Presentation 2 - Wisconsin Housing Alliance
Download
Report
Transcript Presentation 2 - Wisconsin Housing Alliance
Installation Codes
Manufactured Home Installer Course
Part 2
1
Licensing for Installers
What’s been the Timeline?
Jan 1, 2007 –licensing began
April 1, 2007 – new installation code
effective and inspections began
2
Licensing
You need a license to install a home on a
foundation. If you ONLY do the following
no license is required:
Anchoring – no
Grading – no
Excavation – no
Pouring basement – no
The person supervising the home going on
the foundation - yes
3
Licensing
Your license is subject to the
requirements for General Supervision
– the installer does not need to be on
the job site but must be available to
the building inspector
Homeowners are exempt from
licensing but if people help and would
otherwise need a license they must
be licensed
4
Licensing of Installers
Qualifications
18 years old
Not been found responsible in any court
or agency hearing of a violation of the
installation law during prior 2 years
Not been found responsible in any court
or agency hearing for failure to perform
under installation contract or defrauding a
person in the provision of installation
services
5
Application for Installers
License
A state license fee plus one time
application fee for 4 year license
Take 12 hour qualifying class & pass
exam
6
Renewal
Renewal requires 12 hours of
continuing education over the 4 year
period
Also must not have been found
responsible for breaking the rule or
defrauding a customer
7
Wisconsin Installation Standard
Act 45 laws of 2005 authorized the
Department Commerce to adopt
standards
8
Comm 21.40
Formerly Comm 27.18
Now a part of the UDC
Applies to homes built before April 1,
2007
April 1, 2007
Comm 21.40 applies
Part 3285 applies
Home Built before April 1
Home Built on or after April 1
Code starts on page 9 of your workbook
9
All Pre April 07
Homes follow
Comm 21.40
10
Even this one!
11
Comm 21.40
Review pages 9 and 10 of your
workbook for all of the details
regarding the code for Pre-April 1,
2007 built homes.
12
Comm 21.40 for homes before
4/1/2007
No footing on unprepared fill. All
organic matter must be removed.
Soil bearing test using pocket
penetrometer
Grade site to drain water away for
minimum of 5 ft from home
A footing for every pier, nominal 16”
by 16”
Consult others if soil is less than 2000
psi
13
Comm 21.40 Footings
one 4 by 16 by 16 solid blocks or two
4 by 8 by 16 solid blocks.
16 by 16 ABS pad rated at not less
than 6000 lbs
18 inch diameter hole bored below
the frost line or to unfractured
bedrock and filled with poured
concrete
Other materials or systems approved by Commerce
14
Note: frost protection not required
ABS Pads
ABS pads
are
permitted for
homes built
prior to April
1, 2007.
The
honeycomb
always faces
up
15
Not all ABS Pads are the Same!
4755
lbs/sq ft
4000
lbs/sq ft
5000
lbs/sq ft
In 2000 pfs soil, the capacity of each pad is as shown
above, also the direction of a single stack of blocks is
specified on the back with arrows.
16
Comm 21.40 Piers
Concrete blocks, manufactured steel
stands or manufactured concrete stands
Single stack piers limited to 36 inches
Single stack piers loads limited to 8,000
lbs
36 to 80 inch piers – double blocked
(layered in opposing layers)
80 inch or more – double blocked laid in
concrete mortar, cores filled with mortar
and ½ inch steel reinforcing rod*
Note mortar and reinforcing rod is more
stringent than Part 385
17
Comm 21.40 Concrete Blocks
2 core design, construction grade
8x8x16
Cores placed with cores open
vertically
Block nearest main frame shall be
perpendicular to the linear direction
of frame
No block may contact the frame
18
Comm 21.40 – Pier Spacing
No more than 7 feet on center
No more than 3 feet from exterior
side of each end wall
Can be varied to follow manufacturer
tables
Piers under clear-span openings of 4
feet or more in mating walls
Piers must be plumb and centered
under point of support
19
Comm 21.40 - Caps
Solid concrete block or solid wood
block having nominal thickness of at
least 2 inches
Cap must be same width and length
as top of pier
No more than 2 pieces – 2 piece caps
positioned with joint perpendicular to
frame if used
20
Comm 21.40 - Shims
Where used, driven from opposing
sides and be no less than 4” by 8”
Wood caps and shims at least equal
to #2 spruce pine fir with min
bending stress rating of 1200 psi. All
wood caps must be of same species
of wood. All shims must be of same
species of wood.
