SOUTH SACRAMENTO COUNTY STREAMS GROUP UPDATE Marshall Marik

Project Manager South Sacramento Streams Group Sacramento District January 19, 2012

US Army Corps of Engineers Sacramento District BUILDING STRONG ®

Morrison Creek Construction Along Union Pacific Railroad  Construction kick-off meeting was held January 5th.

 Constructor has provided pre-construction submittals for review.

 Coordinating with Sacramento Municipal Utilities District for gas pipeline protection plan.

BUILDING STRONG ®

Post Authorization Change Report (PACR)  Existing conditions hydrology is certified.

 Floodplain work is on-going.

 PACR is scheduled to complete in July 2014.

BUILDING STRONG ®

Marshall Marik US Army Corps of Engineers 1325 J Street Sacramento, CA 95814-2922 (916) 557-7698