No Slide Title

Download Report

Transcript No Slide Title

1

The Severn Barrage

Presentation to Severn Estuary Forum 8 th June 2006 David Kerr Sir Robert McAlpine

2

Tidal Power from the Severn Bondi study (EP46 - 1981) was the first major study Tripartite study (EP57 - 1989) defined the present scheme Could produce power by 2017 if progressed soon

3

Location:

• Bristol Channel/ Severn Estuary • Downstream of Cardiff to Weston-super-Mare • 16 km length

4

Tidal Power

• The Barrage impounds the tide, then the water is released through a turbine to generate electricity • Proven Technology: La Rance in France has generated tidal power reliably for over 35 years

5

Barrage Operation

6

Barrage Layout (1989 Report)

• 216 Turbines, 40MW each, 8640MW total • 166 Sluices 35,000m 2 • Ship Locks • Small Locks • Public Road

7

Facts and Figures

     Annual Output 17 TWh (5% of UK consumption) Installed Capacity 8640 MW Renewables Obligation:  15% by 2015 (50-55TWh) - Barrage cannot contribute  20% by 2020 would require a further 17TWh. Barrage could contribute all of this - if sanctioned soon Capital Cost £8Bn 1989 > ~£14Bn 2005 – needs re-estimate Security of supply benefit

8

Environmental Studies 1989

A total of 70 studies, with a budget of £2M, covering: • Hydrodynamics (tides, currents, waves) • Sediments, Salinity, Water Quality, Drainage • Ecology, Birds, Fish

9

Main effects of the Barrage

Tide Range reduced from 14m to 7m (springs)

 A smaller inter-tidal area  Reduced currents, leading to:-

A large reduction in suspended sediment

 Sunlight penetration through the water column  An increase in dissolved oxygen to more normal levels  A more stable seabed with more life

Expected to Result in an increase in bird species and numbers

10

Flood protection in the Severn Estuary and Rivers

• Flooding in the estuary can occur when extreme high tides coincide with storm surges • Flooding in the rivers can occur when these same sea conditions coincide also with high river flows • The water level in the basin can be controlled  To prevent the flooding in the estuary (upstream of the barrage)  To avoid obstruction to river flow caused by high tides

11

Use Of Barrage for Flood Protection

12

Environmental Balance ?

• Loss of the unique harsh environment • Some birds may lose habitat • Marine life and other birds will increase • Flood protection to estuary and rivers • Carbon Saving

The environmental assessment needs to be updated to account for the changes in the Estuary since the 1980’s and also the changes in legislation

13

Transport Key Issues

Ports and Shipping

• Forecast Shipping Movements • Size of Locks to suit Portbury & Avonmouth

Road and Rail

• Cost-benefit of a Barrage Crossing

14

Construction : Prefabricated Caissons

15

Caisson Construction Sites • 1989 report identified potential UK sites shown •Potential Sites in Europe • Project and Employment Benefits of using many Sites

16

Turbine Installation

17

Cost – Price relationship

Tax Equity Return Transmission Opex Transmission Capex Barrage Opex Barrage Capex

p/kWh April 2005 money

10 9 8 7 6 2 1 0 5 4 3 Cost ILEX April 2005 spot market forecast Actual Price 7 Dec 05 ROC recycle ROC buyout Wholesale electricity price

18

Conclusion

The Severn Barrage should be re-examined as part of the Energy Review

19

20

Flow Patterns with Barrage

21

Construction Sequence (1989 Report)

22 Cardiff Gloucester Bristol

Areas at Risk from Flooding

23

Modes of operation Ebb Generation:

Preferred for most schemes

Flood Generation Less usable water volume Two Way Generation No extra Energy Higher cost of Energy due to more complex turbines Energy is spread over more of the day

24

Outline Programme for Implementation