Note - shims not required but concrete blocks cannot
contact the frame.
21
Comm 21.40 – Height limits
Combination of nominal 2
inch solid concrete block or
wood cap plus shims must
not exceed 3 ½ inches
Minimum clearance under home of 12 inches between
lowest point of main frame in area of utility connections.
Min clearance of 12 inches for 75% of home. Remainder
may be less than 12 inches but cannot touch ground
22
Recap on 21.40 on key items
All organic matter removed
Proper drainage
7 foot maximum spacing between piers
Construction grade blocks
Any hardwood used must be the same species
If ABS pads used, honeycomb is up
Double stacked blocks above 36”
23
Federal Installation Standard
Known as Part 3285 this code applies
to home built on or after April 1,
2007.
The Wisconsin changes are noted in
the text in your binder – latest
changes were 3/19/09
24
The Standards
3280 – HUD Construction Standards
for the home
3285 – HUD Model Installation
Standards
The following must be AT LEAST AS
STRINGENT as the federal model
State Standards
Manufacturer Manuals
25
Understanding Part 3285
Use the Blue and Red Cheat Sheet
This Key to the Code will help you
find applicable sections as you use
the code quicker!
26
Definitions
Words have meaning so read them
carefully – see 3285.5
For example, an anchor is a part of
an anchoring system.
27
DAPIA
DAPIA – means Design Approval
Primary Inspection Agency
A manufacturer must provide with
each new home a DAPIA approved
designs and instructions that are
consistent with the standards –
3285.2
28
Application of the Standard
These standards apply to HUD
Code manufactured Homes not
modulars.
29
Fire Separation
Fire separation distances in accord
with NFPA 501(a) must be
maintained. Means 10 feet
Fire separation distance must also
comply with Comm 26 in a mobile
home park
(10 feet between basic
structures)
Local ordinances might have
additional requirements
30
Flood Zones
Installer is responsible to
determine if home is being
installed in flood zone.
3285.102(c) – Contact the zoning
administrator for the county
If it is, special installation methods
are required.
Note there are also Shoreland
zoning implications
31
Zone Maps
3 maps in the HUD Code
Wind – Wisconsin in Zone 1
Roof Load – Wisconsin is South and
Middle Zones
Thermal Zone – Wisconsin is Zone 3
U/O value must be less than 0.079
U/O is inverse of R value 0.079 = R 12.6
Homes may not be installed in a wind
zone that exceeds the design load for the
home.
32
See pages 11 & 12 in your workbook
Site Preparation
Soil tests can be conducted with a pocket
penetrometer
Footings must be sized and spaced
according to soil bearing capacity
See the tables in 3285.202
Poor soils – peat, organic clays or
uncompacted fill require a geologist,
engineer or architect’s opinion
33
Site Drainage
Drainage must be provided to direct
surface water away from home and
prevent build up under home.
Minimum slope of ½ inch per foot for
the first 10 feet for homes built on or
after April 1, 2007 and 5 feet for
older homes.
