C802.16m-09/2668
Date Submitted:
2009-11-17
Source:
Hokyu Choi
Samsung Electronics
Venue:
Base Contribution: N/A
[email protected]
Purpose: Discussion
Notice:
This document does not represent the agreed views of the IEEE 802.16 Working Group or any of its subgroups. It represents only the views
of the participants listed in the “Source(s)” field above. It is offered as a basis for discussion. It is not binding on the contributor(s), who
reserve(s) the right to add, amend or withdraw material contained herein.
Release:
The contributor grants a free, irrevocable license to the IEEE to incorporate material contained in this contribution, and any modifications
thereof, in the creation of an IEEE Standards publication; to copyright in the IEEE’s name any IEEE Standards publication even though it
may include portions of this contribution; and at the IEEE’s sole discretion to permit others to reproduce in whole or in part the resulting
IEEE Standards publication. The contributor also acknowledges and accepts that this contribution may be made public by IEEE 802.1
Patent Policy:
The contributor is familiar with the IEEE-SA Patent Policy and Procedures:
<http://standards.ieee.org/guides/bylaws/sect6-7.html#6> and <http://standards.ieee.org/guides/opman/sect6.html#6.3>.
Further information is located at <http://standards.ieee.org/board/pat/pat-material.html> and <http://standards.ieee.org/board/pat >.
1
Background & Suggestion
• Current TGm workplan is obsolete.
– Sponsor Ballot in March is realistic.
– Official ITU-R IMT-Adv schedule was not precisely reflected
• External collaboration requires up to date TGm schedule
– WiMAX Forum
– Industries
• Suggestion
– Shift current Ballot time line
– Update ITU-R IMT-Adv schedule
2
TGm Timelines (current)
Q2
IEEE 802.16
System
Requirements
IEEE 802.16m
Evaluation
Methodology
System
Description
IMT
Advanced
Proposal
2007
Q3
Q4
Q1
2008
Q2
Q3
ITU-R IMT Advanced
Circular
Letter
IMT.EVAL
Q1
Q2
2009
Q3
Q4
2010
Q2
Q3
Q1
Sep ’07*
Amendment Ready for IMTAdv evaluation
Jan’08*
Amendment Feature Complete.
EC Conditional Approval for SB.
Nov ’07
EC Conditional Approval for
RevCom submission
Jan 09*
Amendment Ready for
Industry Release.
RevCom submission
ITU based Updates
Jan ’09
Sept ’09*
Final Proposal
Nov ’08
Refinements
July ’09
Working Doc
Jan’10
Letter Ballot
May ’10
Sponsor Ballot
Jun ’08
Jun ’08
ITU based potential updates
Oct ’08
Jan’09
Oct ’09
Proposal Submission
IMT.RSPEC
Q4
Apr MayJun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr MayJun Jul Aug Sep Oct NovDec Jan Feb Mar Apr MayJun Jul AugSep Oct Nov Dec Jan Feb Mar Apr MayJun Jul AugSep Oct Nov Dec
802.16m
Amendment
IMT.TECH
Q4
Jun ’10
Proposal Evaluation & Consensus Building
Develop Recommendation
ITU-R WP5D
Apr MayJun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr MayJun Jul Aug Sep Oct NovDec Jan Feb Mar Apr MayJun Jul AugSep Oct Nov Dec Jan Feb Mar Apr MayJun Jul AugSep Oct Nov Dec
*System Requirements and Evaluation Methodology, System Description, IMT-Advanced Proposal
Documents may be further updated based on ITU output (shown by dotted lines).
3
3
ITU-R WP5D IMT-Adv Schedule
WP 5D
meetings
2008
No.1
(0)
No.2
2009
No.3
No.4
2010
No.5
No.6
No.7
No.8
2011
No.9
No.10
Step1 and 2
(20 months)
Step 3
(8 months)
(1)
Step 4
(16 months)
Steps 5,6 and 7
(20 months)
(2)
(3)
Steps 8
(12 months)
(4)
Steps in radio interface development process:
Step 1: Issuance of the circular letter
Step 2: Development of candidate RITs and SRITs
Step 3: Submission/Reception of the RIT and SRIT proposals
and acknowledgement of receipt
Step 4: Evaluation of candidate RITs and SRITs
by evaluation groups
Step 5: Review and coordination of outside evaluation activities
Step 6: Review to assess compliance with minimum requirements
Step 7: Consideration of evaluation results, consensus building
and decision
Step 8: Development of radio interface Recommendation(s)
Critical milestones in radio interface development process:
(0): Issue an invitation to propose RITs
(1): ITU proposed cut off for submission
of candidate RIT and SRIT proposals
March 2008
October 2009
(2): Cut off for evaluation report to ITU
June 2010
(3): WP 5D decides framework and key
October 2010
characteristics of IMT-Advanced RITs and SRITs
(4): WP 5D completes development of radio
February 2011
interface specification Recommendations
IMT-Advanced A2-01
TGm Timelines (suggestion)
Q2
IEEE 802.16
System
Requirements
IEEE 802.16m
Evaluation
Methodology
System
Description
IMT
Advanced
Proposal
2007
Q3
Q4
Q1
2008
Q2
Q3
ITU-R IMT Advanced
Circular
Letter
IMT.EVAL
Q1
Q2
2009
Q3
Q4
Sep ’07*
2011
Q1
Q4
Amendment Ready for IMTAdv evaluation
Jan’08*
Amendment Feature Complete.
EC Conditional Approval for SB.
Nov ’07
EC Conditional Approval for
RevCom submission
Jan 09*
Amendment Ready for
Industry Release.
RevCom submission
ITU based Updates
Jan ’09
Sept ’09*
Final Proposal
Nov ’08
Refinements
July ’09
Working Doc
Mar’10
Letter Ballot
July ’10
Sponsor Ballot
Jun ’08
Jun ’08
ITU based potential updates
Oct ’08
Jan’09
Oct ’09
Proposal Submission
IMT.RSPEC
2010
Q2
Q3
Q1
Apr MayJun Jul AugSep Oct NovDec Jan FebMar Apr MayJun Jul AugSep Oct NovDec Jan FebMar Apr MayJun Jul AugSep Oct NovDec Jan FebMar Apr MayJun Jul AugSep Oct NovDec Jan FebMar
802.16m
Amendment
IMT.TECH
Q4
Jun ’10
Oct ’10
Proposal Evaluation
Consensus Building & Decision
Feb ’11
Develop Recommendation
ITU-R WP5D
Apr MayJun Jul AugSep Oct NovDec Jan FebMar Apr MayJun Jul AugSep Oct NovDec Jan FebMar Apr MayJun Jul AugSep Oct NovDec Jan FebMar Apr MayJun Jul AugSep Oct NovDec Jan FebMar
*System Requirements and Evaluation Methodology, System Description, IMT-Advanced Proposal
Documents may be further updated based on ITU output (shown by dotted lines).