The Do’s and Don’t of Modernization

Download Report

Transcript The Do’s and Don’t of Modernization

The Do’s and Don’t of Modernization
AAMVA Panel Discussion, July 18, 2012
Nancy Dumais, Program Manager
CT DMV Modernization
Current State
•
Summary:
–
CT Modernization (CIVLS)
• Under contract with 3M
» Fixed Price
» Start: Jan 2010
» Target completion - 2013
• MOTS solution approach
• Scope: Full, agency-wide, integrated solution all DMV business areas
» Regulated Business Licensing (Dealer Licensing, Driving School Licensing, Fiscal)
» Vehicle Services: Title and Registration (R2)
» Driver Services: Licensing and Sanctioning (R3)
• Timetable (see graph, next slide)
• Summary Status (Green, Yellow, Red): Time, $$, Schedule
2
CIVLS Project Timeline
1Q
CIVLS
Kickoff
2012
2011
2010
2Q
3Q
4Q
1Q
2Q
3Q
4Q
1Q
2013
2Q
3Q
4Q
Licensing Managed and Regulated Businesses
Release 1
Mar 2011
Web Renewals – Dealer Licensing
Release 1A
Release 2
4/2011
Feb/Mar 2012
Vehicle Services: Registration & Title
Nov 2012
9/2010
8/2011
Release 3
Driver Services: Licensing & Sanctioning
Jun
2013
3
Our Journey to Modernization
•
Initial Approach: ReROD/RTOL
–
–
•
ReROD: Custom Build (in-house)
RTOL: Custom Build (vendor to develop)
Got firm handle on AS-IS and TO-BE Environment –
Strategic Operational Assessment and Future State Design (BCP2)
–
–
–
–
Driven by DMV Strategic Plan
Assessed Current State
Incorporated DMV Best Practices
Developed Future State Business Processes
–
Developed Future State Technology Architecture
•
•
Stepped back: New Approach: A COTS/MOTS Enterprise Solution
–
What’s COTS/MOTS?
–
•
Confirmed availability of COTS/MOTS solutions in marketplace
Took “Deep dive” on key DMV business processes
–
–
–
Documented “core” business requirements to DMV “Repository”
“Signed off” by DMV Business Owners
Documented “supporting” DMV business processes and requirements
•
•
Audit, Records Management, etc.
Completed RFP & Contracting Process
–
–
–
–
•
Design workshops with DMV Staff
“Re-signed off” by DMV Business Owners
Issued RFP
Conducted 2-Day, On-Site Hands-On Demos for all vendors
Negotiated Contract
Documented Business Rules
–
On-going
4
Panel Topic Areas: Experiences
RFP Drafting
•
RFP Drafting: April – July, 2008
•
Lessons learned from prior RFP modernization
»
•
Significant preparations paid off
»
»
»
•
Engaged IBM consultants for Strategic Operational Assessment and Business Requirements
Surveyed other states on modernization activities and lessons learned
Developed “readable” RFP/Requirements for MOTS solution
Successful “hands-on” vendor evaluation process
»
»
»
•
RFP too big, too detailed, hamstrung proposers, complicated negotiations, ultimately cancelled award
Filtered out all but experienced vendors (3 bid)
Was a “hands-on” operational prototype used as basis for evaluation
Broad agency representation at Executive and business unit level
Selected vendor team: Prime Vendor/Integrator + Product Vendor
»
Learned lesson: choose vendor with a stake in the product and the DMV market
5
Panel Topic Areas: Experiences
Contract Negotiation
•
Contract Negotiation: March – July, 2009
•
•
•
•
Benefited from external support from legal, business, technical, contractual experts
Negotiated a “deliverables-based” contract
6 month delay from AG Office
Kickoff Feb 2010
6
Panel Topic Areas: Experiences
Project Management
•
Project Management
•
Contracted with Prime vendor as Integrator; Product vendor as sub
»
•
It really “takes a village”: It does, but how do you shepherd the flock?
»
»
•
CT found that the partnership didn’t work as well as working directly with Product Vendor
Significant internal state staff required: staff depth of expertise mixed; staff unaccustomed to large-scale
project work
•
Average staff support level: 19 people (core team + part-time SMEs)
•
Consultant staff required for specialized expertise areas
•
IT staff challenges (DMV IT, State IT)
Roles/Responsibility challenges (hard to make boundaries: Who really owns what? Who decides what?)
Turnover challenges: It really takes continuity, but how do you keep the team in tact throughout?
»
»
State
•
1 State PM throughout; 8 Vendor PMs
•
Commissioner turnovers: Administration changes, legislative changes, agency interface changes
•
Business Owner changes due to org changes and retirements
•
Retirees left major knowledge and experience gaps
•
Changes made decision-making challenging
Vendor(s) staff changes:
•
PM turnover in Prime Contractor team
•
PM turnover in Subcontractor team
•
Overall: 8 Project Managers to date
•
Significant learning curve and transition pains with each transition (business analysts, technical staff,
management staff)
7
Panel Topic Areas: Experiences
Project Management
–
Project Management (continued)
•
Solution Design challenges: paid for “integrated” solution; not fully realizing it (prepare to bend)
»
»
•
•
“Integrated solution” easier said than done
•
Vendor product(s) not really “plug and play” – not fully consistent functionality across product suite
•
Product and solution “silos” hard to breakdown
“customer-centric” easier said than done: individual customers, organization customers (Dealers, Leasing
companies), all have challenges in data, business processes, implementation, etc.
Iterative Phases: A challenge but necessary
Lessons Learned:
»
Dig in up front in 1st 90 days
•
with hands-on teams including business owners, IT, solution developers
•
reconcile what’s in and what’s out UP FRONT
8
Panel Topic Areas: Experiences
System Deployment
•
System Deployment
•
Multiple, overlapping releases –
»
»
»
•
Data, Data, Data!
»
•
R1 proved out infrastructure with small business area
R1A proved out web infrastructure
R2 – in process, learned from prior releases
Conversion and data quality issues abound
•
Caused Release 1 GO LIVE slip
Stick to Schedule, or STOP
9
Panel Topic Areas: Experiences
Training
•
Training
–
Lessons Learned: TRAIN EARLY, TRAIN OFTEN
• Release 1 – Training delivered just prior to GO LIVE
» Too much change in too short a time
•
New system, new processes, new roles
•
Timing conflicted with peak workload periods
•
Training gaps experienced post-GO-LIVE
• Release 2 and Release 3 – Revised approach
» Conducted hands-on, “out of the box” training EARLY
•
Trained Project team members, Business owners, Managers, and SMEs
•
Improved “MOTS” understanding during design work
•
Trained Branch personnel EARLY (12 months prior to GO LIVE)
•
Trained Branch Managers as “Trainers” (with support from Project Team)
•
Rolling Branch office closures (2-4 days) over 2 months (Feb/March)
•
Branch Managers delivered hands-on, in-Branch training to all Examiners
•
THREE stages of Training: (1) “Out-of-Box”, (2) CT-specific, and (3) GO LIVE
•
Commissioner, Project Manager met with all Branch staff at all Branch offices
•
Results: (via direct feedback and on-line survey results)
•
Tangible demonstration of management commitment to Project and Staff
•
Improved understanding of new system, new processes, and new policy changes
•
Built support and advocacy for modernization
Discussion / Q&A
Questions?
11