Point 1 activities and outlook
ATLAS week plenary
Marzio Nessi
Freiburg, 4st October 2004
Point 1 activities and perspectives
Marzio Nessi
ATLAS plenary
2nd October 2004
04/10/ 2004
Summary
 Surface infrastructures
 USA15, US15, SDX1 counting rooms
 UX15 main cavern activities
 Cryogenics
 Gas and Cooling projects
 Racks and cabling
 Next 3 months
 2005 and 2007 outlook
04/10/ 2004
Marzio Nessi
2
Point 1
All buildings delivered
All surface buildings infrastructure operational (air, power, safety,..)
For all these bldg. we are already in M&O regime !
SR1 : ID clean rooomATLAS cooling towers
SPS cooling towers
cryo bldg.
SDX1
SX1
access bldg.+ TDAQ
Air/cooling bldg.
Gas bldg.
SCX1 :Control room bldg.
04/10/ 2004
Marzio Nessi
3
SX1
• air and power installed and
operational
• cranes ok and stable
• protections around the shafts final
• safety systems installed
last June, after a big storm, we
experienced a problem with the
SX1 roof
Water was dropping down
through the PX16 shaft on top of
the Tile calorimeter
04/10/ 2004
Marzio Nessi
4
SCX1 bldg. (future control rooms)
Conference room /
offices
TCn
drawing
office
Conference
room
04/10/ 2004
Marzio Nessi
5
In SCX1 : weekly meetings
Monday :
10:00 - 11:00
schedule (next 4 months)
Tuesday:
08:00 - 09:00
09:00 - 10:00
muon installation
08:00 - 09:00
09:00 - 10:00
ID installation
Thursday:
09:00 - 10:00
services installation
Friday:
09:00 - 10:00
toroid installation
Wednesday:
Point 1 management (EAM)
calorimeters installation
On the ATLAS agenda system,
minutes/actions on EDMS/agenda system,
possibility to connect by phone
04/10/ 2004
Marzio Nessi
6
SDX1 (TDAQ)
• Constuction started, finished by end
October
• HVAC contract signed, work in Nov
• Power , water cooling and fibers in
tendering phase
04/10/ 2004
Marzio Nessi
7
Cooling and Ventilation systems
Installation of all conducting ducts
completed (shaft, external chimneys,..)
Sommer problem with the firm is now over !!
04/10/ 2004
Marzio Nessi
8
Ventilation systems
Ventilation technical room
operational
HVAC stations in bldg SU1
completed and operations
04/10/ 2004
Marzio Nessi
9
Cooling systems
Mixed water production plant
(for cooling) operational
Cooling plant underground in
USA15 completed and operational
04/10/ 2004
Marzio Nessi
10
Experimental Cavern (UX15)
04/10/ 2004
Marzio Nessi
11
HS structure (UX15)
• We have anticipated the construction of the last 2 floors of HS structure
• and reached the minimal opening of the arches
• We plan in the next 3-4 months to prepare the arches is 3 pieces on the
surface, ready for modular installation, once the toroid is completed
04/10/ 2004
Marzio Nessi
12
UX15 infrastructure
 Cranes are ok and operational (no major problems
after ~ 12 months)
 We are pulsing air in the cavern
 Light and power on the metallic structures ongoing
( HO by end October)
 Both lifts in HO operational
 Elevators below the experiment installed
 Grounding network being installed
 Fire extinguishing system + foam system installed
 Brackets for big wheels installed and load tested
04/10/ 2004
Marzio Nessi
13
SH1 – Cryogenic Compressor Building
No new installation work since Feb. Compressors are commissioned. Next
stage is refrigerator commissioning in USA15 (Oct)
Helium main
refrigerator
compressor
station
Nitrogen
refrigerator
compressor
station
Helium shield
refrigerator
compressor
station
Electrical power
Compression
Main helium
2MW
500 g/s @ 18 bar
Helium shield
1.7MW
300 g/s @ 18 bar
Nitrogen
350kW
800 g/s @ 14 bar
Liquid and gas storage

6 Gaseous Helium storage tanks installed/commissioned/painted and in use
length
30m
weight
60ton
volume
250m3
Total
Helium
storage
capacity
27.000Nm3
of gaseous
helium at
18bar and
room
temperature
Liquid and gas storage


