MLCR Internal Wiring network and power network cables installed power sockets, lights etc, installed and powered power distribution from under floor distribution points to.

Download Report

Transcript MLCR Internal Wiring network and power network cables installed power sockets, lights etc, installed and powered power distribution from under floor distribution points to.

MLCR
Internal Wiring network and power
network cables installed
power sockets, lights etc, installed and powered
power distribution from under floor distribution points to racks, in hand. Real
soon now.
Air conditioning units installed – bring your own electric fire.
Furniture ordered. Standard units Wednesday week. Specials following week.
Desks along each wall. One set of drawers and a filing draw. One book case.
Sample chair delivered to ISIS control room. Need to find somewhere to put it,
where people can check it.
Network rack in place, but network cables still outstanding. Both from the
outside and into the hall. The hall wiring – fallen into the hole created by Steve
Britnall’s long term absence. Meeting Colin Barry tomorrow am to sort out, his
problems and hope to have an estimate of cost and time shortly there after.
Temporary solution in place for BPMs. Looking to extend for the EPICS control
of magnets.
PPS tested and in rack. Cables being run out into the hall & towards the DSA to
the test points etc. Installation in the DSA hard.
MICE Local Control Room