LS1 Status Report LS1@LHCC – 117th LHCC Frédérick Bordry 5th March 2014 LS 1 from 16th Feb.
Download ReportTranscript LS1 Status Report LS1@LHCC – 117th LHCC Frédérick Bordry 5th March 2014 LS 1 from 16th Feb.
LS1 Status Report LS1@LHCC – 117th LHCC Frédérick Bordry 5th March 2014 LS 1 from 16th Feb. 2013 to Dec. 2014 16th Feb. 5th March 2013 2014 2015 F M A M J J A S O N D J F M A M J J A S O N D J F M A beam to beam available for works Physics Beam commissioning LS1 Status Report – 117th LHCC Frédérick Bordry 5th March 2014 Shutdown Powering tests 2 LHC Injectors dashboards - Full maintenance of all the equipment being completed - New access system being commissioned PS & PSB main activities: Consolidation of the PS Main Units completed, New PS ventilation system commissioning started, PSB dump replacement being completed… PSB beam dump Septum 16 External Shielding in progress PS Main Magnets LS1 Status Report – 117th LHCC Frédérick Bordry 5th March 2014 3 LHC Injectors dashboards SPS main activities: LSS1: Irradiated cabling campaign is on-going Re-installation of the machine will start on March, Transformers exchange complete, TT10 vault repair completed… TT10 vault LSS1 -irradiated cabling campaign LS1 Status Report – 117th LHCC Frédérick Bordry 5th March 2014 SPS transformer installation 4 LHC Injectors dashboards PSB PS SPS LS1 Status Report – 117th LHCC Frédérick Bordry 5th March 2014 5 LHC Injectors start-up ► LHC-injectors … getting ready for hardware tests ► ► ► Full commissioning of the new access system is starting PS &PSB : hardware tests will start in April Beam for late spring in Linac 2 summer in PS LS1 Status Report – 117th LHCC Frédérick Bordry 5th March 2014 6 116th LHCC Meeting (4th December 2013) LS1 Status Report – 117th LHCC Frédérick Bordry 5th March 2014 7 Opening:100% 98 % done Closure: 50% 96 % done 85 % done 85 % done 70 % done Done Done 90 % done 3000 3 85 % done 40 % done LS1 Status Report – 117th LHCC Frédérick Bordry 5th March 2014 Done 8 SMACC progress – report on DFBA DFBA consolidation ► Leaks were found on the lower gimbal bellow in 2 DFBAs ► Shuffling modules were extracted and transport to surface for repair • ► Both back in tunnel Teams reinforced – schedule is not an issue anymore DFBAK lower gimbal bellow repair on surface DFBAK shuffling module back LS1 Status Report – 117th LHCC Frédérick Bordry 5th March 2014 9 SMACC Dashboards 3 weeks LS1 Status Report – 117th LHCC Frédérick Bordry 5th March 2014 Superconducting Magnets and Circuits Consolidation (SMACC). 10 Last M line opening (S45) 6th of February 2014 Operator responsible : JM Hubert Pictures by M Struik LS1 Status Report – 117th LHCC Frédérick Bordry 5th March 2014 11 LS1 Status Report – 117th LHCC Frédérick Bordry 5th March 2014 12 LS1 Status Report – 117th LHCC Frédérick Bordry 5th March 2014 13 R2E progress Point 1 All equipment are reinstalled and reconnected Commissioning in progress Point 5 & Point 7 Major cabling campaign in progress UL16 power converters UL55 safe-room WCC installation @ P5 LS1 Status Report – 117th LHCC Frédérick Bordry 5th March 2014 TZ76 14 R2E dashboards R2E @ Point 1 Right R2E @ Point 1 Left 100% Commissioning Commissioning 80% 80% Infrastructure EL 60% Infrastructure EL 60% Infrastructure 40% 20% 100% 40% 20% Preparation Preparation 0% 0% Baseline Forecast SP_baseline Done SP_Real