A liquid nitrogen storage dewar (50m3 @ 84K) and a gaseous nitrogen
storage tank (80m3 @ 15bar) installed/commissioned and in use.
To be installed; another liquid nitrogen storage dewar in 2005 (today
installed at B180)
80m3 GN2
storage Tank
50.000l Liquid
N2 storage
Dewar at 84K
Tank and Dewar
next to the
compressor
building SH1
Piping
4km of stainless steel piping in buildings, shafts and caverns have
been installed and commissioned
Vent lines in
shaft PX14
Chimney on the
roof of SDX1
Piping
• 100% X-rays inspection
done
USA15 – Cryogenic area
2 Helium and a nitrogen refrigerator have been installed and are ready to be
commissioned
He Main
Solenoid
Refrigerator,
6kW @ 4,5K,
(500L/h)
Valve Unit to
be installed
Dec-Jan
Nitrogen
Refrigerator,
20kW @ 84K,
(500L/h)
He Shield
Refrigerator,
20kW 40-80K,
60kW 300-100K
UX15– He external cryogenics, side wall USA15
Installed and ready for commissioning: Helium distribution valve box and
transfer line
Main He transfer line
from refrigerators
He Distribution Valve Box supplying liquid
helium to the superconducting magnets
UX15– Ar/N2 external cryogenics, side wall USA15



7 Valve boxes and 2km of transfer lines installed and ready for
commissioning
2 x 50.000l liquid Argon (80K) dewars
15.000l liquid Nitrogen dewar
Valve Boxes and Transferlines
2 Argon dewars
Nitrogen dewar
UX15– He proximity cryogenics, side wall USA15



Valvebox and Buffer
Dewar under
construction, installation
foreseen Dec.
Toroid Barrel Current
Lead Cryostat being
designed
Solenoid Control Dewar
and chimney to be
installed after completion
TB.
He PCS Valve Box
Solenoid Control
Dewar and Chimney
He PCS valve box
He PCS Buffer
Dewar
TB Current Lead
Cryostat
UX15– Ar/N2 proximity cryogenics, side wall USA15
Calorimeter Barrel valve
box, installation Nov
Calorimeter Endcap
expansion vessel and valve
box, installation 2005
Calorimeter Barrel
expansion vessel,
installation Nov
Cooling systems
Cooling system
Specification
Schemes
Implementation in Components list
UX/USA
Evaporative
ATC-TL-EP-0001
yes
ATCNSO 0008
yes
yes
TRT
ATC-TL-EP-0002
yes
ATCNSO 0009
yes
yes
ID cables
yes
yes
ATCNSO 0010
partially
partially
Liquid Argon
ATC-TL-EP-0003
yes
ATCNSO 0011
yes
yes
TileCal
ATC-TL-EP-0004
yes
ATCNSO 0012
yes
yes
Vacuum pipes
ATC-TL-EP-0005
yes
ATCNSO 0020
yes
yes
Muon
Not complete
yes (but some
partially
no
no
options are
open)
Price and
manpower
estimation
For most of these WPs we have formal internal agreement with CERN services
for the construction of it, we provide manpower and material budgets
 construction has started (first calos + SR1)
04/10/ 2004
Marzio Nessi
24
Cooling piping to the inside of the detector
Calorimeters cooling stations and pipes
routing
Fluid supply from USA15 to
UX15 distribution racks
contracted, installation in
the next 2-3 months
04/10/ 2004
Evaporative system –
pipes routing in UX15
Marzio Nessi
25
Cooling piping to the inside of the detector
Pipes leaving the distribution rack towards the detector – CMS
example. Cu pipes have been recently defined as ID baseline.
We are also investigating if this can be used for the gas
distribution inside the detector (not TRT)
04/10/ 2004
Marzio Nessi
26
Cooling systems schedule

Calorimeters
August 2005

Vacuum pumps
October 2005

Muon
end of 2005

Inner detector
Cooling stations manufacturing starts October 2004
Cooling station manufacturing starts December
Design will be finished by the end of 2004
Distribution racks for all ID systems
2004
August 2005
 Distribution manifolds has been ordered for evaporative and TRT
mono-phase, for ID cables manifolds design is ongoing
TRT mono-phase
ID cables
Evaporative for Pixel, SCT
 Still some changes on specification from ID
04/10/ 2004
Marzio Nessi
November 2005
November 2005
end 2005
27
Gas systems – work packages
 ATLAS Muon Gas System Construction, Installation and
Commissioning ATC-GE-MA-0007 – released, approved
 ATLAS TRT Active Gas System Construction, Installation and
Commissioning ATC-GE-MA-0018 - released, approved
 Construction, Installation and Commissioning of the ATLAS
Inner Detector CO2 and N2 Gas Systems – under approval
Others
 Fixed gas piping
 installation now on UX15 side US15 – close to be finished
 cleanliness has been checked and is OK
 Compressed air distribution – layout done, work agreed with
company installing fixed gas piping
 Valves islands for gas control systems - under investigation
 Cooling for mixing room in SGX1 – problem under control
04/10/ 2004
Marzio Nessi
28
Piping work (from surface to USA15-UX15)
no Si
04/10/ 2004
Marzio Nessi
29
Gas systems - manufacturing schedule

