Middle School Expansion August 11, 2003

Download Report

Transcript Middle School Expansion August 11, 2003

Middle School Expansion
August 11, 2003
8-11-03 Brick going up on north
side next to classrooms.
Rain test on new roof. Roof at
60% completion.
Main east west corridor.
Typical entrance detail to classrooms.
Main north south corridor. Looking to the the south.
Main east west corridor looking toward the west.
Vestibule looking toward the southwest.
Profile of building from the southwest corner.
Brickwork at about 20%.
View from Amethyst.
The Project is going well.
We will be ready for students to use the
modular at the start of the school year.
The six-classroom addition is on budget and on
schedule. It will be ready for occupation as
scheduled in early 2004.
Rick Denney, Facilities Director 8-11-03