Where site is sloped, home must be
protected from surface runoff
34
Crown and Grade Site
35
36
Controlling Water is Critical
37
Gutters and Downspouts
Manufacturer must specify if the
home is designed for gutters and
downspouts
When installed, runoff must be
directed away from the home
38
Ground Moisture Control
Vapor barrier must be installed
Min. 6 mill poly or equivalent
Overlap 12 inches and seal
Barrier may be under, over or around
footings
Voids and tears must be repaired
3285.204
39
Ground Moisture Control
1 pint of water vapor is generated
in 24 hours
@ 55 degrees under 10 sq. ft of
floor area. 1500 sq ft home then
equals 150 pints of water. That’s
16-19 gallons of water
40
Foundations - Piers
Concrete blocks – Must conform to
ASTM standard C 90-02
Pressure treated wood – think pilings
Adjustable metal - Manufactured
piers must be labeled or listed for
loads and installed to the pier
manufacturer’s instructions
41
Pier loads
Must be designed with load taken into
consideration
Spacing is dependant on factors such
as soil bearing capacity and foot size
See tables at 3285.303
Pier spacing tables do not take into
consideration flood or seismic loads
42
Pier Configuration
Load bearing blocks not decorative
Nominal 8 by 8 by 16 inches
Stacked with hollow cores aligned
vertically
When stacked side by side, each
layer at right angles to preceding one
Center beam/mating line supports are
always required for multi-section
homes
Primary failure regarding piers is insufficient sizing of mating
line piers under ridge beam openings
43
A single block pier requires a
minimum 18” diameter footing!
44
No part of the pier can overhang the
footing!
45
Caps
Must evenly distribute loads across the
capped hollow block piers
May be made of solid concrete or
masonry at least 4 inches nominal
thickness OR
hardwood lumber at least 2 inches thick
46
Caps
Must be same length and width as
piers
Split caps on double stacked piers
must be installed with long dimension
across the joint in blocks below
47
Gaps
Must be filled
Options
2nd 4” concrete block but cannot contact
frame
Nominal 4 by 6 by 1 inch shims
•
a.
b.
c.
Must be used in pairs
Driven tightly
Must not occupy more than 1 inch of
vertical space
48
Manufactured Piers
Adjustable risers
must not extend
more than 2 inches
when finally
positioned
49
Clearance under Home
Minimum of 12 inches between lowest
member of main frame and grade under
all areas of the home
Comm 21.40 for older homes is
A minimum clearance of 12 inches shall be maintained
beneath the lowest point of the main frame in the area of
any utility connection. A minimum clearance of 12 inches
shall also be maintained under the home for at least 75%
of the home. The remainder of the home may be less
than 12 inches above the ground but may not touch the
ground.
50
Less than 36” Piers
Permitted to be constructed of open or
closed cell 8 by 8 by 16 when capacity
of block is not exceeded
Long sides are at right angles to
supported I-beam
Hollow cores stacked vertically
Horizontal offsets from top to bottom
not to exceed ½ inch
No mortar unless instructions require
it
51
52
53
Piers 36 to 67” and Corner Piers
All frame piers 36 to 67” high and all
corner piers over 3 block high must
be double blocked
No mortar unless instructions require
Horizontal offsets not to exceed 1”
54
55
56
Hardwood plate must
run in same
direction as
concrete cap
Bottom 2 courses must
be spun around
57
Perimeter support piers
Piers at mate-line supports, perimeter
piers, and piers at exterior wall
openings can be single open-cell or
closed cell blocks to a maximum
height of 54 inches
Must be installed with the long
dimension parallel to perimeter rail
58
Pier Support Locations
No more than 24 inches from both
ends of frame
No more than 120 inches center to
center under the main I beam
Mating line, marriage wall line, ridge
beam all mean the point where
sections join and they require support
– Be alert to extreme weight
considerations in these locations!
59
Perimeter Support Locations
•
•
•
Both sides of any exterior door
Any side wall opening of 48 inches or
more
Under any load-bearing porch posts,
factory installed fireplaces and wood
stoves
3285.311
60
Alternative to Perimeter
Supports
If additional floor joists or outriggers
are providing perimeter support, the
sizing of piers and footers under the
main chassis beam must be adjusted.