Distribution racks

Mixer modules

Pumps modules
04/10/ 2004
MDT
RPC
TGC
CSC
TRT
end of 2004
Feb/March 2005
mid 2005 (if problem with components solved)
mid 2005
May 2005
80% done, should be ready by the end of 2004
(some problems with humidity for MDT and components acceptance (safety) for
TGC)
production has started
Marzio Nessi
30
Cable trays installation started
04/10/ 2004
Marzio Nessi
31
Cable trays installation started
• USA15 done
• link galleries done
• UX15 fanout done
• UX15 below the toroid : now
• UX15 to US15 : next
• UX15 HS structure : next
04/10/ 2004
Marzio Nessi
32
CABLE TRAYS inside ATLAS (z=0)
Re-evaluating
the geometry
of this flexible
chain
04/10/ 2004
Marzio Nessi
33
Cable trays inside the detector
Detailed layout done for
-Barrel calorimeters services on the Tile surface
-Barrel Toroid cabling
-Cryogenics cabling
-BT heaters
Detailed design work has started for
- ID cabling on the calorimeter surface
- Muon services in sector 13
04/10/ 2004
Marzio Nessi
34
Azimuth cable trays
04/10/ 2004
Marzio Nessi
35
Calorimeters
cooling pipes
TileCal CANbus
daisy chains
To be preinstalled,
then removed
Drawing:
ATCSDB__0035
04/10/ 2004
Marzio Nessi
36
Azimuth cable trays
04/10/ 2004
Marzio Nessi
Brackets for azimuth
cable trays
37
Sectors 11&13. Calorimeter cooling pipes
04/10/ 2004
Marzio Nessi
38
This part of
manifolds to be
preinstalled, then
removed
Calorimeters
cooling
manifolds
04/10/ 2004
Marzio Nessi
39
Racks in UX15
Not assigned racks
04/10/ 2004
Marzio Nessi
40
Racks in UX15
• The layout and amount of racks was revised, we have now
~30% less racks in the cavern
• All racks have been procured and are right now at Point 1
• Next step: install as much as possible and start installing the
cable trays associated
• We start with all racks on US side; this will allow an early
installation of type 4 ID cable to US15
• We have to solve the problem of the powering of these racks.
From first analysis it looks like we do not need to bring
much power (no specific distribution system or
cooling)
04/10/ 2004
Marzio Nessi
41
Next installation
To
US15
racks
04/10/ 2004
Marzio Nessi
42
USA15 counting room
All rack space assigned !
Information now transferred to
the rack wizard
04/10/ 2004
Marzio Nessi
43
Rack wizard
We are asking all users to fill
their layout database, with as
much information as possible
04/10/ 2004
Marzio Nessi
44
USA15 counting room
DSS
• all 250 racks procured and installed (incl cable trays)
• all racks water cooling distribution installed
• first racks instrumented : DSS
04/10/ 2004
• all infrastructure installed (power, lights, safety, air,..) 45
Marzio Nessi
USA15 Electrical Equipment
Link from transfos to switchboard to be done
Switchboard to rack room.
Two transformers for the racks installed
18kV/400V/2880A each to 3 main branches of 800A.
Two switchboards installed
Feed the main branches
04/10/ 2004
Marzio Nessi
46
USA15 Power Path
Canalis 160A
On top of racks
Canalis 800A
Along the walls
Similar layout for level 2.
• The power is supplied to the racks with Canalis prefab busbars.
• Main branches handle 800A (400V triphased) along the walls.
• Secondary branches handle 160A above the racks.
• 3 Main branches per floor.
04/10/ 2004
Marzio Nessi
47
USA15 Power Path is being installed
Control bus
Canalis 160A
Twido box
Control bus
Distribution box
CANALIS 160A
CANALIS 800A
TWIDO Box
Input
plug
Plugs control
Distribution
Box
• Canalis busbars :
• Control bus :
Ventilation
Auxiliary Plugs
Power
to
Crates
Carry the power to the rack.
Control bus to communicate with the Twido box
• Twido box
On/Off and other monitoring functions with a TWIDO PLC con. to control bus.
• Distribution Box
04/10/ 2004
3 plugs for racks, with remote control of the switch.
1 auxiliary
Marzio
Nessi plug, 1 plug for ventilation unit.
48
Racks basic infrastructure
Cooling and Control Unit
We have ordered (delivery by
beginning of January)
-Cooling and control units
-Air deflectors
-Water cooled heat exchangers
Plan to deliver to the users an
operational USA15 counting room by
February 2005
04/10/ 2004
Marzio Nessi
49
Plans for the next 8 months
• Start the 20th of October with the installation of the Barrel Toroid,
end BT by July 2005
• Install the 27th of October the Barrel LAr Calorimer
• End by Xmas 2004 the mechanical assembly of the Barrel Tile
• Start installation of LAr Electronics on the front face of the detector
• Install calorimeter movement system and test it
• Install muon chambers in the feet region
• Install muon chambers in sector 13
• Install ID pipes on the calorimeter surface
 See G.Tappern talk Thursday
04/10/ 2004
Marzio Nessi
50
Schedule
04/10/ 2004
Marzio Nessi
51
BT Assembly plus muon rail positions
04/10/ 2004
Marzio Nessi
52
Barrel Toroid Installation Structures
04/10/ 2004
Marzio Nessi
53
Barrel Cryostat to be lowered on Oct 27th
04/10/ 2004
Marzio Nessi
54
Muon Barrel Installation
04/10/ 2004
Marzio Nessi
55
Detector Placement
• Detector positioning strategy –see D.Lissauer talk Thursday
Center of
Toroid
should coinside with
the Nominal
Beam Line.
Assemble as Ellipse.
~20mm move due to
Toroid weight.
Position of First
two Coils Fixes
the center of the
Toroid.
04/10/ 2004
~10 mm due to
services and Muon
chambers.
Marzio Nessi
56
UX15 Stabilty
Points on the Floor
Hydrostatic
system on
the Bedplate
HLS
04/10/ 2004
Marzio Nessi
57
Nice hydrostatic data quality

