ERGEG Electricity Regional
Initiatives Status Review
José Sierra, RIG Chair
Rafael Gómez-Elvira (RIG Chair Team)
XIX Florence Forum
14 December 2010
List of contents
• PART 1: The ERGEG ERI Status review
•
•
•
•
The RIs Status Review
The RIs under the new context of the Third Package
FGs & NCs: Pathways to take for regional projects
Future interaction between RIs and the FG process
• PART 2: Progress at a glance from the perspective
of the draft FGs on CACM
• Capacity Calculation
• Long-term
• Day-Ahead
• Intraday
XIX Florence Forum, 14 December 2010
2
1. The ERGEG ERI Status Review
The RIs Status Review
• Published on 10 November 2010
• Contributions from ERI & GRI TFs
• Progress achieved in the regions
since November 2009
• Analysis per region and per topic
• First time - Case studies & policy
advice from regions’ experiences
XIX Florence Forum, 14 December 2010
3
1. The ERGEG ERI Status Review
The RIs under the new context of the Third Package
• RIs have an important role to play in:
• Encouraging progress on the ground
• Informing the development of the cross-border
regulatory framework
• Encouraging early implementation of draft FGs &
NCs where this is practicable
• RIs organised to facilitate necessary co-ordination of
key actors.
XIX Florence Forum, 14 December 2010
4
1. The ERGEG ERI Status Review
FGs & NCs: Pathways to take for regional projects
• After years of voluntary progress, the time to
implement is coming with the existing platform.
• FGs & NCs - the more defined they are the more
regional progress will happen. Feedback to ACER.
• The FGs on CACM are setting the framework to
converge within and among regions.
• Regions have to move towards the target model
(capacity calculation, LT, Day-Ahead, Intraday)
XIX Florence Forum, 14 December 2010
5
2. The ERGEG ERI:
Progress at a glance from the perspective
of the draft FG CACM
Capacity calculation
A harmonised and more coordinated methodology for
capacity calculation based on physical network reality
• CSE & NE already applies a common transmission
network model (ATC)
• CWE and CEE regions: ongoing projects for flowbased capacity calculation
ERGEG encourages enhanced coordination at European
level
XIX Florence Forum, 14 December 2010
6
2. The ERGEG ERI:
Progress at a glance from the perspective
of the draft FG CACM
Long-term
A common allocation platform with common allocation rules
• CSE region and northern borders of Switzerland:
extension of CASC-CWE platform beginning of 2011.
Rules harmonisation between the two regions on
schedule.
• CEE region: implementation of CAO with common
allocation rules beginning of 2011.
• FUI region: ongoing projects for coordinated regional
allocation (platform)
• SW region: a pending election (interaction with MIBEL)
 ERGEG welcomes progress made at cross-regional level
XIX Florence Forum, 14 December 2010
7
2. The ERGEG ERI:
Progress at a glance from the perspective
of the draft FG CACM
Day-ahead
One single Price Coupling all over Europe
• From ITVC to price coupling in CWE-NE
• Price coupling Italy-Slovenia (CSE)
• Price coupling MIBEL-CWE (SW)
• Price coupling Britned-CWE in 2011 + IFA in 2012
(FUI)
• Price coupling NE-Estonia:
 ERGEG encourages coordination of all the ongoing
projects and a strong co-operation between PXs and
TSOs to implement a pan-European price coupling
XIX Florence Forum, 14 December 2010
8
2. The ERGEG ERI:
Progress at a glance from the perspective
of the draft FG CACM
Intraday
Implicit continuous & auctions if sufficient liquidity
• Implementation of an open intraday continuous
trading between France and Germany
• Ongoing NWE ID project between GB, CWE and
Nordic regions
• SW: ongoing improvement of intraday model in
regional interconnections
• FUI: ongoing SEM introduction of intraday trading
• NE-Baltic: continuous implicit allocation to Estonia
ERGEG encourages development of projects at regional
level
XIX Florence Forum, 14 December 2010
9
Thank you for your attention!