61
Footings
Must be located on undisturbed soil or
fill compacted to 90% of maximum
relative density
A footing for every pier
Footing size depends on the load
bearing capacity of soil, footings and
piers
3285.312
62
Footing Types
Concrete types
4 inch nominal precast pads meeting
ASTM C 90-02 with 28
day compressive
strength of 1,200 psi
6-inch minimum
poured in place
concrete pads or slabs
with at least 28 day
compressive strength
of 3,000 psi
Bad footing
63
Footing Types
ABS footing pads – not really applicable for
new homes since no frost protection
Installed according to pad manufacturer
instructions and certified for use in soil
classification at the site
Must be listed for required load capacity
Treated Wood – not really applicable since
limited frost protection except for elevated type
installations (pilings)
64
Frost Protection
Only 3 ways in Wisconsin to install a post April 07 home
Footings must be designed using
methods and practices that
prevent the effects of frost heave
by:
1. Conventional below the frost line
footing
2. Monolithic slab above frost line –
Commerce has issued
acceptable design
3. Insulated foundation system
above frost line
3285.312
Frost line is 48 inches statewide as set
by Commerce
65
Acceptable Slab Design
Seal is not required in Wisconsin
version of installation standards per
Comm 20.09(4)b
Larry Swaziek of the Department of
Commerce issued an Acceptable Slab
Design
(see page 94-95 in your workbook)
66
Acceptable Slab Design
6” thick
10” thickened edge with rebar
Min 3000 psi concrete
Make sure you read the footnotes for
design limitations very carefully
67
68
69
Footing Sizing Table
How to use the tables
Use soil bearing capacity to
determine size and thickness
needed
70
This is a simplified pier plan for a home – 3 of the I-Beams are deleted
Calculate Bearing Points
for clarity
Note that the marriage line
piers are not equal distance
apart
71
This is a simplified pier plan for a home – 3 of the I-Beams are deleted
Calculate Bearing Points
for clarity
Write down all of the weights
that exceed 5300 which is the
capacity of a 6 inch thick slab
72
Look at the chart on the next page and
note the following things:
1. Your soil bearing capacity – this
section the table from pages 37-38
of your manual assumes 2000 psf
soil.
2. What is your roof load zone? For our
example we’ll use 30 psf.
3. What is the pier spacing you want to
use?
73
Table 1 – Frame only blocking
Pier Spacing
4 ft
6 ft
8 ft
10 ft
Roof Live Load
Location
Load (lbs)
20
Frame
2900
30
Frame
3300
40
Frame
3600
20
Frame
4200
30
Frame
4700
40
Frame
5200
20
Frame
5500
30
Frame
6200
40
Frame
6900
20
Frame
6800
30
Frame
7600
74
Table 1 – Frame only blocking
Pier Spacing
Roof Live Load
Location
Load (lbs)
All under 8000
4 ft
2000 pfs soil
6 ft
8 ft
10 ft
Pages 37 - 38
20
Frame
2900
30
Frame
3300 ok
40
Frame
3600
20
Frame
4200
30
Frame
4700 ok
40
Frame
5200
20
Frame
5500
30
Frame
6200 NO
40
Frame
6900
20
Frame
6800
30
Frame
7600 NO
75
Keys
Don’t exceed 8,000 lb capacity of
single stack of blocks or 16,000 lb
capacity of double stack
If print shows required perimeter
support make sure it is present
Concentrate on largest loads first
usually the mating line
A + B dictates C
76
3 factors to consider
A. soil bearing capacity
B. pier spacing
C. footing size
A + B dictates C
77
Footing tables
On pages 55-57
You can read these tables the same
way.