04/10/ 2004
Marzio Nessi
58
Floor Stability – Top View
From August 2003 to September 2004
Precision (1 sigma) of the dZ = 0.2 mm
04/10/ 2004
Marzio Nessi
59
Floor and Bedplate Stability – 3D Model
From June 25th, 2004 to September 08th, 2004
From 25 June 04 to 08 Sept 04
A23+10
C23+10
10
C17+8
C23+5
A17+8
B0+8
C12+5
A11+5
B0+5
A23+5
0.6
0.5
5
0.4
0.3
0.2
0
0.1
0
B0-5
C12-5
-5
A11-5
-0.1
C23-7
A23-7
B0-9
-0.2
-0.3
-0.4
-10
-0.5
A17-14 A22-15
C22-15 C17-14
-20
04/10/ 2004
Marzio Nessi
-15
-10
-5
0
5
10
15
-0.6
20
60
2005 to 2007 planning
M.Kotamaki our planning officer, will present this Thursday
the result of very intensive analysis and planning done over
the summer (dedicated task force)
very critical are the 6 months just after the completion of
the BT and the final positioning of the barrel calorimeters in
the center of ATLAS
- cabling of the calorimeters
- cabling of the ID
In parallel
- installation of the barrel muon chambers
- endcap calorimeters assembly on the trucks
- testing of cryogenics and BT
04/10/ 2004
Marzio Nessi
61
Today working schedule
Installation schedule version 6.24 summary
04/10/ 2004
Marzio Nessi
62
Integration analysis
In the mean time our main worry is to understand the
details of all these operations and the possible conflicts
The devil is in the details !!!
As an example a problem just found and solved with the routing of a
cryo line of the LAr and the installation of a specific muon chamber
04/10/ 2004
Marzio Nessi
63
04/10/ 2004
Marzio Nessi
64
Installation of BIR chamber
Conflict during
installation BIR
chamber
04/10/ 2004
Marzio Nessi
65
04/10/ 2004
Marzio Nessi
66
04/10/ 2004
Marzio Nessi
67
04/10/ 2004
Marzio Nessi
68