Transcript Slide 1

15mgd Membrane Bioreactor Plant & Replacement of Aged Equipment at Jurong Water Reclamation Plant

Project Consultant

• Black & Veatch (SEA) Pte Ltd 

Project Status

• Tender for the MBR plant called on 5 Sep 2008 and will close on 13 Nov 2008 • Tender for the replacement of M&E equipment to be called in 4 th Quarter 2008 

Scope of Works

• To build a 15mgd MBR plant at the existing 45mgd Jurong WRP to produce more IW to meet demand.

• To replace M&E equipment associated with liquid and gas stream including upgrading the aeration system.

1