78
Footing Sizes –
Table on Pages 55 -
56
8 by 16 in. pier
16 by 16 in pier
Soil
Capacity
Min
Footing
Size
Max
Footing
Capacity
Min
Max
Thicknes Footing
s
Capacity
Min
Thicknes
s
2000
16 x 16
3,400
6
3,400
6
20 x 20
5,300
6
5,300
6
24 x 24
7,600
8
7,700
8
30 x 30
11,600
10
11,900
10
36 x 36
16,300
15
16,900
10
42 x 42
21,700
18
22,700
12
79
A 6 inch slab cannot be used under
portions of this home that exceed
5300 lbs
That means the marriage line area
must be thickened
For below the frost line footings, pier
loads above 3400 lbs require double
blocking and larger footings that 16 x
16.
80
Calculate
Pointsthe Foundation
Let’s Use theBearing
Tables to Design
Note the load amounts
If this is a slab set note that
mating line must be more
than 6” thick per tables
81
Biggest Load –
Table on Pages 55 -
56
8 by 16 in. pier
16 by 16 in pier
Soil
Capacity
Min
Footing
Size
Max
Footing
Capacity
Min
Max
Thicknes Footing
s
Capacity
Min
Thicknes
s
2000
16 x 16
3,400
6
3,400
6
20 x 20
5,300
6
5,300
6
24 x 24
7,600
8
7,700
8
30 x 30
11,600
10
11,900
10
36 x 36
16,300
15
16,900
10
42 x 42
21,700
18
22,700
12
Footer 24 x 24 satisfies 7000 lb mating line load for below the
frost line footings
82
Biggest Load –
Table on Pages 55 -
56
8 by 16 in. pier
16 by 16 in pier
Soil
Capacity
Min
Footing
Size
Max
Footing
Capacity
Min
Max
Thicknes Footing
s
Capacity
Min
Thicknes
s
2000
16 x 16
3,400
6
3,400
6
20 x 20
5,300
6
5,300
6
24 x 24
7,600
8
7,700
8
30 x 30
11,600
10
11,900
10
36 x 36
16,300
15
16,900
10
42 x 42
21,700
18
22,700
12
83
8” Slab thickness satisfies 7000 maximum load on mating line
Biggest Load –
Table on Pages 55 -
56
8 by 16 in. pier
16 by 16 in pier
Soil
Capacity
Min
Footing
Size
Max
Footing
Capacity
Min
Max
Thicknes Footing
s
Capacity
Min
Thicknes
s
2000
16 x 16
3,400
6
3,400
6
20 x 20
5,300
6
5,300
6
24 x 24
7,600
8
7,700
8
30 x 30
11,600
10
11,900
10
36 x 36
16,300
15
16,900
10
42 x 42
21,700
18
22,700
12
84
20 x 20 or 6” slab satisfies all other loads
Tables Assume Square Footings
It is a major mistake to read the footing
tables in square dimensions and not
properly translate those figures to a
round bored hole.
85
Translating
□ to O
Area of a circle is:
PI x radius of circle
Quick Calc
3.14 x (9 x 9) = 254
Diameter is 18 inches
18” circle = 254 inches
20” circle = 314 inches
24” circle = 452 inches
Radius is 9 inches
Thus 20” diameter is not close to 20” square.
314” vs 400” – you need a 24 inch bored hole
86
Anchorage
After blocking and leveling, the manufactured
home must be secured against the wind by an
anchoring system
Anchoring equipment means ties, straps, cables,
turnbuckles, chains and other approved
components including tensioning devices that are
used to secure a manufactured home to anchor
assemblies.
