Transcript Slide 0

Cable Rehabilitation Program
(Second Responder Cable Treatment Program)
By Lee Maurer
Maintenance Planning
SWEDE Conference
April 26, 2011 - Bastrop, Tx
Oncor System Overview
27,000 Square Miles of Territory
630 miles
3.2 Million Electric Service Points
3,000 Circuits
Miles of Underground Primary
(Networks not included)
390 miles
 17,218 Cable Miles – URD
 4,641 Cable Miles – Feeder
 21,859 Total Miles.
Miles of Overhead Primary
 10,608 Mainline Primary
 13,026 3ø Non-Mainline
 5,006 2ø Lines


27,212 Single Phase Lines
55,852 Total Miles
LM- Maintenance Planning
11
Cable Components
Pre-1990
Tinned Copper Insulation
Concentric Neutral Shield
XLPE or
HMWPE
Insulation
Since 1990
TRXLPE
Insulation
Aluminum
Conductor
Conventional
Conductor Shield
LM- Maintenance Planning
Jacket
Bare Copper
Concentric
Neutral
Insulation
Shield
Aluminum
Conductor
(Strand-filled)
Super Smooth
Conductor Shield
2
Primary Underground Cable
(Network Excluded)
Previous specification cable
Current specification cable
3
Primary Cable Faults
LM- Maintenance Planning
4
Cable Rehabilitation Program - Background
 System wide maintenance plan (Second Responder) for extending the life of
aging infrastructure
 Pre-1993 PE cable issues
 8,000 cable miles – Pre-1993 PE cable
– 7,000 cable miles – URD
– 1,000 cable miles – Feeder
 Cable Manufacture 1980 - 1995
– General Cable, Hendrix, Pirelli (Now Prysmian), Southwire
 Capital Rehabilitation method for aged cable
– 235 cable miles rehabilitated (By Utilx)
 Cost effective alternative to replacement of cable
 Additional 600 cable miles rehabilitated in other programs
LM- Maintenance Planning
5
Second Responder Process
When a cable faults, the troubleman (first responder) determines if the
cable is loop fed and if the faulted cable can be switched out.
Padmount Transformer
Pole Riser
Normal Open Point
Fault
Isolated Faulted Cable
LM- Maintenance Planning
6
Second Responder Process (cont’d)
 If the cable can be switched and service restored to the customers, the location
of the faulted cable is sent to Oncor Program Services.
 Program Services will then schedule a Utilx cable repair/rehabilitation crew to
the cable.
 The crew will attempt to repair and inject the cable with rehabilitation fluid.
LM- Maintenance Planning
7
2nd Responder Process
 4,291 sections of failed cables came through the process
since 2008
– 65% were able to be injected successfully.
 235 cable miles have been rehabilitated using 2nd
responder process since 2008.
LM- Maintenance Planning
8
Business Comparison
 Cable Repair - Splicing
$X
– O&M Cost
– Same old cable
 Rehabilitation of Span
$ 4X
– Capitalized Cost
– Added 20+ years of life
 New Cable (Bore)
$ 15X
– Capitalized Cost
– New 40+ year asset
LM- Maintenance Planning
9
Business Considerations that Prevent Rehabilitation
 Cable installed in conduit (except preventative)
 Corroded concentric neutral of 25% or less remaining
 The faulted cable section must not have been deenergized more than six months.
 There cannot be more that one joint per 100 feet of
cable. (Business Case)
 Other Technical Reasons
– Butyl rubber cable
– Cable with tape conductor shield
– Loss of insulation shield conductivity
– Insulation shield with no adhesion
LM- Maintenance Planning
10
Questions
Oncor Contacts
Lee Maurer
Senior Manager
Mark Darilek
Project Manager
Mike Sulak
Program Manager
Richie Harp
Consulting Engineer
Maintenance Planning
Maintenance Planning
Operations/Program Services
Distribution Standards
817-215-6128
[email protected]
817-215-6809
[email protected]
817-215-6151
[email protected]
817-215-6008
[email protected]
Fort Worth, TX
11