FAIRway Danube Commission Meeting in Budapest 29.09.2015 Károly GOMBÁS (Andreas Bäck) Harmonized realization of the Fairway Rehabilitation and Maintenance Master Plan Global Project IWW of the Rhine-Danube Corridor Proposed.

Download Report

Transcript FAIRway Danube Commission Meeting in Budapest 29.09.2015 Károly GOMBÁS (Andreas Bäck) Harmonized realization of the Fairway Rehabilitation and Maintenance Master Plan Global Project IWW of the Rhine-Danube Corridor Proposed.

FAIRway
Danube Commission Meeting in Budapest 29.09.2015
Károly GOMBÁS (Andreas Bäck)
Harmonized realization of the
Fairway Rehabilitation and
Maintenance Master Plan
Global Project
IWW of the
Rhine-Danube Corridor
Proposed Action
FAIRway waterways
Conclusions by
Danube Ministers
Fairway Maintanance Master Plan
for the Danube and its navigable tributaries
Guidelines
+ CEF
Key facts
Schedule
Start: 07/2015
Closure: 06/2020
[Duration of 5 years]
Budget
Total: 23,4 Mn EUR
CEF: 19,7 Mn EUR
Setting
Multi-applicant CEF
study including pilot
operations: seven
interlinked actions
Page 5
Overview on FAIRway activities
• Elaborate coordinated national action plans and define pilots
• Procure equipment for hydrological services
• Execute and evaluate pilots
• Harmonized basic data on critical locations
• Coherent monitoring of navigational status
• Harmonized water level prognosis
• Potential of fairway relocation and floating ship data
• Develop innovative approaches (aerial monitoring, AtoNs …)
• Prepare documentation for future implementation steps
• Manage project and disseminate results
Page 6
Activity 2 National action plans and
definition of pilots
Ministerial Conclusions (Dec 2014) ask for national roadmaps based on the
Fairway Rehabilitation and Maintenance Master Plan until June 2015.
Further development within FAIRway:
• Develop 1st version further
• Update national action plans yearly
• Elaborate pilot implementation concept and evaluation framework
Page 7
Activity 3 Procurement of hydrological
service pilots
Joint market survey, aligned technical specifications, preparation of
procurement documents with support of international experts
Joint tenders envisaged for transnational waterway asset management system.
Data gathering
Surveying vessels
and gauging
stations, floating
ship data
Data processing and analysis
Waterway asset
management
system
Water level
prognosis
Respond to data
Multifunctional
marking equipment
Page 8
Activity 3 Pilot operation over 3 years…
Exploit full
potential of
navigation
conditions
through dynamic
marking
Systematic
decision
support
through
improved data
analysis.
Optimized surveys
with denser
intervals at
critical locations.
Strategically
placed water level
gauges deliver
basic data.
Matchable
water level
prognosis
displayed in a
harmonized
way.
… to gain experience for the full deployment of the FRMMP
Page 9
Activity 5 Innovative approaches
Add new perspectives to the waterway administration.
• Aerial photo monitoring concepts
• Optimum speed at navigable canals
• Recalculation of Low Navigable Water Level at the Lower Danube
• Agree on AIS AtoN application standard
Page 10
Activity 6 Documentation for full
deployment
Prepare for the full implementation of the Fairway Rehabilitation
and Maintenance Master Plan based on the national roadmaps
and pilot results.
• Feasibility studies in Slovakia (Lower Váh and Gabcikovo)
• Prepare implementation of additional measures
Page 11
Thank you for your attention!
Contact
Andreas Bäck
viadonau
Strategy & Action Programmes
T +43 50 4321-1609
[email protected]
Donau-City-Straße 1, 1220 Vienna
Seite 12