Conventional anchors or alternative foundation
system (Tie Down or Oliver Technologies type
systems)
87
Tie Downs
Maximum spacing – see
the tables
See drawings for near
beam and second beam
methods
If sidewall or over the
roof, mate-line or shear
wall straps are installed,
they must be connected
Must be augured at least
30 inches unless the
foundation is a frost
protected above frost
line system
88
Tie Down Straps
1 ¼ inch by 0.035 in or larger steel
strapping conforming to ASTM D 395397 standard
Capable to resist a min ultimate load of
4750 lb and a working load of 3150 lbs
(check listing labels) – Same capacity
as the anchors
Coated with zinc to not less than 0.30
oz/ft2 of surface
89
Tie Down Tips
No long tails
Tension evenly or you might pull the
home off the supports
Determine if stabilizer plate is needed
– See anchor manufacturer
instructions
Try locking clamp version
90
Anchorage
The anchors must be capable of meeting
the loads the home was designed to
withstand – see data plate
Follow the anchor company’s instructions
for spacing, angles, connections and so
forth
Install anchors to their FULL depth
A diagonal anchor tie is intended to resist
horizontal or shear forces, but may also
resist vertical, uplift and overturning
forces
3285.401
91
Ground Anchors
Must be listed (listed means
approved)
Steel coated and weather protected.
HUD now allows either zinc coated or
painted anchors.
Capable to resist a min ultimate load
of 4750 lb and a working load of 3150
lbs (check listing labels)
92
Tie Down Engineering
Vector System
Several companies have alternative systems that work without anchors
93
Vector System with
Longitudinal Support
94
Note base plate and longitudinal support
Tie Down Safety Issues
Locate Utilities
abandoned electrical drops is a concern
utility lineman’s gloves are
recommended
Test for power on anchor before
connecting to home can be done using a
simple voltage checker
$5.25 worth of
safety
95
Image courtesy of Lab
Safety, Janesville
On-site structures
Each expansion room or other on-site
structure must be able to support its
own weight including any garage
unless pre-designed by manufacturer,
engineer or architect
Any addition must be designed by
either the home manufacturer, a
registered engineer or architect
96
Did the manufacturer approve this addition?
97
Optional Equipment
Comfort systems (HVAC) must be installed
by a licensed HVAC contractor if not factory
installed
Air conditioning equipment must be
properly sized
All heat producing equipment must be
properly vented thru the skirting or exterior
wall as appropriate
When not installed by home manufacturer,
must be installed according to the appliance
manufacturer’s instructions
98
Skirting
Must be weather resistant
Attached so no water is trapped
between siding and trim or forced
up into the wall cavity trim
All wood skirting within 6 inches of
the ground must be pressure
treated or be naturally resistant to
decay and termites – This would
include lumber and sheathing
extension if any of the wood is less
than 6 inches above the ground
99
100
Crawlspace Venting
NEW - One square foot for every 1,500 sq
ft of floor area – Important – Check with
your manufacturer before proceeding with
reduced venting
Vent openings as high as practicable
Vents must located on at least two opposite
sides of home
Openings must be covered with a
perforated corrosion and weather resistant
covering to prevent rodent entry
101
Front OK
102
103
104
Which vent panel permits the
most free air to pass through?
105
The Answer is A
This panel has a large number of
openings which although they are
small allows more air to pass than the
other panels which have much more
hard surface area. Panels are rated,
see the back of any panel you buy to
know what you are getting.
106
Access Openings MUST:
Not less than 18 wide by 24 high and
not less than 3 sq ft
Must be located so that any utility
connections under the home are
accessible
107
3285.505
108
Dryer vents, air conditioning, &
combustion air vents
Must pass through skirting to the
outside
This includes fireplace air inlets
Air conditioner equipment not
installed by the manufacturer must
be done by a person holding an HVAC
license!
109
Ductwork, Plumbing & Fuel
Supplies
Manufacturer must supply
instructions for proper field assembly
110
Water
When local water supply pressure exceeds
80 psi, a pressure reducing value must be
installed
An identified and accessible shutoff value
must be installed underneath or adjacent
to the home
Crossovers and lines must be protected
from freezing
Only listed MH heat tape is permitted
Water system must be inspected and
tested for leaks after completion at the
site.
