Seattle City Light’s
10 – Year Transmission Expansion Plan
The following are the planned transmission project at SCL for the
next ten year. All the projects has no major impact to the bulk
transmission system. Most of our work are all internal
transmission lines and generator reconnection.
• 115kV North Seattle Transmission Lines upgrade
• 230kV Transmission lines to proposed new substation
• Boundary Transformer replacement with connection to existing
115kV transmission line
• BPA’s Proposed Summer Falls and Main Canal Hydropower
interconnection 115kV Transmission Line
1
Project:
115kV North Seattle Transmission Lines upgrade
Description:
Increase North Seattle 115kV Transmission line capacity and to improve
transmission reliability. Perform retension, reconductor, and/or raise existing
115kV transmission lines in the northend of Seattle to 100 degree C conductor
temperature if possible. Eight lines need to improve ratings. Four lines have
been improved to 65 degree C so far. The other four (BO-SH#1, BO-SH#2, BONO, & BO-UN) are being evaluated for improvement.
Sponsor: SCL
Construction consists of:
• Fixes to BO-SH#1, 11.27 miles, 954 kcmil ACSR Rail
• Fixes to BO-SH#2, 10.93 miles, 954 kcmil ACSR Rail
• Fixes to BO-NO, 14.61 miles, 795 kcmil AAC Arbutus
• Fixes to BO-UN, 16.69 miles, 795 kcmil AAC Arbutus
Schedule completion: 2007 - 2008
Status: Planning
Project Manager: SCL
2
Project:
230kV Transmission lines to proposed new substation
Description:
Proposed to build a new substation in the north of downtown
area to serve load growth. A 200MVA, 230kV substation with connection to 3
transmission lines. Construct 230kv transmission lines. Location to be
determined
Sponsor: SCL
Construction:
• Install 2 miles of underground 230kV transmission line from East Pine
Substation to New Substation and 230kV/115kV autotransformer
• Install 6.5 miles (4.5 miles of overhead and 2 miles of underground 230kV
construction) energized 115kV transmission lines from Canal Substation
to New Substation
• Connect existing 115kV transmission from Broad St. Substation to New
Substation
Schedule: 2010-2012
Status: Planning stage, commitment base on load growth and type of distribution
system.
Project Manager: SCL
3
Project:
Boundary Transformer replacement with connection to
existing 115kV transmission line
Description:
Bonneville Power Administration (BPA), Seattle City Light (SCL) and Pend
Oreille PUD (POPUD) have negotiated the Boundary Transformer Agreement,
which provides for installation and operation of a transformer and breaker in the
Boundary Substation to allow for the cost-effective delivery of Article 49 Power
and tailwater encroachment compensation from the Boundary Project to the
POPUD via SCL’s Boundary Tap Line and BPA’s Box Canyon Tap Line.
Installation of a 230/115KV autotransformer in the Boundary Switchyard to
interconnect to SCL's 115KV Boundary transmission tap line will also enhanced
electric grid reliability.
Sponsor: SCL, BPA, Pend Oreille PUD
Schedule completion: 2009
Construction consists of:
• Remove old transformer
• Install a new 160MVA, 230kV/115kV autotransformer
• Install a new 115kV breaker
• Connect to existing 115kV transmission line
Status: Transformer purchase with construction scheduled
Project Manager: BPA
4
BPA’s Proposed Summer Falls and Main Canal
Hydropower interconnection 115kV Transmission Line
Description:
BPA proposes to construct a new Main Canal-Pinto Ridge single circuit 115-kV
wood pole transmission line from the Main Canal hydropower project for eight
miles and connect to the new Pinto Ridge Substation. BPA also proposes to
construct a new Summer Falls – Pinto Ridge single circuit 115-kV wood pole
transmission line from the Summer Falls hydropower project for two miles and
connect into Pinto Ridge Substation. The proposed transmission lines and
100 foot wide easements would be purchased and owned by Seattle City Light
and Tacoma Power
Sponsor: SCL, TP
Construction consists of:
• Constructed 115kV transmission line from Main Canal to new 230kV
substation called Pinto Ridge
• Constructed 115 kV transmission line from Summer Fall to new 230kV
substation.
Schedule Completion: 2008
Status: Planning
Project Manager: BPA
Project: