LS1 Status Report LS1@LHCC – 117th LHCC Frédérick Bordry 5th March 2014 LS 1 from 16th Feb.

Download Report

Transcript LS1 Status Report LS1@LHCC – 117th LHCC Frédérick Bordry 5th March 2014 LS 1 from 16th Feb.

LS1 Status Report
LS1@LHCC – 117th LHCC
Frédérick Bordry
5th March 2014
LS 1 from 16th Feb. 2013 to Dec. 2014
16th Feb.
5th March
2013
2014
2015
F M A M J J A S O N D J F M A M J J A S O N D J F M A
beam to beam
available for works
Physics
Beam commissioning
LS1 Status Report – 117th LHCC
Frédérick Bordry
5th March 2014
Shutdown
Powering tests
2
LHC Injectors dashboards
- Full maintenance of all the equipment being completed
- New access system being commissioned
PS & PSB main activities:
Consolidation of the PS Main Units completed,
New PS ventilation system commissioning started,
PSB dump replacement being completed…
PSB beam dump
Septum 16 External Shielding in progress
PS Main Magnets
LS1 Status Report – 117th LHCC
Frédérick Bordry
5th March 2014
3
LHC Injectors dashboards
SPS main activities:
LSS1:
Irradiated cabling campaign is on-going
Re-installation of the machine will start on March,
Transformers exchange complete,
TT10 vault repair completed…
TT10 vault
LSS1 -irradiated cabling campaign
LS1 Status Report – 117th LHCC
Frédérick Bordry
5th March 2014
SPS transformer installation
4
LHC Injectors dashboards
PSB
PS
SPS
LS1 Status Report – 117th LHCC
Frédérick Bordry
5th March 2014
5
LHC Injectors start-up
►
LHC-injectors … getting ready for hardware tests
►
►
►
Full commissioning of the new access system is starting
PS &PSB : hardware tests will start in April
Beam for late spring in Linac 2  summer in PS
LS1 Status Report – 117th LHCC
Frédérick Bordry
5th March 2014
6
116th LHCC Meeting (4th December 2013)
LS1 Status Report – 117th LHCC
Frédérick Bordry
5th March 2014
7
Opening:100% 98 % done
Closure: 50%
96 % done
85 % done
85 % done
70 % done
Done
Done
90 % done
3000
3
85 % done
40 % done
LS1 Status Report – 117th LHCC
Frédérick Bordry
5th March 2014
Done
8
SMACC progress – report on DFBA
DFBA consolidation
►
Leaks were found on the lower
gimbal bellow in 2 DFBAs
►
Shuffling modules were
extracted and transport to
surface for repair
•
►
Both back in tunnel
Teams reinforced – schedule is
not an issue anymore
DFBAK lower gimbal bellow repair on surface
DFBAK shuffling module back
LS1 Status Report – 117th LHCC
Frédérick Bordry
5th March 2014
9
SMACC
Dashboards
3 weeks
LS1 Status Report – 117th LHCC
Frédérick Bordry
5th March 2014
Superconducting Magnets and Circuits Consolidation
(SMACC).
10
Last M line opening (S45)
6th of February 2014
Operator responsible : JM Hubert
Pictures by M Struik
LS1 Status Report – 117th LHCC
Frédérick Bordry
5th March 2014
11
LS1 Status Report – 117th LHCC
Frédérick Bordry
5th March 2014
12
LS1 Status Report – 117th LHCC
Frédérick Bordry
5th March 2014
13
R2E progress
Point 1
All equipment are reinstalled and reconnected
Commissioning in progress
Point 5 & Point 7
Major cabling campaign in progress
UL16 power converters
UL55 safe-room
WCC installation @ P5
LS1 Status Report – 117th LHCC
Frédérick Bordry
5th March 2014
TZ76
14
R2E dashboards
R2E @ Point 1 Right
R2E @ Point 1 Left
100%
Commissioning
Commissioning
80%
80%
Infrastructure EL
60%
Infrastructure EL
60%
Infrastructure
40%
20%
100%
40%
20%
Preparation
Preparation
0%
0%
Baseline
Forecast
SP_baseline
Done
SP_Real