Disconnect water heater if test is air only
111
Piping support
Water lines supported every 3 feet
Drain lines supported every 4 feet –
See 48 inch on center max 3280.608
112
Gas Supply
Home design calls for system
pressure of 10 to 14 inches of
water column pressure (0.036
psi)
113
Ductwork Crossovers
All ductwork connections must be
sealed
Galvanized metal straps or tape and
mastics listed to UL 181 A or B must
be used around duct collar and
secured tightly
Metal straps require metal sheet
screws
Fasten with at least 3 galvanized sheet
metal screws equally spaced around the
collar
114
Ductwork
Max distance for duct supports is 4 feet
If straps are used they must be ½” wider than
spacing of spirals in flex duct
Arrange so that straps cannot slip between
spirals and to prevent kinking
Ducts cannot contact ground
Listed for exterior use only
115
Ductwork
Crossovers outside the envelop must be
insulated with proper materials
In-floor or ceiling crossover connections
must be sealed to prevent air leakage
116
Subpart H - Electrical
Snap connections may or must be
fastened to adjacent stud – CHECK
instructions
If a fixture is mounted on a
combustible surface a limited
combustible or non-combustible ring
must be installed
Wires connected black to black, white
to white and ground to ground
Test all connections
117
Smoke Alarms
Additional shipped loose alarms for
basement set models are typically
provided by the manufacturer
They may be wired to communicate
with factory installed units at main
floor
A separate WI law also requires
carbon monoxide detectors
118
Exterior close-up
Manufacturers provide instructions for
joining sections. Pay particular
attention to directions on fasteners
The mate-line gasket must be
installed following manufacturer
instructions
Exterior close up strips are trim that
must be fastened securely and sealed
with an exterior sealant
119
Before Sections are Secured
The poly sheeting used for transport
must be removed completely
120
Hinged roofs and eaves
May be
subject to
alternative
construction
inspections if
flue
penetrations
are above the
hinge
No Seal!
121
Gaps
UPON COMPLETION – no gaps are
permitted between structural elements
PRIOR TO COMPLETION – minor gaps not
exceeding one inch are permitted
PROVIDED they are filed upon completion
122
Gaps
Fill gaps must be shimmed with
dimensional lumber and fastener lengths
used to make connections must be
increased to provide adequate penetration
into receiving lumber.
Pay particular attention to end wall and
floor completion gaps – May have
marriage wall sheathing in from end wall
ends
123
Close up
All shipping blocking, strapping or
bracing must be removed from
appliances, window and doors.
At a minimum, shipped loose wall
panels must be installed using PVA
adhesive on all framing members and
fastened with 1 inch long staples or
nails 6 inch on center panel edges and
12 inches on center in the field unless
manufacturer directs other methods
124
Bottom Board
Bottom Board is an industry term for
barrier installed by the factory on the
bottom of the floor system. It is for rodent
control.
Inspect for loosing or areas damaged by
transport or installation
Tears must be repaired
125
Bottom Board
Any missing insulation must be
replaced
Splits or tears must be resealed with
tape or patches
P traps must be checked to be sure
they are well insulated and covered
All repaired edges must be taped or
otherwise sealed
126
Other UDC Issues to Watch
Site constructed elements subject to
UDC
Basement stairs
Exterior decks, stairs and railings
Garage attachments
Habitable basements
Egress windows for bedrooms
Heating calculations for entire envelop
127
Trouble spots-Basement Stairs
Maintain 6'-4" Headroom In
Required 3' Long Landing
Finished Stairwell Length (FSL)
Floor/Ceiling
Depth
Headroom
(Min. 6'-4")
Two Similar
Right
Triangles
Maintain
6'-4"
Headroo
m In
Required
3' Long
Landing
Headroom + Floor/Ceiling Depth (HFCD)
Unit Rise
So to solve for FSL, FSL = Unit Run x HFCD
Unit Rise
Unit Rise
Max. 8"
Unit Run
Min. 9"
Finished Stairwell Length(FSL)
Unit Run
128
End
Return to MH Installer Course Click
here
129