Extension of Industrial Water Network to Jurong Island
1
Extension of Industrial Water Network to Jurong Island
Objective

This project is to extend the industrial water (IW) network
from the Jurong Water Reclamation Plant (JWRP) to
Jurong Island, to meet the increasing demand of
industries on the Island.
Scope


Modification of existing pipelines
Supply and lay 12km 900mm dia. IW transmission pipeline
Project Schedule


Calling of Tenders
: 3rd Quarter 2009
Scheduled Completion : Mar 2011