WESTRIDGE ELEMENTARY SCHOOL CLASSROOM AND …

Download Report

Transcript WESTRIDGE ELEMENTARY SCHOOL CLASSROOM AND …

PRINCE WILLIAM COUNTY PUBLIC
SCHOOLS
SCHOOL DIVISION WIDE ENROLLMENT FORECAST
CURRENT SCHOOL CAPACITY
568 Students
FORECAST ENROLLMENT
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
School
School
School
School
School
School
School
School
School
School
School
School
Year
Year
Year
Year
Year
Year
Year
Year
Year
Year
Year
Year
DEFICIT
594
662
667
679
681
684
685
686
686
685
685
686
Students
Students
Students
Students
Students
Students
Students
Students
Students
Students
Students
Students
26 Students
94 Students
99 Students
111 Students
113 Students
116 Students
117 Students
118 Students
118 Students
117 Students
117 Students
118 Students
DESIGN PROGRAMMING REQUIREMENTS

SIX CLASSROOM ADDITION (net - based on 24 students per room)
• New classrooms must be prioritized based on the needs of the
youngest grade level first per State Department of Education
Standards

PROVIDE SECURE ENTRANCE (to control school access after
students arrive)

PROVIDE CLINIC SPACE WITH OPERABLE WINDOW TO THE OUTSIDE

PROVIDE 2000 SQUARE FOOT ACTIVITIES ROOM (to supplement
existing Multipurpose Room)
PRELIMINARY PROJECT SCHEDULE

Mid April 2009
Meet with Principal to review project
scope and conceptual plans











Mid April thru May 2009
Meet with school principal and staff, as
necessary, to develop a
proposed addition plan
that will support the instructional needs of
the
school
Late May 2009
Invite community to school PTO meeting
to review proposed project
schematic plans and
invite comments
June thru Sept 2009 A/E to develop design documents
Early Oct 2009
Submit building plans for PW County for
review and approval
Mid Dec 2009
Anticipate plan approvals
Feb 2010
Advertise for Bids
Late March 2010
School Board awards construction
contract
April thru Nov 2010 Additions constructed
Winter Break 2010
Move into new additions
Jan thru April 2011 Renovate existing classrooms with changed use
Late May 2011
Begin use of renovated existing