Baseline SP_baseline Forecast SP_Real R2E @ Point 5 R2E @ Point 7 Commissioning Safe-room 100% Safe-room 100% Commissioning 80% 80% 60% 60% 40% 40% 20% Done Infrastructure EL Infrastructure 20% Dismantling Preparation 0% 0% Baseline SP_baseline Forecast SP_Real LS1 Status Report – 117th LHCC Frédérick Bordry 5th March 2014 Done Baseline SP_baseline Forecast SP_Real Done 15 The other activities Vacuum UPS-RE82 18 kV & 3.3 kV circuit breakers Before Cryo plant Pumping station LS1 Status Report – 117th LHCC Frédérick Bordry 5th March 2014 After P7 enclosure Helium spill test ACS transport Courtesy of Katy Foraz 16 Infrastructure dashboards LS1 Status Report – 117th LHCC Frédérick Bordry 5th March 2014 17 Schedule: version 3.0 From to 3.1 ► Schematic view of version 3.1, now includes ► ► ► ► DFBA repairs at P6 and P8 CSCM in sectors 67 and 81 a margin of 2 weeks after flushing for N.C. solving The sector test from P2 to P3 25LS1Feb. 2014– 117 Status Report th Frédérick Bordry 5th March 2014 LHCC K. Foraz - CMS week Courtesy of Katy Foraz 18 Conclusion LS1 Status Report – 117th LHCC Frédérick Bordry 5th March 2014 LHC injectors getting ready for hardware tests LHC: all signals are green for beam on January 2015 http://cern.ch/ls1dashboard 19 LHC schedule beyond LS1 Only EYETS (19 weeks) (no Linac4 connection during Run2) LS2 starting in 2018 (July) 18 months + 3months BC (Beam Commissioning) LS3 LHC: starting in 2023 => 30 months + 3 BC injectors: in 2024 => 13 months + 3 BC 2015 2016 2017 2018 2019 2020 2021 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 LHC Injectors bbbbbbbbbbbbb ooooooooooo oooooooooooo ooooooooo ooooooooo ooooooooooooo ooooooooooo oooooooooooo ooooooooo oooooooooo Run 2 ooooooooo ooooooooo ooooooooo ooooo ooooooooo ooooooooo ooooooo ooooooooo ooooooo ooooooooo ooooooooo ooooooooo oooooo ooooooooo ooooooooo ooooooo oooooooooo ooooooo LS 2 bbbbbbbbbbbboooo bbbbbbbbbbbboooo oooooooooo ooooooooo ooooooooo oooooooooo ooooooooo ooooooooo Run 3 ooooooooo ooooooooo ooooooooo ooooooooo oooooooooo ooooooooo ooooooooo ooooooooo t 2022 2023 2024 2025 2026 2027 2028 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 LHC Injectors ooooooooo ooooooooo ooooooooo ooooooooo oooooooooo ooooooooo ooooooooo ooooooooo LS 3 oooooooooo 2029 ooooooooo ooooooooo bbbbbbbbbbbb ooooooooo 2030 bbbbbbbbbbbbooooo 2031 ooooooooo ooooooooo ooooooooo ooooooooo ooooooooo ooooooooo ooooooooo ooooooooo oooooooooo ooooooooo ooooooooo ooooooooo 2032 2033 Run 4 ooooooooo ooooooooo ooooooooo ooooooooo ooooooooo ooooooooo ooooooooo ooooooooo oooooooooo ooooooooo ooooooooo ooooooooo oooooooooo ooooooooo ooooooooo ooooooooo 2034 2035 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 LHC Injectors LS 4 Run 5 bbbbbbbbbbbboooooo ooooooooo ooooooooo ooooooooo oooooooooo ooooooooo ooooooooo ooooooooo ooooooooo ooooooooo ooooooooo ooooooooo bbbbbbbbbbbboooooo ooooooooo ooooooooo ooooooooo ooooooooooo ooooooooo ooooooooo ooooooooo oooooooooo ooooooooo ooooooooo ooooooooo LS1 Status Report – 117th LHCC Frédérick Bordry 5th March 2014 LS 5 bbbbbbbbbbbboooooo ooooooooo ooooooooo ooooooooo ooooooooo ooooooooo ooooooooo ooooooooo bbbbbbbbbbbboooooo ooooooooo ooooooooo ooooooooo oooooooooo ooooooooo ooooooooo ooooooooo LHC schedule approved by CERN management and LHC experiments spokespersons and technical coordinators Monday 2nd December 2013 21