PPS Status and Issues John Alexander (as told to M. Zisman) Electronics and Controls Daresbury Laboratory MICO Meeting February 7, 2008

Download Report

Transcript PPS Status and Issues John Alexander (as told to M. Zisman) Electronics and Controls Daresbury Laboratory MICO Meeting February 7, 2008

PPS Status and Issues
John Alexander
(as told to M. Zisman)
Electronics and Controls
Daresbury Laboratory
MICO Meeting
February 7, 2008
Status
• PPS racks are complete and in position in MLCR
— a small number of wiring modifications remain to be done
• Majority of PPS hardware needed for DSA installation has
been purchased
— still “some assembly required”
• Installation of PPS hardware and wiring between it and
the PPS racks has commenced
— this job is owned by Colin Barry
o need to determine timescales (end of February?)
• Drawings detailing wiring from the racks to the Hall
equipment remain to be done (at DL)
— need final layout of Hall search route to be defined
o requires Long, Zisman, Apsimon, Stevens
August 1, 2007
US Funding Status-Zisman
2
Issues (MZ view)
• Need to understand required time scale for completion of
work
— January 21 date has come and gone
— need to complete DSA portion by March 27 (2008!)
o reasonably complete system mid-June at latest!
– system that can handle both DSA and MICE Hall
 RF and hydrogen not needed this soon
• Alexander will be at CM20 next Monday-Tuesday for
discussion
— needs to meet with Barry, Spensley, Long, Nichols, Apsimon, and Zisman
o also Alan Stevens (ISIS)
— we need intermediate milestones that can be monitored
August 1, 2007
US Funding Status-Zisman
3