Baseline
SP_baseline
Forecast
SP_Real
R2E @ Point 5
R2E @ Point 7
Commissioning
Safe-room
100%
Safe-room
100%
Commissioning
80%
80%
60%
60%
40%
40%
20%
Done
Infrastructure EL
Infrastructure
20%
Dismantling
Preparation
0%
0%
Baseline
SP_baseline
Forecast
SP_Real
LS1 Status Report – 117th LHCC
Frédérick Bordry
5th March 2014
Done
Baseline
SP_baseline
Forecast
SP_Real
Done
15
The other activities
Vacuum
UPS-RE82
18 kV & 3.3 kV circuit breakers
Before
Cryo plant
Pumping station
LS1 Status Report – 117th LHCC
Frédérick Bordry
5th March 2014
After
P7 enclosure
Helium spill test
ACS transport
Courtesy of Katy Foraz
16
Infrastructure dashboards
LS1 Status Report – 117th LHCC
Frédérick Bordry
5th March 2014
17
Schedule: version 3.0 From
to 3.1
►
Schematic view of version 3.1, now includes
►
►
►
►
DFBA repairs at P6 and P8
CSCM in sectors 67 and 81
a margin of 2 weeks after flushing for N.C. solving
The sector test from P2 to P3
25LS1Feb.
2014– 117
Status Report
th
Frédérick Bordry
5th March 2014
LHCC
K. Foraz - CMS week
Courtesy of Katy Foraz
18
Conclusion
LS1 Status Report – 117th LHCC
Frédérick Bordry
5th March 2014
LHC injectors getting ready for hardware tests
LHC: all signals are green for beam on January 2015
http://cern.ch/ls1dashboard
19
LHC schedule beyond LS1
Only EYETS (19 weeks) (no Linac4 connection during Run2)
LS2
starting in 2018 (July)
18 months + 3months BC (Beam Commissioning)
LS3
LHC: starting in 2023 => 30 months + 3 BC
injectors: in 2024
=> 13 months + 3 BC
2015
2016
2017
2018
2019
2020
2021
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
LHC
Injectors
bbbbbbbbbbbbb
ooooooooooo
oooooooooooo
ooooooooo
ooooooooo
ooooooooooooo
ooooooooooo
oooooooooooo
ooooooooo
oooooooooo
Run 2
ooooooooo
ooooooooo
ooooooooo
ooooo
ooooooooo
ooooooooo
ooooooo
ooooooooo
ooooooo
ooooooooo
ooooooooo
ooooooooo
oooooo
ooooooooo
ooooooooo
ooooooo
oooooooooo
ooooooo
LS 2
bbbbbbbbbbbboooo
bbbbbbbbbbbboooo
oooooooooo
ooooooooo
ooooooooo
oooooooooo
ooooooooo
ooooooooo
Run 3
ooooooooo
ooooooooo
ooooooooo
ooooooooo
oooooooooo
ooooooooo
ooooooooo
ooooooooo
t
2022
2023
2024
2025
2026
2027
2028
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
LHC
Injectors
ooooooooo
ooooooooo
ooooooooo
ooooooooo
oooooooooo
ooooooooo
ooooooooo
ooooooooo
LS 3
oooooooooo
2029
ooooooooo
ooooooooo
bbbbbbbbbbbb
ooooooooo
2030
bbbbbbbbbbbbooooo
2031
ooooooooo
ooooooooo
ooooooooo
ooooooooo
ooooooooo
ooooooooo
ooooooooo
ooooooooo
oooooooooo
ooooooooo
ooooooooo
ooooooooo
2032
2033
Run 4
ooooooooo
ooooooooo
ooooooooo
ooooooooo
ooooooooo
ooooooooo
ooooooooo
ooooooooo
oooooooooo
ooooooooo
ooooooooo
ooooooooo
oooooooooo
ooooooooo
ooooooooo
ooooooooo
2034
2035
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
LHC
Injectors
LS 4
Run 5
bbbbbbbbbbbboooooo
ooooooooo
ooooooooo
ooooooooo
oooooooooo
ooooooooo
ooooooooo
ooooooooo
ooooooooo
ooooooooo
ooooooooo
ooooooooo
bbbbbbbbbbbboooooo
ooooooooo
ooooooooo
ooooooooo
ooooooooooo
ooooooooo
ooooooooo
ooooooooo
oooooooooo
ooooooooo
ooooooooo
ooooooooo
LS1 Status Report – 117th LHCC
Frédérick Bordry
5th March 2014
LS 5
bbbbbbbbbbbboooooo
ooooooooo
ooooooooo
ooooooooo
ooooooooo
ooooooooo
ooooooooo
ooooooooo
bbbbbbbbbbbboooooo
ooooooooo
ooooooooo
ooooooooo
oooooooooo
ooooooooo
ooooooooo
ooooooooo
LHC schedule approved by CERN management and LHC experiments
spokespersons and technical coordinators
Monday 2nd December 2013
21